that the North East Area Committee agreed that £4,264.10 be allocated from the £25,000 grant funding agreed on 20 September 2012 for the Cherry Tree Recreation Ground project. Reason: To secure the release of external funding from Viridor by paying the Third Party Contribution and to ensure the project can proceed at the earliest opportunity. 2. that, subject to securing an agreement with the Friends of Cherry Tree Recreation Ground in respect of the transfer of the third party contribution and funding pledged by Viridor and Suffolk County Council towards the project costs, the Head of Communities and Culture be authorised to conduct a procurement exercise on behalf of the Friends of Cherry Tree Lane Recreation Ground for the installation of new play equipment at the recreation ground. Reason: To ensure proper arrangements are in place for the funding and the procurement and installation of new equipment. 3. that prior to commencing the procurement exercise, the Head of Community and Culture would undertake a public consultation exercise with residents in the neighbourhood and the Friends of Cherry Tree Recreation Ground, to help identify the most suitable scheme design taking into account their issues or concerns, and consult with ward Councillors on the choice of scheme designs before the final scheme was selected. Reason: To ensure that the best possible design is achieved to meet the resident’s needs and any concerns. 4. that the procurement of equipment include consideration of the maintenance provision available and resource implications of new equipment before procurement be undertaken. Reason: To ensure that the best possible design is achieved to meet the maintenance requirements for the Council.
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: NORTH EAST AREA 10 REF NO: NEAC/13/06 DATE: 25 JULY 2013 SUBJECT: PROJECT TO IMPROVE YOUNG PEOPLE’S PLAY AREA FACILITIES AT CHERRY LANE REC REPORT AUTHOR: EDDIE PETERS
Short description of report content and the decision requested: The report outlines an initiative to improve facilities for children and young people on Cherry Lane Recreation Ground, owned and managed by the Council in the North East area of Ipswich. These improvements will include providing additional young people’s equipment and improve the existing equipped play area.
The need to improve facilities has been identified by the Friends of Cherry Lane Recreation Ground and the Council through consultation with the local community, including children and young people.
The Friends have successfully secured funding pledges amounting to £76 288.46. (comprising: 2012-13 NE Area committee Budget - £25,000, SCC Locality Funding - £9,500 and an external Viridor grant - £41 788.46). However, in order to release the Viridor Pledge they need to make a Third Party Contribution (TPC) - £4,264.10 to release the external grant funds for use in line with the terms of all Viridor grants. The TPC is entirely separate from any project costs or funding, and is a payment between the Contributing Third Party (CTP) (an organisation or individual unconnected to the Friends group who applied for the grant) and the Viridor. The TPC must not be factored into, or come from, any award from Viridor Credits or other Landfill Communities Fund (LCF) monies.’ If the payment of the TPC is paid by the council to Viridor out of the NE area committee grant or the SCC locality funds, the available budget for the project would be reduced to £72,024.36. The Friends have obtained quotes in the region of £70,000 suggesting that it should be possible to deliver the desired improvements with a budget of £72,000 approx. Options include: • Area Committee to release part of the funds already allocated to the project and tailor any play area improvements to the budget figure. • Area Committee consider providing the required additional amount to enable the Viridor grant to be released with no reduction in budget for the project. • Ask the Friends to seek the TPC funding from elsewhere, e.g. a different external funding organisation or another SCC locality budget . However, this option has the potential to delay delivery of the project .
List of Appendices included in this report: a) Appendix 1 – Catchment area plan showing current play provision b) Appendix 2 – Catchment area plan showing current youth provision c) Appendix 3 – Consultation analysis d) Appendix 4 – Viridor Guidelines
This report has been prepared by Eddie Peters, Tel: 01473 432130 Email: [email protected] This report was prepared after consultation with: Internal consultees: Staff in Parks & Open Spaces External consultees: – local community Friends of groups (Friends of Cherry Tree group) Young people The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report) Building a Better Ipswich Ipswich Play Strategy 2007 (currently under review)
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. Ipswich Play Strategy 2007 (currently under review) 2. Cherry Tree Play Improvements - NE Ipswich Viridor Grant form ___________________________________________________________ 1. Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEAC/24/11 Area Committee Budget Updatethat the financial statement in Appendix 1 to the report be noted. Reason: To provide clear and transparent details o...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.