Item191
Resolved
- Grant Full Planning Permission upon condition that:- 1. The development shall be carried out in accordance with the details shown on the following submitted drawings nos _ 4392-PL1A, -PL2A, PL3A, PL4A, PL5A, and the requirements of any succeeding conditions. 2. No development approved by this planning permission (or such other date or stage in development as may be agreed in writing with the Local Planning Authority), shall take place until a scheme that includes the following components to deal with the risks associated with contamination of the site shall be submitted to and approved. In writing, by the Local Planning Authority: i ) A preliminary risk assessment which has identified: - All previous uses - Potential contaminants associated with those uses; - A conceptual model of the site indicating sources, pathways and receptors; and - Potentially unacceptable risks arising from contamination at the site. ii) A site investigation scheme, based on ( i ) to provide information for a detailed assessment of the risk to all receptors that may be accepted, including those off site. iii) The results of the site investigation and detailed risk assessment referred to in (ii) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken. iv) A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in iii) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action. Any changes to these components require the express written consent of the Local Planning Authority. The scheme shall be implemented as approved. 3. No occupation of any part of the permitted development shall take place until a verification report demonstrating completion of works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved, in writing, by the Local Planning Authority. The report shall include results of sampling and monitoring carried out in accordance with the approved verification plan to demonstrate that the site remediation criteria have been met. It shall also include any plan (a "long-term monitoring and maintenance plan") for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action, as identified in the verification plan. The long-term monitoring and maintenance plan shall be implemented as approved. 4. No development should take place until a ... view the full minutes text for item 191.
Word for word from the decision Ipswich published for this meeting.
Source: democracy.ipswich.gov.uk