Resolved
(i) that the Executive approves the proposed revisions to the Local Development Scheme Work Programme set out in Appendix 1 of the report; Reason: The Local Development Scheme needs to be kept up to date so that stakeholders know what the Council’s programme of plan preparation is, and to ensure that progress monitoring through the Annual Authority Monitoring Report is done against robust timetables (ii) that the Executive authorises the Town Planning Operations Manager to make consequential amendments to the current Ipswich Local Development Scheme in consultation with the Portfolio Holder; Reason: To reflect the changes made to the work programme throughout the document (iii) that the Town Planning Operations Manager be authorised to formally bring into effect the revised Local Development Scheme by 30 th July 2013. Reason: It is a legal requirement that the Council should formally bring the revised Local Development Scheme into effect