Overview and Scrutiny Panel (Environmental Well-Being) approved this item on Wednesday 12 October 2011. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Cabinet be recommended to: a) approve the retention of the St Ives Green House until March 2014 and the rental of the St Neots property (Option 2) with the additional revenue costs being met from the existing Environmental Projects revenue budget; b) support the development of the project to be the main mechanism for the Council to deliver Government’s Green Deal initiative in conjunction with project partners, and c) receive an update on the progress of the project in October 2012.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Environmental Well-Being)
Background
2.1The UK Government is committed to reducing carbon emissions by 80% by 2050. Home energy use in the UK is currently responsible for around 30% of all emissions and this is the largest single area that the council can significantly influence.
2.2Prior to refurbishment the Green House properties received a SAP (Standard Assessment Procedure for energy efficiency) rating of ‘E’. The ratings of both properties were increased to a ‘B’ following completion of the work. Carbon emissions for both houses have been reduced by 75%. The fuel costs for St Ives have been reduced by £633 a year and St Neots by £478.
2.3In addition to assisting householders cut their fuel bills the established Green House ‘brand’ developed through the project will enable the council to lead a local economic transformation in the construction/business sector and is already seen nationally as a case study of best practice in this area (See ANNEXE C attached).
Financial implications
3.1This section outlines three possible options for the future of the Green House properties, the first of which is for the sale of both properties in line with the current Medium Term Plan and two further options to enable the retention of the St Ives Green House as a showcase property until the end of the financial year 2013/14. 3.2 The three options are outlined in detail (ANNEXE D attached) and the table below summarises the financial impact of the three options with the variation in each case from the current MTP:
EXISTING MTP – Sale Impact Only 2011/12 2012/13 2013/14 2014/15 TOTAL £000 £000 £000 £000 £000 CAPITAL -470 -470
REVENUE Reduction in borrowing costs -18 -21 -26 -65 Net running costs 0 0 0 0 Total -18 -21 -26 -65
Opt. 1 - SELL BOTH NOW 2011/12 2012/13 2013/14 2014/15 TOTAL £000 £000 £000 £000 £000 CAPITAL -415 -415
REVENUE Reduction in borrowing costs -16 -19 -23 -58 Net running costs Total -16 -19 -23 -58
VARIATION TO MTP Capital 55 55 Revenue 2 2 3 7
Opt. 2 - KEEP BOTH 2 YEARS 2011/12 2012/13 2013/14 2014/15 TOTAL Renting St Neots £000 £000 £000 £000 £000 CAPITAL -415 -415
REVENUE Reduction in borrowing costs 0 0 -23 -23 Net running costs 1 1 0 2 Total 1 1 -23 -21
VARIATION TO MTP Capital 470 0 -415 0 55 Revenue 19 22 3 44
Opt. 3 - KEEP ST IVES 2 YEARS 2011/12 2012/13 2013/14 2014/15 TOTAL Sell St Neots now £000 £000 £000 £000 £000 CAPITAL -170 -245 -415
REVENUE Reduction in borrowing costs -7 -8 --23 -38 Net running costs 8 8 16 Total 1 0 -23 -22
VARIATION TO MTP Capital 300 0 --245 0 55 Revenue 19 21 3 43
3.3If both properties are sold now (Option 1) the Council will have to meet the modest (7k) revenue impact of the lower estimated sale proceeds. In addition as promoting energy efficiency is a key objective within the Council’s Corporate Plan and a requirement for the Council under the Energy Bill 2010, the sale of the Green Houses, will compromise the Council’s ability to deliver against this agenda and in particular the scope for promoting the Green Deal locally.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Environmental Well-Being) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Overview and scrutiny panel structureRESOLVED a) that Option 2 as detailed in the report now submitted be endorsed as a new structure for the Overview and...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.