that the South East Area Committee approves funding of £20,000 from the South East Area Committee budget for the provision of a new all-weather 5-a-side playing surface and Diamond climber play equipment for Landseer Park, as detailed in the report. Reason: To enable the existing park and play area to be upgraded, improve local facilities and make the play area more accessible to a wider range of users
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: SOUTH EAST AREA 11 REF NO: SEAC/14/20 DATE: 19 MARCH 2015 SUBJECT: FUNDING REQUEST: LANDSEER PARK – COMMUNITY PROJECT TO IMPROVE THE PLAY AREA REPORT AUTHOR: SAM TEAGUE HEAD OF SERVICE: GORDON MOLE Short description of report content and the decision requested: This report requests a £20,000 grant from the South East Area Committee to enable funding for play equipment improvements to be delivered at Landseer Park.
The report also highlights community led initiatives to make various improvements on Landseer Park. These improvements form the basis of an Action Plan (Appendix 2).
The site is owned by Ipswich Borough Council (IBC) and managed by the Parks & Open Spaces Service. The initiative to install play equipment has been instigated by the recently formed Friends of Landseer Park and supported by feedback from local community via surveys, identifying potential improvements. The South East Area Committee has supported a variety of improvements and community led initiatives for Landseer Park.
List of Appendices included in this report: a) Appendix 1 – Landseer Park Community Survey 2013 Summary b) Appendix 2 – Landseer Park Action Plan c) Appendix 3 - Schedule of Costs d) Appendix 4 – Play equipment proposed, pictures e) Appendix 5 – Plan showing play area vision
This report has been prepared by Sam Teague, Parks & Open Spaces Email: [email protected] Tel: 01473 433536 This report was prepared after consultation with: Internal consultees Cllr Bill Knowles Chair of the South East Area Committee, Ian Blofield Head of Housing services, Tibbs Pinter Communities, Equality and Diversity, Nick Wilcox Area Supervisor for parks and open spaces, Debbie Owen Community Engagement Officer External consultees all user groups and volunteers, Friends of Landseer Park and Park users, via surveys. The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report) Building a Better Ipswich South East Area Action Plan
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1.
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1. Area Committee Action Plan, which can be found online: https://www.ipswich.gov.uk/content/whats-on-south-east ______________________________________________________________ 1. Introduction
1.1This funding request to South East Area Committee seeks £20,000 to deliver and install a spinning Diamond climber and an all-weather multi- court, both for children aged 8 and over, in Landseer Park. The Friends of Landseer Park are seeking this funding to complement works associated with the play area, for which they have already secured some funding from the South East Area Committee and the Suffolk County Council locality funding.
1.2The new facilities, which will be accessible to all park users, will provide much needed improvements to the equipped play area. Both facilities can be installed without intruding on the existing layout and can be supplemented at a later date with additional equipment, subject to funding being available to help deliver the remaining work on the proposed action plan. The plan showing the play area vision is attached at Appendix Five.
1.3The Diamond climber, as illustrated in Appendix Four, would be the first of its kind to be installed by Ipswich Borough. The all-weather 5-a- side pitch makes use of the system manufactured by Nottssport Sports Surfacing, which is constructed from a hard-wearing fire resistant synthetic fibre. The surface is top-dressed with sand, which protects the surface from wear and also improves the playing experience. A full cost breakdown is provided within Appendix Three.
1.4A similar all-weather 5-a-side surface has been installed at Castle Hill Recreation Ground in summer 2014 and has proved very popular among young people, see Appendix Four.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.