Resolved
RESOLVED (a) that the report now submitted be noted; and (b) that the objectives identified for the Enforcement Service during 2013 be endorsed.
Development Management Panel (Decommissioned 18/05/2016) noted this item on Monday 25 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (a) that the report now submitted be noted; and (b) that the objectives identified for the Enforcement Service during 2013 be endorsed.
1.1The main purposes of this report are to update Members on enforcement activity during 2012, to report back on the priorities which were identified for last year and to outline the proposed priorities for 2013.
2. ENFORCEMENT TEAM STRUCTURE
2.1The composition of the enforcement team remained unchanged last year. The team consists of the Team Leader, two full time area Enforcement Officers and a part-time (15 hours a week) team support officer.
3. WORKLOADS AND PERFORMANCE
3.1The target in the Development Management Service Plan is that an initial site visit should be made within 10 workings days of receipt of a complaint. The performance in the last four years has been:
2009 2010 2011 2012 Total number of cases 443 330 337 300 Number of initial site 300 290 320 287 visits recorded Percentage of recorded 75% 70% 92% 95% site visits carried out in 10 working days
3.2Considerable importance continues to be attached to making initial visits as soon as possible after a complaint is made. This enables an early assessment of the nature of the breach, which is not always that reported by the complainant, its severity and early discussion at Enforcement Forum so that an initial course of action can be agreed. Where the allegation is of immediate harm, for example to a heritage asset such as a listed building, demolition of a conservation area building or work to protected trees, site visits are made urgently.
3.3At the beginning of 2011 there were 428 cases on hand. By the end of 2011 this had risen 20% to 512 cases and by the end of 2012 it had risen a further 17% to 597. There were 300 new cases in 2012, a reduction of 11% on the previous year. This number is more in line with the average for the previous 10 years of 327 cases. The number of cases closed was 208, down from 240 in 2011 and 321 in 2010.
3.4Cases vary considerably in complexity and in the work necessary to bring about a satisfactory outcome and these factors have as much influence on workload as the number. As the following table shows, the types of complaint received have been fairly consistent over time. Nature of complaint 2009 2010 2011 2012 Creation of access 6 1 4 5 Advertisements 14 23 23 14 Commercial 6 5 6 6 outbuildings Domestic outbuildings 24 25 14 18 Breach of planning 116 22 42 31 conditions Caravans 25 11 13 7 Commercial extension 1 1 2 6 Domestic extension 20 24 8 22 Means of enclosure 26 17 22 26 Engineering operations 47 25 25 14 Houses in multiple 0 1 2 2 occupation Listed building and 19 12 20 20 conservation areas Other breach of 1 2 6 18 planning control Development not in 28 14 30 25 accordance with approved plans Untidy land 20 13 16 14 Satellite dishes and 9 9 6 1 aerials Work to protected trees 0 1 4 2 Changes of use – 0 6 12 7 agriculture Changes of use – 21 17 21 17 commercial Business operation 41 47 47 24 from home Residential uses 19 54 14 21 Total 443 330 337 300
3.5The reasons for closure over the last four years have also been fairly consistent. Serious breaches are a small but important percentage.
Reason for closure 2009 2010 2011 2012 Minor amendment 1 0 0 1 approved Planning permission 22 27 27 23 granted De minimis (trivial) 14 7 6 4 Formal enforcement 6 3 1 1 action Lawful development 21 15 9 8 Further action not 60 94 38 45 expedient Not development 77 83 72 48 Permitted development 32 20 13 21 Remedied voluntarily 60 71 70 41 Other 0 0 4 16 Total of closed cases 293 321 240 208
2 4. REVIEW OF 2012
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SUMMARY OF ENFORCEMENT ACTIVITY FOR 2012Report | 47 KB | DownloadRead as text |
Follow Development Management Panel (Decommissioned 18/05/2016) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.