External Peer Review of Internal Audit

Noted Finance 2 papers

Audit Committee noted this item on Monday 6 March 2023. Below is the council's own wording, with the papers it was decided on.

Item312

Resolved

Resolved – That the report be noted by Audit Committee. - That Democratic Services revise the meeting timetable to add an additional Audit Committee into the schedule.
Word for word from the decision Hyndburn published for this meeting. Source: democracy.hyndburnbc.gov.uk

Follow this further

Built from Hyndburn's papers

What the report saysPro

Report to Audit Committee, 4 pages

Purpose of report

1.1To inform Audit Committee of the outcome of the mandatory external inspection of Hyndburn’s Internal Audit Team against the requirements of the Public Sector Internal Audit Standards and present the final report of the external inspection team.

Recommendations

2.1I recommend that Audit Committee:  notes the content of this report.

3. Reasons for Recommendations and Background

3.1Every Internal Audit team within the public sector must conform to the Public Sector Internal Audit Standards. The Standards state every public sector internal audit team must undergo an external assessment of their conformance with the Standards once every 5 years. Hyndburn Borough Council’s Internal Audit team was previously assessed in early 2018 meaning the next external assessment had to be completed by early 2023.

3.2The external review can be achieved in a number of ways. The review can be procured from an external provider such as one of the large private accountancy firms or from one of the professional bodies such as the Chartered Institute of Internal Auditors. Procuring the review in this way does carry a direct financial cost. An alternative process is to undergo the inspection by external Peer Review. This does not incur a direct financial cost but it does require reciprocal staff time input.

3.3A structured Peer Review process was created for the 2017/18 review process. The methodology was fully reviewed and agreed for the 2022/23 reviews. Following discussion across the County, 8 of the Borough Councils within the Lancashire Audit Group agreed that they would be part of the current Peer Review Process. Two of the Lancashire Councils chose to procure an external review, 4 authorities buy-in an audit service, one authority is part of the North West Chief Audit Executives Group and has their review through that group. The final authority buy their audit service from the authority which is part of the North West group.

3.4The Lancashire Districts that are part of the Peer Review process have been inspected by 2 experienced Heads of Audit from 2 other Councils. The Head of Audit & Investigations has carried out a review of another Lancashire Internal Audit Team and will be involved in the review of another Lancashire Internal Audit Team in the coming weeks.

3.5Hyndburn’s review began in mid-2022 with the Head of Audit & Investigations evidencing all of the Standards. Significant volumes of information about the Internal Audit Team, its processes and work were shared with the Review Team prior to the inspection. All individuals chosen to be interviewed as part of the review also completed a questionnaire prior to the review. Some additional Heads of Service who were not interviewed were also asked to complete a questionnaire.

3.6The External Review Team examined the evidence, questionnaires and then carried out interviews via Teams to explore issues further on 15th, 16th and 17th of November 2022. The External Review Team met with the Head of Audit & Investigations via Teams on 21st November 2022.

3.7The External Review Team’s report is attached as Appendix 1.

3.8The External Review can arrive at 3 judgements based on the outcome of the review process, these are conforms, partially conforms and does not conform. Their judgement is that Hyndburn’s Internal Audit Team conforms to the Public Sector Internal Audit Standards.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Peer Review of Internal AuditReport 4 pages DownloadRead as text
PDF
Final Peer Review Report: January 2023Report 10 pages Download

At this meeting

Whole meeting

More from Hyndburn Audit Committee

All decisions
MeetingDecisionOutcome
23 Jun 2025 Minutes of the Last MeetingResolved – That the minutes be received and approved as a correct record. Approved Open
23 Jun 2025 Risk Management Monitoring ReportResolved – The Committee noted the content of the report and the changes made to the risk registers. Noted Open
23 Jun 2025 Annual Internal Audit Report & OpinionResolved – The committee noted the 2024/2025 Annual Internal Audit Report and Opinion. Noted Open
23 Jun 2025 Internal Audit Plan Progress UpdateResolved – The Audit Committee noted the report for information. Noted Open
23 Jun 2025 Follow Ups UpdateResolved – The committee noted the report for information. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies