Resolved
RESOLVED that the Audit and Assurance Plan be approved.
Corporate Governance Panel approved this item on Wednesday 30 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Assurance Plan be approved.
CORPORATE GOVERNANCE PANEL 30 JUNE 2010
INTERNAL AUDIT SERVICE: INTERNAL AUDIT PLAN (Report by the Audit & Risk Manager)
1. PURPOSE
1.1To allow the Panel to comment on the internal audit plan for the 12 month period commencing August 2010 before it is finalised. The plan is attached.
2. STRATEGIC AND ANNUAL PLANNING
2.1The Audit and Risk Manager is required, by the 2006 CIPFA Code of Practice for Internal Audit, to provide an opinion on the overall adequacy and effectiveness of the Council’s control environment. The annual audit plan provides the majority of the information for his assessment to be made. This opinion is a key element that the Chief Executive and the Panel will consider when they are reviewing elements of the assurance framework and preparing the Council’s annual assurance statement.
2.2The Internal Audit Service maintains a four year strategic audit plan, listing all the risk and system areas that are considered likely to affect the Council’s internal control environment. The strategic plan shows the relative importance of each risk and system area and the frequency with which it should be audited. Risks recorded in the risk register have been included in the strategic plan. This has led to a number of audit areas being combined so that audits can address common risk themes across services, rather than be conducted on a service by service basis.
2.3To prepare the annual audit plan, the strategic plan is first reviewed and audits placed in priority order. The highest priority schemes which can be delivered within the resources available are then included in the annual audit plan which, following the comments of this Panel, will be determined by the Director of Commerce and Technology as the Council’s chief financial officer.
3 RESOURCING THE AUDIT PLAN
3.1The Internal Audit structure included the Audit and Risk Manager and 3 full time equivalents (FTE) of auditors. The main elements of their work are the delivery of the annual audit plan, provision of a wide range of advice and assistance to staff across the Council and undertaking fraud and whistleblowing investigations.
3.2One of the auditors has retired and another has reduced from full time to half time following maternity. Given the Council’s financial position the opportunity was taken to consider whether the post needed to be filled. It was decided that 0.5 FTE could be given up as a minimum and potentially 0.7 FTE dependent upon the expectations of the Council’s new external auditors and accordingly a 0.8FTE auditor could be appointed. This proposal was made to the Employment Panel and approved in May. (Copy of proposal attached at Annex C)
3.3Since that time discussion has been ongoing with Heads of Service and Directors on the audit programme for next year and it has been possible to remove or defer a small number of audits. 3.4 More significantly, further consideration has been given to the following options:
• The decision as to which areas do not need audit at all is clearly subjective and it would be possible to delete some of the lowest risk audits from the strategic plan. The audits that could be removed are shown in Annex B along with a brief explanation. • It would be possible to focus each audit on the most significant aspects and omit consideration of items that were marginal risks. • The remaining planned audits could be supplemented by a ‘light touch’ self assessment scheme. This would require Managers to complete a check list where significant service, system or personnel changes had occurred. The results would lead to some specific simplified audits thus mitigating the impact of the two options above and providing some level of assurance.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT SERVICE: INTERNAL AUDIT PLANReport | 28 KB | DownloadRead as text |
PDF |
Internal Audit Service Internal Audit Plan AppendixAppendix | 86 KB | Download |
PDF |
Internal Audit Service Internal Audit Plan Appendix BAppendix | 21 KB | Download |
PDF |
Internal Audit Service Internal Audit Plan Appendix CAppendix | 19 KB | Download |
Follow Corporate Governance Panel at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Mar 2016 | Appointment of vice-chairmanRESOLVED that Councillor T Alban be appointed as the Vice-Chairman of the Corporate Governance Panel for the remainde... | Decided | Open |
| 9 Mar 2016 | External audit plan 2015/16RESOLVED that the Panel notes the content of the revised External Audit Plan for 2015/16 and agrees with the level of... | Agreed | Open |
| 9 Mar 2016 | Grant certification 2014/15RESOLVED that the Panel note the content of the External Auditor’s Annual Certification Report 2014/15. | Noted | Open |
| 9 Mar 2016 | Internal audit service: internal audit plan 2016-17RESOLVED to approve the Internal Audit Plan for 2016/17. | Approved | Open |
| 9 Mar 2016 | Accounting policies for the annual financial report 2015/16RESOLVED to approve the amendments to the accounting policies for the Annual Financial Report 2015/16 as listed in Ap... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.