DEVELOPMENT MANAGEMENT - DEFERRED ITEM - Demolition of existing buildings and erection of 43 dwellings, access, amenity space and associated works, land between St. Andrews Way and Chapel End, Sawtry.
ApprovedCommittee1 paper
Development Management Panel (Decommissioned 18/05/2016) approved this item on Monday 15 December 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED that, subject to the prior completion of a Section 106 obligation relating to affordable housing, open space and wheeled bins, the application be approved subject to conditions to be determined by the Development Services Manager (Development Management) to include those listed in paragraph 8 of the report submitted to the meeting of the Panel held on 20th October 2014 (also appended to these minutes) and three non-standard conditions – highways, footpaths and fencing.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Management Panel (Decommissioned 18/05/2016)
DEVELOPMENT MANAGEMENT PANEL 15thDecember 2014
Case No: 1301274FUL (FULL PLANNING APPLICATION)
Proposal: DEMOLITION OF EXISTING BUILDINGS AND ERECTION OF 43 DWELLINGS, ACCESS, AMENITY SPACE AND ASSOCIATED WORKS
Location: LAND BETWEEN ST ANDREWS WAY AND CHAPEL END
Applicant: DAVIDSONS DEVELOPMENTS LTD
Grid Ref: 517275 283659
Date of Registration: 09.09.2013
Parish: SAWTRY
This application is being presented to Development Management Panel, as it was deferred from the 20th October 2014 meeting to enable the Head of Development to obtain definitive advice from the relevant agencies – Anglian Water Authority, Environment Agency and Middle Level Commissioners in response to issues raised on flooding and drainage matters and to clarify with the applicant the position in respect of the adoption by the relevant authorities of estate roads and drainage.
This application was originally presented to Development Management Panel on the 20th October 2014 (report attached as a Green Paper) with an - officer recommendation to :
-APPROVE subject to the prior completion of a Section 106 obligation relating to affordable housing, open space, and wheeled bins and to include conditions as listed below and any additional conditions required by the Highway Authority. or -REFUSE in the event that the applicant is unwilling to complete the obligation necessary to make the development acceptable.
1. Summary of the update to the report prior to Development Management Panel in October:
1.1As part of the Friday Letter, Members were advised that the Parish Council’s comments included in the Panel Report Pack did not include the Parish Council’s requests of items to be considered as part of the S106 Agreement, (i) a footpath along the development side of St Andrews Way from the roundabout in Fen Lane around into the Old Great North Road to allow safe pedestrian access to St Andrews Cemetery, (ii) a footpath in Chapel End, (iii) the grass footpath from Chapel End to Manor Drive to be hard surfaced and (iv) real time displays on the bus shelters in Fen Lane these requests were however noted. Additionally these requests were not set out in the S106 Agreement Advisory Group Report. Whilst some of the requests from the Parish Council may have been seen to be desirable they were not considered necessary to make the development acceptable and therefore not considered necessary to be secured by a S106 Agreement.
1.2An update to the report was provided in Para. 7.89 S106 (Open Space), whereby the applicant confirmed that the Open Space is to be adopted and maintained by the Council and that the S106 Agreement shall include the appropriate maintenance contributions.
1.3Comments received following the publication of the Panel Report included comments from the Police Architectural Liaison Officer, these comments acknowledged the positive alterations to the proposal with regards to community safety and crime reduction.
1.4Two representations were received which raised points regarding the repositioning of windows to plot 38, the reason why demolition is included in the application description, why the application was presented under the S106 heading on the agenda, concern over precedent, comments on representations received and consideration over boundary treatment. An officer response was provided to these points.
2. Updates since October Development Management Panel
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
DEVELOPMENT MANAGEMENT: DEFERRED ITEM: Demolition of existing buildings and erection of 43 dwellings, access, amenity space and associated works, land between St. Andrews Way and Chapel End, Sawtry.Report
38DEVELOPMENT MANAGEMENT - DEFERRED ITEM - Demolition of existing buildings and erection of 43 dwellings, access, amenity space and associated works, land between St. Andrews Way and Chapel End, Sawtry.This decision
DEVELOPMENT MANAGEMENT - DEFERRED ITEM - Demolition of existing buildings and erection of 43 dwellings, access, amenity space and associated works, land between St. Andrews Way and Chapel End, Sawtry.This decision
Follow Development Management Panel (Decommissioned 18/05/2016) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.