Grant Certification 2012/13

Noted Committee 2 papers

Corporate Governance Panel noted this item on Wednesday 14 May 2014. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

RESOLVED (a) that the grant specification report for 2012/13 be received and noted; and (b) that the Accountancy Manager be requested to write to the Local Government Association to express the Panel’s concerns over the cost to the authority of auditing benefit claims and requesting that the criteria for taking a second sample be adjusted to only require this if the errors in the previous round of sampling are material.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Corporate Governance Panel

Executive summary

For 2012/13, the Council received central government grant in two main areas; National Non-Domestic Rates and Housing & Council Tax Benefits.

Part of the control framework for such grants is that they are subject to external audit and the Councils auditors, PricewaterhouseCoopers undertake this work. As part of the auditors reporting requirements, they are required to issue an Annual Certification Report to those charged with governance, a copy is attached as Annex A.

In respect of National Non-Domestic Rates, no issues were reported. However, in respect of Housing & Council Tax Benefits some minor errors were identified which has meant that additional testing was required. The consequential impact of this additional testing is an increase in the original fee by £8,400.

Recommendation(s): It is recommended that the Panel notes the Auditor’s report. 1. PURPOSE

1.1To report to the Panel, as those charged with governance, the conclusions and recommendations of the external audit of the 2012/13 certification audit of both the National Non-Domestic Rates and the Housing & Council Tax Benefits Scheme grant claims/returns.

Background

2.1For 2012/13, the Council received two significant blocks of grant; National Non-Domestic Rates (£54.3m) and Housing and Council Tax Benefits Scheme (£45.7m). In respect of the grant claims/returns for these funding schemes, both are subject to external audit by the Councils appointed auditor, PricewaterhouseCoopers. The findings of the audit are required to be reported to “those charged with governance”; which is the Corporate Governance Panel at the Council. The auditor’s report is attached to this report as Annex A.

3. RESULTS OF CERTIFICATION WORK

National Non-Domestic Rates

3.1No amendments were made to the National Non-Domestic Rates grant return, consequently no qualification was made.

Housing and Council Tax Benefits Scheme

3.2The testing that was performed by the Councils external auditor identified a small number of errors in respect of the Council’s compliance with the scheme regulations; these errors are noted below:

 Manual adjustments A total difference of £20.48 was found. Corrections were made in the certified subsidy claim but the auditors were not able to undertake further testing prior to the certification deadline, consequently a qualification letter was issued in late November 2013. Additional testing was undertaken during December 2013 and no further issues were found which resulted in an updated qualification letter being issued in early January 2014.

 Uprating checklist It is required that “uprating parameters” are duly actioned when they have been notified to the Council. It was noted in the November 2013 qualification letter that the Council had a number of parameter omissions.

 Classification of expenditure As a result of a system error, two errors were found where expenditure has been misclassified (totalling £40.91). Subsequent testing by the Council has shown no further errors so an adjustment was made to the Subsidy Claim in respect of the error found. The auditors made no further reporting to central government in respect of this error.

The management response in respect of these errors is noted below:

The difference between the original and final values of the Housing and Council Tax Benefits claim was an increase in subsidy due to the local authority amounting to £28,763. It is worth noting that only £61.39 of this amount (i.e. £20.48 + £40.91) related to errors identified by the audit. The remaining value was due to manual adjustments which had already been identified by the authority prior to the commencement of the audit work. Auditors were informed at the start of their work that the final claim would need to be edited to reflect the manual adjustments.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FINAL HDC Annual Certification Report 12-13Appendix 1 179 KB Download
PDF
Grant Certification 2012/13Report 288 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 8 attended
MG
Councillor Michael George Baker, MBEMember, present
ER
Councillor Eric Richard ButlerChair, present
KJ
Councillor Ken James ChurchillMember, apologies
GJ
Councillor Gregory John HarlockVice-Chair, present as substitute
RH
Councillor Roger HarrisonMember, apologies
PK
Councillor Patrick KadewereMember, present
PG
Councillor Peter Gerald MitchellMember, apologies
RJ
Councillor Richard John WestMember, present

On this subject at Huntingdonshire

Search all
  1. Grant Certification 2012/13This decision
  2. Grant certification 2017/18Noted
  3. Grant Certification 2016/17Noted
  4. Grant certification 2015/16Noted
  5. Grant certification 2014/15Noted
  6. External audit grant certification 2013/14Noted

More from Huntingdonshire Corporate Governance Panel

All decisions
MeetingDecisionOutcome
9 Mar 2016 Appointment of vice-chairmanRESOLVED that Councillor T Alban be appointed as the Vice-Chairman of the Corporate Governance Panel for the remainde... Decided Open
9 Mar 2016 External audit plan 2015/16RESOLVED that the Panel notes the content of the revised External Audit Plan for 2015/16 and agrees with the level of... Agreed Open
9 Mar 2016 Grant certification 2014/15RESOLVED that the Panel note the content of the External Auditor’s Annual Certification Report 2014/15. Noted Open
9 Mar 2016 Internal audit service: internal audit plan 2016-17RESOLVED to approve the Internal Audit Plan for 2016/17. Approved Open
9 Mar 2016 Accounting policies for the annual financial report 2015/16RESOLVED to approve the amendments to the accounting policies for the Annual Financial Report 2015/16 as listed in Ap... Approved Open