Resolved
RESOLVED that a report summarising the findings of the Play Facilities Working Group be submitted to the Cabinet.
Overview and Scrutiny Panel (Social Well-Being) decided this item on Tuesday 2 February 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that a report summarising the findings of the Play Facilities Working Group be submitted to the Cabinet.
OVERVIEW AND SCRUTINY 2ND FEBRUARY 2010 PANEL (SOCIAL WELL-BEING)
REPORT OF THE PLAY FACILITIES WORKING GROUP
1. INTRODUCTION
1.1The Play Facilities Working Group met on 16th December 2009 when Councillor P G Mitchell was present.
1.2Apologies for absence from the meeting were submitted on behalf of Councillors [name removed] and R J West.
1.3In attendance were Councillor C R Hyams, Executive Councillor for Operational and Countryside Services.
1.4Also in attendance were [name removed], Democratic Services Officer, [name removed], Service Development Manager and [name removed], Scrutiny and Review Manager.
1.5Councillor P G Mitchell declared a personal interest in the study owing to his involvement with the Stilton Skate Park Project.
2. THE WORKING GROUP’S REMIT
2.1Following detailed discussion it has been decided that the Working Group should focus on “outdoor youth activity facilities”, which essentially are skateboard ramps and multi-use games areas.
3. WORKING GROUP DISCUSSIONS
3.1With regard to insurance of facilities, Councillor P G Mitchell has requested that investigations are carried out into whether the District Council could co- ordinate insurance for Parishes wishing to insure their facilities under a group scheme. The idea being that the Parishes would achieve a lower premium. Officers were, therefore, tasked with investigating this matter with the Council’s Insurance and Risk Officer.
3.2Having received and considered data on the cost of maintaining facilities, Councillor Mitchell has requested further information as follows:-
• the cost to the Council of ROSPA inspections; • the cost of inspecting facilities; • the cost of maintaining facilities in terms of repair and replacement; and • the cost of the service’s overheads.
3.3[name removed] reported that the District Council currently contributes towards the cost of four skateboard ramps as follows:-
• St Neots – owned, inspected and maintained by the District Council; • Yaxley – inspected by the District Council; • Somersham – inspected by the District Council; and • St Ives – owned, inspected and maintained by the District Council.
A request was made for the costs associated with these facilities to be made available to Members.
3.4In discussing the way forward, two alternative approaches were considered, both offering a 40-40-20% split in revenue costs between the District Council, Town/Parish Council and users of the facilities respectively. Both Options aimed to encourage the provision of outdoor youth activity facilities in rural areas. The two options are:-
Option 1
A fully costed service provided by the District Council’s Operations Division, which would be offered to all Parishes. Only one facility per year would be added to the Operations Division’s programme. Skateboard ramps and multi- use games areas would be the only types of facilities that would qualify under the scheme. It was, however, acknowledged that at some point there would be a need for more resources, both financial and operational.
Option 2
The District Council would offer funding to Parishes to assist with their facilities’ revenue costs. The expectation is that the offer would only be made available in rural areas. Parishes that either already have an established facility or those that might wish to erect a facility within their Parish in the future would be eligible.
3.5Councillor P G Mitchell expressed his support, in principle, for Option 2. It was acknowledged that, subject to the agreement of the Overview and Scrutiny Panel (Social Well-Being), both options would require a Medium Term Plan bid to be submitted to the Cabinet.
Councillor P G Mitchell
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PLAY FACILITIES WORKING GROUPReport | 28 KB | DownloadRead as text |
Follow Overview and Scrutiny Panel (Social Well-Being) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2015 | Urgent item - cambridgeshire county council health committeeRESOLVED a) that Councillor D Brown be appointed to the Cambridgeshire County Council Health Committee for the ensuin... | Decided | Open |
| 3 Nov 2015 | Overview and scrutiny panel structureRESOLVED to a) endorse Option 2 as a new structure for Overview and Scrutiny panels, b) request that amendments to th... | Approved | Open |
| 3 Nov 2015 | Overview and scrutiny progressDecision Digest The 159th Edition of the Decision Digest was received by the Panel. In so doing, the Panel, RESOLVED ... | Decided | Open |
| 7 Jul 2015 | Exclusion of the publicRESOLVED That the public be excluded from the meeting because the business to be transacted related to any action tak... | Decided | Open |
| 7 Jul 2015 | Re-admittance of the publicRESOLVED That the public be re-admitted to the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.