Overview and Scrutiny Panel (Environmental Well-Being) decided this item on Tuesday 12 October 2010. Below is the council's own wording, with the papers it was decided on.
RESOLVED a) that an ad hoc local drainage liaison group be established comprising the Chairman and relevant Ward Members in an attempt to resolve local drainage issues; and b) that the group be invited to address the issues of flooding in the St Audrey’s Lane area of St Ives in the first instance.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Environmental Well-Being)
Flooding in St. Ives - Overview
1. INTRODUCTION
1.1In July 2008 Anglian Water’s Customer Service Manager and Collection Manager attended a meeting of the Overview and Scrutiny (Service Support) Panel to discuss the problems being encountered by residents of St. Audrey’s Lane, Warren Road and Pig Lane in St. Ives arising from flooding of the foul sewerage system. The matter had been brought to the attention of the Panel by way of a petition signed by 26 people and presented to its meeting in February 2008. The minutes of the meeting are attached (Appendix A) with Anglian Water representatives agreeing to give an update to the Panel in six months.
2. OVERVIEW
2.1In October 2008 an update from Anglian Water stated that a CCTV survey of St. Audrey’s Lane and Pig Lane surface water sewer had been completed and funding was available to jet the sewer.
2.2In February 2009 the Panel was made aware of further problems experienced in inclement weather and sought a further update from Anglian Water.
2.3In July 2009 Anglian Water’s Customer Response Manager was invited to attend a future meeting to discuss progress since their previous attendance. An update was received stating that Anglian Water had been working on the pumping regime and surface water sewers. Jetting of the Pig Lane surface water had been carried out during the previous autumn, although access to the sewer had been difficult as further down its length it had been laid through back gardens. The sewer took a dog leg turn around a mature tree, at which point the sewer was blocked. Anglian Water was unable to clear this blockage and were considering how to proceed. Optimisation of the pumping regime was ongoing.
2.4A significant change had been made at Broadleas Pumping Station in February 2009 which was working well and Anglian Water were confident that this would enhance throughput which they hoped would improve the situation during heavy rainfall. Anglian Water at that time were unable to progress the work on the surface water sewer as they had been unable to clear the blockage. The sewer had difficult access and it was felt that this probably needed to be re-laid which the company didn’t have the funds to pursue at the time. A new Collection Manager had been appointed and he declined an invitation to attend a Panel meeting, although he did request a list of questions from Members. A copy of the questions and corresponding answers is attached as Appendix B.
2.5In June 2010 Councillor Davies wrote to Anglian Water’s Customer Response Manager updating her on the ongoing problem of sewer surcharging in St. Audrey’s Lane and Pig Lane which was related to surface water matters. Councillor Davies also raised concerns about the ongoing developments in the west of St. Ives and the effect that this was likely to have on the terminal pumping station. Anglian Water’s response suggested that the outstanding issues were still in hand and were anticipated to be completed by the end of summer. The letter explained that growth in St. Ives would be managed by Anglian Water’s Planning and Equivalence Team in conjunction with the Asset Planning Team which would review the local infrastructure and arrange for appropriate reinforcement to occur prior to development being completed. However Anglian Water indicated that the company could only react to growth that it was aware of and it was not a statutory consultee within the planning process. All operation data available to Anglian Water suggested that the pumping station on Broadleas was adequately sized to manage normal flows. Capacity at the station would be fully reviewed in light of any proposed development in the area and if it were believed that the station would not be able to adequately manage any proposed increase in flow, Anglian Water would invest in the Pumping Station accordingly. The proactive jetting plans within the area were being reviewed and frequencies would be adjusted in accordance with issues identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Environmental Well-Being) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Overview and scrutiny panel structureRESOLVED a) that Option 2 as detailed in the report now submitted be endorsed as a new structure for the Overview and...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.