Overview and Scrutiny Panel (Performance and Customers) agreed this item on Monday 6 June 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1) that consideration should be given to removing low risk items from the register; 2) that a report about risk 58 should be submitted to the Panel at its meeting in September 2016; and 3) that the risk that one party could withdraw from the shared service agreement should be fully considered and included on the risk register.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Overview and Scrutiny Panel (Performance and Customers)
Executive summary
This is the first report the Cabinet have received on risk management and the contents of the Council’s risk register. Reports were previously submitted to the Corporate Governance Committee.
The risk register is reviewed frequently by Heads of Service to ensure that it remains fit for purpose and captures the significant risks to the achievement of the Council’s objectives.
Due to the need to meet the reporting timetable for Overview and Scrutiny Panel (Performance and Customers) the report details the contents of the risk register as at 24 May 2016. It focuses in the main on corporate risks and the corporate risk register is attached for review.
The Risk Management Strategy requires the Cabinet to consider each of the very high or ‘red’ residual risks that exceed their risk appetite levels, and to decide whether they should be further mitigated by cost-effective and affordable actions. This report provides information in respect of the one ‘red’ risk that currently falls into this category.
There are currently no financial implications arising from this report, however some costs may be incurred if it is decided that further risk mitigation should be introduced.
Recommendation(s): The Overview and Scrutiny Panel is invited to comment on the corporate risk register.
The Cabinet is
RECOMMENDED
1. To review and scrutinise the corporate risk register and then consider what, if any, further risks should be included in it; and 2. Decide whether it requires further action to be taken to mitigate risk 58. 1. PURPOSE OF THE REPORT
1.1This report provides Cabinet with information about the current risks in the risk register. It concentrates mainly on corporate risks – that is those risks that may be potentially damaging to the achievement of the Council’s objectives.
Background
2.1In line with the Council’s Risk Management Strategy, a risk register has been developed that holds details of the significant risks faced by the Council. Details of the progress made in identifying and managing risks was reported regularly to the Corporate Governance Committee (CGC). Council have decided that responsibility for oversight of the risk management process should rest with the Cabinet rather than the CGC.
2.2The risk management strategy requires Cabinet to receive reports on the management of risk and decide upon the action to be taken for all mitigated risks that exceed the Council’s risk appetite or have the potential to harm its reputation or the continuity of services.
3. ANALYSIS
3.1Risks contained within the register are in the main identified by Heads of Service and Team Managers and reflect the risks associated with the delivery of the themes and aims contained in the Corporate Plan and individual Service Plans.
3.2The total number of corporate and operational risks and their ‘risk scores’ (the sum of likelihood and impact) at both the inherent (without controls) and residual (with controls) levels are summarised in Appendix 1 and 2. The full corporate risk register is attached at Appendix 3.
3.3The risk management strategy approved by Cabinet in July 2015 introduced differing risk appetite levels for key areas of the business. The appetite levels have been applied to all of the risks in the register. Appendix 4 plots the corporate risks against each risk appetite level.
Corporate risks: likely to affect the medium to longer term priorities of the Council .
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Overview and Scrutiny Panel (Performance and Customers) at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.