CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Hyndburn Borough Council
Special Scrutiny Committee, Wednesday 16 July 2025

Minutes of the last Meeting

Approved Scrutiny 1 paper

Special Scrutiny Committee approved this item on Wednesday 16 July 2025. Below is the council's own wording, with the papers it was decided on.

Item99

Resolved

Resolved - That the Minutes be received and approved as a correct record.
Word for word from the decision Hyndburn published for this meeting. Source: democracy.hyndburnbc.gov.uk

Follow this further

Built from Hyndburn's papers

What the report saysPro

Report to Special Scrutiny Committee, 4 pages

Public Document Pack

SPECIAL SCRUTINY COMMITTEE

Wednesday, 5th February, 2025

Present: Councillor Bernard Dawson MBE (in the Chair), Councillors Zak Khan, Clare Pritchard (Vice Chair) and Mohammed Younis Co-optees: Andy Tatchell and Shahed Mohammed

In Attendance: Councillor Noordad Aziz (Cabinet Portfolio Holder for Transformation, Education and Skill Steve Riley, Executive Director (Environment)

Apologies Councillors Heather Anderson, Clare McKenna and Clare Yates

197 Apologies for Absence and Substitutions

Apologies for absence were submitted on behalf of Councillors Clare McKenna, Heather Anderson and Clare Yates. There were no substitute representatives in attendance at the meeting.

198 Declarations of Interest and Dispensations

There were no interests or dispensations declared at the meeting.

199 Minutes of the last Meeting

The minutes of the last meeting of the Special Overview & Scrutiny Committee, held on 14th October 2025, were submitted for approval as a correct record.

Resolved - That the Minutes be received and approved as a correct record.

200 Town Centre Levelling Up Project Progress

The Cabinet Portfolio Holder for Transformation, Education and Skills, Councillor Noordad Aziz, submitted a report to respond to the request from the Special Overview & Scrutiny Committee for a general update on the Council’s Levelling Up Fund (LUF) funded town centre projects. The report gave details of the progress of the three main projects: Market Hall, Burtons Chambers and Market Chambers. In respect of Burtons Chambers and Market Hall, Councillor Aziz reported that significant progress had been made.

The Executive Director (Environment) referred to the Market Chambers project and informed the Committee that a sale by agreement had just been secured with the last freehold owner but that the compulsory purchase order would still continue to hopefully provide a full clean title. He explained that a public CPO enquiry had taken place in December 2024, following objections to the acquisition of the Market Chambers. The enquiry had been adjourned until after the Cabinet meeting on the 22 January 2025, to allow the Inspector time to understand the Council’s commitment to supporting the operating costs, once Market Chambers was open. Both legal representatives had asked

1 the Inspector for a delay in making their final closing statements to progress the sale of agreement, which had been agreed.

Councillor Aziz reported that the Operator 2-Work had been secured for Burtons Chambers and that a preferred operator had been identified for the Market Hall and that these would drive footfall into Accrington town centre and restart further regeneration.

The Committee had submitted questions to Councillor Aziz in advance to the meeting, which were responded as follows:

1. How long will it take for both work phases to be completed?

Reference was made to 3.3.2 of the report which explained that the estimated completion date for phase 1 enabling works provided by Morgan Sindall was Q4 2024/25 although this could extend into Q1 2025/26. The programme timescale had been impacted by the initial 6 month delay in funding announcement/authorisation to start and additional works identified as the building was being stripped out.

Reference was also made to 3.3.3 of the report and the phase 2 fit-out works contract, again provided by Morgan Sindall, is Q3 2025/26. The Committee was informed that this could be extended into Q4 depending on the successful contractor(s) and their tender programme dates.

The Executive Director (Environment) informed the Committee that the Phase 2 fit- out works were being tendered in line with the new Procurement Act 2023 which would come into force on 24th February 2025. He reported that this aimed to improve and streamline the way procurement was undertaken by public bodies and should benefit prospective suppliers, particularly small businesses.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Minutes of the last MeetingReports_pack 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hyndburn

Search all
  1. Minutes of the last MeetingThis decision
  2. Minutes of the Last MeetingApproved
  3. Minutes of the Last MeetingApproved
  4. Minutes of Last MeetingApproved
  5. Minutes of Last MeetingApproved
  6. Minutes of Last MeetingApproved

More from Hyndburn Special Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Overview & Scrutiny Work ProgrammesResolved - That the work programme for the Special Overview & Scrutiny Committee be approved. Approved Open
16 Jul 2025 Co-optee NominationsResolved - that the report be noted. Noted Open
5 Feb 2025 Minutes of the last MeetingResolved - That the Minutes be received and approved as a correct record. Approved Open
14 Oct 2024 Minutes of the last MeetingResolved - That the Minutes be received and approved as a correct record. Approved Open
14 Oct 2024 Appointment of Co-opteesResolved - That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies