PUBLIC RIGHT OF WAY: PART OF PUBLIC FOOTPATH NO. 9 HUNTINGDON, TOWN AND COUNTRY PLANNING ACT 1990 (SECTION 257)
DecidedCommittee1 paper
Development Management Panel (Decommissioned 18/05/2016) decided this item on Monday 18 July 2011. Below is the council's own wording, with the papers it was decided on.
RESOLVED that an Order be made under Section 257 of the Town and Country Planning Act 1990, for the stopping-up of part of Public Footpath No. 9 in Huntingdon upon the granting of planning permission for application No. 10/01750/FUL. [In his introduction, the Planning Service Manager (Development Management) explained the reason why the Order was required, why it had been proposed to stop-up the whole length between points A and B, the benefits of the alternative route to be provided, the responses received to the pre order consultation and the decision making process following the making of the Order.]
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Management Panel (Decommissioned 18/05/2016)
Purpose of report
1.1To seek approval for the making of an order for the extinguishment of part of Public Footpath No9, Huntingdon.
Background
2.1Public Footpath No9, Huntingdon is an urban, hard surfaced footpath which runs in a generally northerly direction from Brampton Road, through part of the RECO industrial site and then continues along Ferrars Road in a generally north easterly direction where it terminates.
2.2As the panel will be aware the Council has resolved to grant planning permission (1001750FUL) for the erection of new food store, petrol filing station, provision of a new street comprising of 9 retail units, 13 residential units, office floor space and associated car parking. That permission will be issued subject to the satisfactory completion of the related Section 106 and other agreements.
2.3The definitive route of Public Footpath No9 cuts across part of this development site and would be obstructed by parts of the development if not extinguished prior to implementation of the planning permission.
3. The Proposal
3.1The proposal is to stop up that part of the public footpath between points A-B on the Order Plan.
4. Issues
4.1The stopping up order is required to enable the anticipated development to be carried out.
4.2Cambridgeshire County Council’s Huntingdon West of Town Centre Link Road Side Road Order 2011 includes the provision of a new footway which will allow pedestrian access previously available by the path to be extinguished (between points A and B on the order plan). For this reason it is not necessary to include the provision of an alternative highway in this extinguishment order.
4.3Huntingdonshire District Council will certify the extinguishment as coming in to operation, only when both District and County Council are satisfied that all work to provide an alternative route has been carried out. This will assure the provision of the new route before the existing public footpath is formally extinguished. 4.4 It is recognised that Public Footpath No9 Huntingdon is an important pedestrian link to and from Huntingdon Railway Station. The provision of a suitable temporary route while construction work is carried out is outside the scope of the extinguishment order. However it is expected that such a suitable temporary route will be provided by agreement between Cambridgeshire County Council and the applicant.
4.5There is a private pedestrian access onto Public Footpath No9 for the use of residents in Roscrea Court. Provision will also be made to allow the residents access to the new footway from the existing private access.
4.6The applicant has agreed to meet the District Council’s legal and advertising costs.
4.7This planning authority is satisfied that this extinguishment order meets the necessary criteria as set out in Section 257 of the Town & Country Planning Act 1990.
5. Pre-order consultations
5.1Cambridgeshire County Council. No objection in principle but have made comments regarding maintaining a pedestrian link during construction work.
5.2Local group of the Ramblers Association. No objection anticipated providing that there is provision for a satisfactory alternative route to Footpath No9. The local group also wish consideration given to the adequate width and lighting of the new path as well as safe crossing points for pedestrians. The footpath is regularly used as a pedestrian route to and from the railway station and a suitable temporary footpath should be provided during construction.
5.3Huntingdon Town Council. No objection to the stopping up of the footpath but should not be stopped up until construction of the new road has started and suitable arrangements would need to be in place for users of the path while construction is taking place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Management Panel (Decommissioned 18/05/2016) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.