One Leisure Independent Review Update

Decided Scrutiny 3 papers

AI summaryHuntingdonshire scrutiny panel passes its comments on the One Leisure independent review update to Cabinet, which will decide on approving 7 actions and a new vision, customer charter and 3-year business plan structure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPanel's views on the update go to Cabinet for decision
MoneyNot stated
What happens nextCabinet to considerCabinet will decide on approving the report's recommendations
Who it affectsOne Leisure users and staffService changes in Huntingdonshire leisure centres

What was decided

The Panel resolved that its comments on the One Leisure Independent Review Update be passed to Cabinet for consideration when it decides on the report's recommendations.

The report before the Panel sets out progress on 7 actions stemming from a 12-month update on the original First Point Management independent review of the One Leisure Long Term Operating Model, approved by Cabinet on 19th March 2024. Report P3, P6, 2.7

Why

The Council commissioned First Point Management in September 2023 to review the One Leisure long term operating model; a 12-month progress report was considered in July 2025 and identified 7 further actions for the service. Report P1, P6

The report is intended to update councillors on the completion, ongoing work or deferral of those 7 actions, some of which are affected by Local Government Reform (LGR). Report 1.1, 2.8

What happens next

Cabinet is asked to agree that outstanding actions from the July 2025 update are concluded, accept 7 new actions, and approve the new One Leisure Vision, Customer Charter and 3-year business plan structure. Report P11, P12, P13, P14

Authority to implement the strategies is proposed to be delegated to the Head of Leisure, Health and Environment in consultation with the Portfolio Holder for Leisure & Health. Report P15

Several actions have target completion dates in early 2026, including feasibility studies by March 2026, Sawtry pool re-opening in Spring 2026, and launch of the Vision, Charter, Design Principles and Business Plan in April 2026. Report P33

Options considered

  • Chosen: Approve all report recommendations including new Vision, Customer Charter and business plan structure. Forwarded by Panel to Cabinet for decision Report P11, P12, P13, P14
  • Chosen: Delegate implementation to Head of Leisure, Health and Environment. Forwarded by Panel to Cabinet for decision Report P15

Implications

  • Other: A new One Leisure Vision and Customer Charter and a new 3-year business plan structure are proposed for approval. Report P14, 4.8, 4.9, 4.10, P40, P42, P44
  • Other: Some actions are deferred because of Local Government Reform (LGR), affecting the timing of work on One Leisure readiness and longer-term operating model options. Report 1.1, 2.7
  • Risk: The report lists 7 new actions to be acknowledged, some of which depend on partnership working with NHS/ICB and on planning and budget approval for the Huntingdon Sport & Health Hub. Report P12, P27, P33
  • Climate: A decarbonisation option is included as part of the Huntingdon Sport & Health Hub work, with a wider review for other centres to follow. Report P27, P33

Who and where

  • One Leisure service users across Huntingdonshire Report P3, 2.3
  • One Leisure operational staff and Senior Management Team Report 4.5, 4.6
  • Huntingdonshire District Council Senior Leadership Team and the Member Advisory Board Report 4.5, 4.7
  • NHS/ICB partner for the Huntingdon Sport & Health Hub Report P27, P33

Timeline

  • September 2023: First Point Management commissioned for the One Leisure independent review Report P1
  • 19th March 2024: Cabinet approved the Independent Review of the Long-Term Operating Model Report P3, 2.2
  • March 2025: Initial One Leisure staff engagement session on design principles Report P33
  • 10th and 15th July 2025: 12-month update considered by Overview & Scrutiny and Cabinet Report P6
  • October 2025: Decarbonisation option included in Huntingdon Sport & Health Hub work Report P33
  • November 2025: Independent review of One Leisure readiness for LGR and market review commissioned; MoU for Sawtry Leisure Centre Report P33
  • December 2025: License for Works at Sawtry Leisure Centre completed Report P33
  • 16th December 2025: Member Advisory Board endorsed Vision, Customer Charter and 3-year Business Plan principles Report 4.7
  • January 2026: Feasibility study proposal for all One Leisure sites received Report P33
  • February 2026: Full planning application and full budget approval for Huntingdon Sport & Health Hub at Full Council; Cabinet approvals sought for Vision, Charter, Design Principles and Business Plan Report P33
  • March 2026: Target completion for independent LGR and market reviews, feasibility studies to RIBA Stage 1, and Legal Heads of Terms with NHS/ICB Report P33
  • Spring 2026: Planned re-opening of Sawtry Leisure Centre swimming pool Report P33
  • April 2026: Planned launch of One Leisure Vision, Charter, Design Principles and Business Plan Report P33

Plain English for the jargon

  • LGR: Local Government Reform, referred to as a reason for deferring some One Leisure actions
  • RIBA Stage 1 and 2: Stages of the Royal Institute of British Architects' work stages used for feasibility and design of the leisure facilities
  • One Leisure: Huntingdonshire District Council's in-house leisure service operating local leisure centres
  • First Point Management: External consultancy that carried out the original 2023 independent review and the 12-month update
  • MoU: Memorandum of Understanding, used as a staff interim agreement for Sawtry Leisure Centre
  • ICB: Integrated Care Board, the NHS partner body for the Huntingdon Sport & Health Hub
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item45

Resolved

RESOLVED that the comments of the Overview and Scrutiny Panel be passed to Cabinet for their consideration when making a decision upon the recommendations within the report.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Overview and Scrutiny Panel (Environment, Communities and Partnerships)

Executive summary

The Council originally commissioned First Point Management & Consultancy Limited (First Point) in September 2023 to undertake an Independent Review of the One Leisure Long Term Operating Model and its in-house leisure function. The Independent Review included focussed on:

1. Short Term Operating Models (2-3 years) 2. Staff Review 3. Built Facilities & Playing Pitch Strategies 4. Medium (3-5 years)- & Long-Term Operating Models (5+ years)

The One Leisure Long Term Operating Model Independent Review was presented to and approved by Cabinet on 19th March 2024. As part of the Independent Review it stated:

“A transformed in-house option is the recommended approach for the short term; this should allow sufficient time to optimise the service before considering medium and long-term delivery options”.

The Independent Review provided a number of recommendations that One Leisure and the Council should consider for implementation. These can be seen in the Independent Review on pages 50 – 51.

As part of the Cabinet report presented to and approved by Cabinet on 19th March 2024 it stipulated that the Head of Leisure, Health and Environment would provide Overview & Scrutiny Committee and Cabinet a 12-month update. This was completed on 10th and 15th July 2025 respectively. Within this 12-month update report as outlined above it identified 7 further actions for One Leisure and the Council to consider and complete. These can be found in section 4.4 points a – h.

Therefore, this report aims only to update the Council and solely focus on the 7 actions identified following the most recent 12-month update report (July 2025) for approval and conclusion of these actions.

Recommendation(s):

The Cabinet/Committee is:

RECOMMENDED

1. To agree and approve that all outstanding actions from the 12-month update report (July 2025) have been concluded;

2. To acknowledge and accept the 7 new actions from within the Year 1 – Transformation Progress Report of Actions & Recommendations from the Long-Term Operating Model for One Leisure undertaken by First Point Management;

3. To accept and/and or approve the completion or on-going nature of the 7 actions identified within the Transformation Progress Report of Actions & Recommendations from the Long-Term Operating Model for One Leisure undertaken by First Point Management;

4. To approve the One Leisure Vision, Customer Charter, and the new structure of the One Leisure 3-year business plan;

5. To delegate authority to the Head of Leisure, Health and Environment in consultation with Portfolio Holder for Leisure & Health, to undertake all necessary actions required to implement the aforementioned strategies; and embed the vision for One Leisure and its continuous improvement. 1. PURPOSE OF THE REPORT

1.1The purpose of this report is to inform and update Councillors that One Leisure and the Council have either completed, are in the process of completing, or have deferred some of the actions due to LGR.

1.2To provide Councillor’s an opportunity to review, consider and respond on One Leisure’s and the Council’s progress since the 12-month update (July 2025) of the One Leisure Independent Review recommendations.

1.3To gain approval of the newly created One Leisure Vision, Customer Charter, and the new structure of One Leisure’s 3-year business plan;

Background

2.1Built & Playing Pitch Strategies for Huntingdonshire were commissioned in late 2022 and were then presented to Overview & Scrutiny Committee (Environment, Communities & Partnerships) on 8th June 2023 and full approval from Cabinet was gained on 20th June 2023.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
6. One Leisure Independent Review Update Appendix 1Appendix 1.5 MB Download
PDF
6. One Leisure Independent Review Update ReportReport 134 KB DownloadRead as text
PDF
One Leisure Independent Review UpdateReport 62 KB Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
TA
Councillor Tim AlbanMember, present
SB
Councillor Simon BywaterMember, present
SC
Councillor Steve CriswellMember, present
MA
Councillor Martin Andrew HassallMember, present
NJ
Councillor Nathan James HuntChair, present
MK
Councillor Marion KadewereMember, present
CA
Councillor Charlotte Ann LoweMember, present
SM
Councillor Shariqa MokbulMember, present
BM
Councillor Ben Michael PittVice-Chair, present
DJ
Councillor Dave John ShawMember, present
DT
Councillor Doug TerryMember, absent
NW
Councillor Nic WellsMember, present

On this subject at Huntingdonshire

Search all
  1. One Leisure Independent Review UpdateThis decision
  2. One Leisure Solar Installations UpdateAgreed
  3. One Leisure Huntingdon Shadow BoardDecided
  4. One Leisure Independent Review UpdateAgreed
  5. New 3G Artificial Turf Pitch (ATP) at One Leisure St Ives OutdoorApproved
  6. One leisure independent review updateNoted

More from Huntingdonshire Overview and Scrutiny Panel (Environment, Communities and Partnerships)

All decisions
MeetingDecisionOutcome
5 Nov 2026 Council Tax Support 2027/28RESOLVED that the comments of Overview and Scrutiny be passed to Cabinet for their consideration when making a decisi... Decided Open
5 Nov 2026 Homelessness StrategyIt was agreed by the Executive Councillor and Officers that this could and would happen and that the strategy would b... Agreed Open
5 Nov 2026 Safeguarding PolicyRESOLVED that the comments of Overview and Scrutiny be passed to Cabinet for their consideration when making a decisi... Decided Open
5 Nov 2026 Cambridgeshire County Council Health CommitteeRESOLVED that Councillor D McIlwain be appointed as the substitute Member to the Cambridgeshire County Council Health... Decided Open
2 Jul 2026 One Leisure Solar Installations UpdateIt was agreed that an update on changes to energy contracts and the impact on costs would be sought and communicated ... Agreed Open