Preparing the Annual Governance Statement

Decided Committee 1 paper

Corporate Governance Panel decided this item on Wednesday 23 July 2014. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

RESOLVED that the following governance issues be recorded as being significant in the annual governance statement: · to develop the themes and aims in the Corporate Plan through service plans and performance measures; · to review partnership working including benefits/outcomes and the contribution partnerships make to the Corporate Plan; · to publicise the vision statement and strategic themes and outcomes; and · continued compliance with the Code of Procurement.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Corporate Governance Panel

Executive summary

An informal meeting of the Panel was held on 27 June at which the Council’s current position against the requirements and supporting principles of the Code of Corporate Governance were reviewed and discussed.

The meeting identified seven areas where it was felt that the Council was not sufficiently complying or in conformance with the Code. Of these, it considered the following items were significant enough to be considered for inclusion in the annual governance statement.

 The themes and aims of the Corporate Plan remained absent from service delivery plans or performance measures or employees performance targets. (This item was included as a significant issue in last year’s AGS)

 Whilst a partnership framework has been adopted, there did not appear to be any regular reporting to Members on benefits/outcomes or the contribution partnerships made to the Corporate Plan. It was noted that the Corporate Plan contained a key action to review partnership commitments and the value for money obtained.

 Whilst the Corporate Plan 2014-16 contains a vision statement and strategic themes and outcomes, these do not appear to have been ‘communicated…with members, employees, the community or partners’ as required by the Code. (This item was also considered to be an area of non-conformance in 2013).

 Continuing compliance with the Code of Procurement.

Whilst not an issue for the annual governance statement, it was felt appropriate (with the formation of the strategic partnership with South Cambridgeshire District Council and the requirements within the Code that ‘effective mechanisms exist to monitor service delivery’) to reiterate the previously agreed position, that the Panel should be informed of shared service governance arrangements. This will allow them to consider the procedures that had been put in place for obtaining the necessary assurances required to support any future statements that may be included in the annual governance statement.

Financial & Legal implications

There are no financial or legal implications arising from this report.

Recommendation

It is recommended that the Panel:

Consider whether the following governance issues should be recorded as being ‘significant’ in the annual governance statement a. Develop the themes and aims in the Corporate Plan through service plans and performance measures b. Partnership working: benefits/outcomes and the contribution partnerships made to the Corporate Plan c. Publicise the vision statement and strategic themes and outcomes d. Continuing compliance with the Code of Procurement. 1. Background Information

1.1To assist with the preparation of the annual governance statement, an informal meeting of the Panel was held on the 27 June to review the evidence and documentation that supports compliance with the Code of Corporate Governance principles.

1.2The meeting was attended by Councillors Baker, Butler, Harlock and West. Also in attendance were the Head of Resources and the Internal Audit & Risk Manager.

2. Outcome of the Review

2.1When considering the current position against the Code, the following issues were identified:

a. Whilst the Corporate Plan had been adopted in April 2014, the themes and aims it contained remained absent from service delivery plans, performance measures or employees performance targets. This item was included as a significant issue in the 2012/13 AGS.

b. Whilst a partnership framework has been adopted the Panel were concerned that there did not appear to be any regular reporting to Members on partnership benefits/outcomes. The Panel also noted that the corporate plan had a key action to review partnership commitments/value for money.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Preparing the Annual Governance StatementReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
MG
Councillor Michael George Baker, MBEMember, apologies
ER
Councillor Eric Richard ButlerMember, present
KJ
Councillor Ken James ChurchillMember, present
PW
Price WaterhouseCooper CliveAdvisor, expected
GJ
Councillor Gregory John HarlockChair, present
RH
Councillor Roger HarrisonMember, present
PK
Councillor Patrick KadewereMember, present
PG
Councillor Peter Gerald MitchellVice-Chair, present
PW
Price Waterhousecooper JacquiAdvisor, expected
RJ
Councillor Richard John WestMember, present

On this subject at Huntingdonshire

Search all
  1. Preparing the Annual Governance StatementThis decision
  2. Preparing the 2014/2015 annual governance statementAgreed
  3. preparing the annual governance statementApproved

More from Huntingdonshire Corporate Governance Panel

All decisions
MeetingDecisionOutcome
9 Mar 2016 Appointment of vice-chairmanRESOLVED that Councillor T Alban be appointed as the Vice-Chairman of the Corporate Governance Panel for the remainde... Decided Open
9 Mar 2016 External audit plan 2015/16RESOLVED that the Panel notes the content of the revised External Audit Plan for 2015/16 and agrees with the level of... Agreed Open
9 Mar 2016 Grant certification 2014/15RESOLVED that the Panel note the content of the External Auditor’s Annual Certification Report 2014/15. Noted Open
9 Mar 2016 Internal audit service: internal audit plan 2016-17RESOLVED to approve the Internal Audit Plan for 2016/17. Approved Open
9 Mar 2016 Accounting policies for the annual financial report 2015/16RESOLVED to approve the amendments to the accounting policies for the Annual Financial Report 2015/16 as listed in Ap... Approved Open