Resolved – That the report was noted for informational purposes. [name removed] to come back to the Committee on the following points raised: · To update the Committee on the Huncoat Garden Village risk. · To update the Committee on the Leisure Transformation risk. · To request further information on weekend burials and to check if this would go on the Risk Register.
Word for word from the decision Hyndburn published for this meeting.Source: democracy.hyndburnbc.gov.uk
To inform Audit Committee of: the outcome of the Strategic, Generic and Operational Risk Registers review;
Recommendation
That Audit Committee: Notes the content of the report.
Background
Report Background: The Councils mission statement in regards to Risk Management is as follows: o The Council is committed to adopting best practices in the identification, evaluation, and cost-effective control of risks to ensure that they are eliminated or reduced to an acceptable level. It is acknowledged that some risks will always exist and will never be eliminated. All employees must understand the nature of risk and accept responsibility for risk associated with their area of work. In doing this they will receive the necessary support, assistance and commitment from Senior Management and Members. The Council’s risk management policy is a long-term commitment and is an inherent part of good management and governance practices. It states within the Council Financial Procedure rules that the Council is responsible for approving the Council’s risk management strategy. The Audit Committee is responsible for the review and monitoring of the Council’s risk management arrangements. The Council has adopted the following definition produced by the Institute of Risk Management, which states:- o Risk Management is the identification, measurement, control and financing of risks which threaten the existence, the assets, the earnings of the personnel of an organisation, the services it provides, the achievement of its corporate priorities or which may cause undue harm to the public.
The Risk Management Process: Risk management must not be the responsibility of just a few specialists. It must be a primary management responsibility for all managers and supervisors and must be a consideration for all employees. Risk assessments are about asking:- o What can go wrong o What is the likelihood of it going wrong o What is the impact should it go wrong o What can be done to eliminate the threat o What should be done to reduce the threat’s likelihood or impact
Page 1 of 22 This 5-point approach can be applied to decisions made every working day, at all levels of the Council. The Council risk assessment scoring is based on the guidance of the Institute of Risk Management: o 3 being a high risk; o 2 being a medium risk; o 1 being a low risk. o The definitions of High, Medium and Low are also based on the guidance of the Institute of Risk Management and aid assessing Impact and Likelihood.
High 3 Medium 2 Low 1
Assessing the Very likely to happen. Likely to happen. Unlikely to happen. Likelihood Regular Occurrence. Likely to happen at Has happened Loss-causing some point over the rarely/never before. circumstances next two years. Loss-causing frequently Loss-causing circumstances rarely encountered circumstances encountered. daily/weekly. encountered few times a year. Assessing May result in: May result in: Serious May result in: Minor Impact Fatality disabling injury / ill injury / ill health, Financial loss in health financial loss in Minimal financial loss of excess of £2 million. excess of £500,000, less than £500,000. Non-delivery of significant disruption to Minor disruption to service for more than provision of service eg. provision of service for 3 weeks. more than 1 week. short time eg. less than Adverse international Adverse national 1 week. Adverse local media coverage. media coverage. media coverage.
Types of Risk: The Corporate Risk Register outlines the key strategic risks facing the Council and the controls currently in place to respond to these risks.
Page 2 of 22 The Councils Risk Register is summarised as follows: o 17 Generic risks - (1 high 4 medium and 12 low) o 66 Operational risks - (1 high 19 medium 46 low) o 19 Strategic risks - (3 high 5 medium and 11 low)
Reasons for recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.