that Executive approve the acceptance of the tender submitted by the contractor listed as BC1 in exempt Appendix 1 to the report and authorise the Head of Housing & Customer Services in consultation with the Head of Corporate Services to enter into a contract with the recommended contractor as set out in this report. Reason: The tender submitted by the recommended contractor was the most economically advantageous to the Council in accordance with the criteria set out in the tender documents
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: EXECUTIVE 9 REF NO: E/13/64 DATE: 26 NOVEMBER 2013 SUBJECT: DEVELOPMENT AT BADER CLOSE - TENDER AWARD PORTFOLIO HOLDER: COUNCILLOR JOHN MOWLES HEAD OF SERVICE: IAN BLOFIELD Short description of report content and the decision requested: This report details the work that has been carried out to procure a contractor to carry out the housing development on land at Bader Close and sets out the results of the Tenders received.
Executive is asked to approve acceptance of the most economically advantageous tender for the housing development on land at Bader Close with the Contractor identified as BC1 in exempt Appendix 1.
The following appendix is to be considered in Part 2 of the agenda as it is likely that if members of the public were present during that item there would be disclosure to them of exempt information.
List of Exempt Appendices referred to in this report: a) Appendix 1 – Price and Technical Requirements Evaluation This report has been prepared by, John Richardson Tel: 01473 433330 Email: [email protected] This report was prepared after consultation with: Internal consultees Head of Housing & Customer Services Head of Corporate Services Operational Manager- Tenancy Services Procurement Manager Financial Services The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report) Building a Better Ipswich LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1. Developing a Programme of New Council Housing 13th March 2012 E/11/86 2. Developing a Programme of New Council House Building 12th June 2012 E/12/01 3. Proposed Development at Bader Close 27th November 2012 E/12/54
1.1Executive have previously agreed to build houses on the vacant land at Bader Close Ipswich. The development has been progressing through the various stages required to develop the site. This report requests Executive consider and agree the appointment of the contractor to develop the site. 1.2 The report details what is included in the contract, gives particulars of the tenders received and the tender evaluation process carried out and requests Executive approve the most economically advantageous tender. ______________________________________________________________ 2. Background
2.1Fundamental reforms to Housing Revenue Account (HRA) introduced from April 2012 saw the abolition of the previous subsidy arrangements and the introduction of a self-financing system.
2.2The reforms coupled with the efficiency savings made in Housing mean that the account generates an annual surplus, providing the opportunity to build the first council homes in Ipswich since June 1992. It also allows the Council to further develop a long-term development programme.
2.3Reports outlining the proposals were considered by Executive at its meetings on the 13th March 2012, 12th June 2012 and the 27th November 2012. These reports authorised the various stages of the development up to the submission of the planning application.
2.4The planning application for Bader Close subsequently submitted was considered at the Planning Committee meeting on 21st August 2013 and permission was granted subject to normal planning conditions The site layout and dwelling designs granted approval are as follows: Total of 108 dwellings 10 one bed accessible bungalows 10 two bedroom accessible bungalows 77 two bedroom houses 11 four bedroom houses.
3. Tendering Process
3.1To meet the Council’s Standing Orders and to comply with legislation governing tenders of the size of the project the OJEU tendering process was followed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.