RESOLVED that powers be delegated to the Head of Planning, Infrastructure & Public Protection to make representations on the appeal to the Planning Inspectorate on behalf of the District Council, in accordance with the following putative reason for refusal: The application has failed to demonstrate that it would not materially harm the safe functioning of Sibson Aerodrome or private flying strips through adverse impacts of glint and glare, and the loss of land necessary to facilitate emergency landings. The development is therefore contrary to policies LP14 and LP34 of Huntingdonshire’s Local Plan to 2036.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
DEVELOPMENT MANAGEMENT COMMITTEE 18th AUGUST 2025 Case No: 25/00652/FUL (appeal ref. 25/00016/NONDET) Proposal: Installation of a solar park to export up to 25 MW (AC) electricity, comprising up to 40,000no. photovoltaic panels, up to 7no. inverters & transformers, 2no. electrical buildings, 1no. onsite control building, boundary fencing and gates, security cameras, and associated infrastructure and engineering operations Location: Land East Of Billing Brook And North And South Of Peterborough Road, Haddon Applicant: Wessex Solar Energy Ltd - [name removed] Ref: (E) 512683 (N) 293366 Date of Registration: 15.04.2025 Parish: Haddon
RECOMMENDATION –
Delegated powers to the Head of Planning, Infrastructure & Public Protection to make representations to the appeal on behalf of the District Council, in accordance with the putative reason for refusal in section 9 of this report.
This application, and by association the District Council’s stance at appeal, is referred to the Development Management Committee (DMC) in accordance with the Council’s Scheme of Delegation, following a call-in request from the Ward Councillor (Cllr Tim Alban).
IMPORTANT NOTE – An appeal against Non-determination has now been submitted and as such it is no longer open to the Local Planning Authority (LPA) to make a formal determination of the application. The appeal has started (ref. 25/00016/NONDET) and the LPA is required to confirm its stance, either adopting putative reasons for refusal or otherwise confirming it does not intend to defend the appeal. The deadline imposed by The Planning Inspectorate for doing so is 20/08/2025.
1. DESCRIPTION OF SITE AND APPLICATION
1.1The application site comprises approximately 25ha of Grade 3b agricultural land, situated in two parcels north and south of the A605, with the bulk of the site being to the north. The site is wholly within Haddon Parish, and Chesterton and Elton Parishes border the north and west edges of the northern part of the site, respectively. 1.2 Along the western edge of the northern parcel, running north to south, is Billing Brook, located within flood zones 2 and 3a, that cover the western most edges of the site. As identified in the 2024 Strategic Flood Risk Assessment, the fluvial Flood Zones run concurrently with areas identified as being at risk from surface water flooding at the 1 in 30 and 1 in 100 year event category, which also run along the edges of the site, particularly along the A605. The 2024 Strategic Flood Risk Assessment identifies the area is at negligible risk of flooding from Groundwater Sources.
1.3Bridleway 111/8 running partially along the western boundary into the site terminating midway in the field. These Public Rights of Way (PROWs) connect to others to the north and east of the northern parcel. The site is located within the Brickclay Mineral Safeguarding Area and along the eastern boundary of the northern half of the site runs an oil pipeline.
1.4The application notes grid connection would be made through underground cables into the wider grid network at the Orton Substation. The works would be carried out by a Statutory Undertaker who has separate statutory powers to carry out these works, and therefore does not form part of this application.
1.5Topographically, the site slopes down from east to west, reflective of the general landscape of this area that rises and falls in noticeable peaks and valleys. The site is located within National Character Area (NCA) 88: Bedfordshire and Cambridgeshire Claylands, and within the Northern Wolds Landscape Character Area as identified in the adopted Landscape and Townscape SPD 2022. Along the eastern, western and northern edges of the site is established planting, predominantly hedgerows, with some intermittent trees, though with trees mostly sited around the areas of the site close to the A605 and along Billing Brook. The southern boundaries include hedgerows, but not as established as other boundaries, and with limited intermittent tree planting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
DEVELOPMENT MANAGEMENT OTHER APPLICATION: INSTALLATION OF A SOLAR PARK TO EXPORT UP TO 25 MW (AC) ELECTRICITY, COMPRISING UP TO 40,000NO. PHOTOVOLTAIC PANELS, UP TO 7NO. INVERTERS & TRANSFORMERS, 2NO. ELECTRICAL BUILDINGS, 1NO. ONSITE CONTROL BUILDING, BOUNDARY FENCING AND GATES, SECURITY CAMERAS,Report
21DEVELOPMENT MANAGEMENT OTHER APPLICATION - INSTALLATION OF A SOLAR PARK TO EXPORT UP TO 25 MW (AC) ELECTRICITY, COMPRISING UP TO 40,000NO.This decision
DEVELOPMENT MANAGEMENT OTHER APPLICATION - INSTALLATION OF A SOLAR PARK TO EXPORT UP TO 25 MW (AC) ELECTRICITY, COMPRISING UP TO 40,000NO.This decision
Follow Development Management Committee at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.