(i) that Option 1 in the report be approved and the Head of Culture and Environment Services, in consultation with the Section 151 Officer and Operations Manager for Legal Services, be authorised to appoint supplier A ( as identified in Exempt Appendix 2 of the report) as the principal and main contractor to build the new sports pavilion and changing rooms at the Ransomes Sports Ground. Reason: To enable the proposed new facilities to be provided. (ii) That the capital programme be amended, utilising part of the 2015/16 capital contingency, to ensure that the development is fully funded in accordance with the details set out in section 9 of the report. Reason: To ensure that sufficient capital funding is made available for the construction of the proposed new sports pavilion building. (iii) That the Head of Culture and Environment Services be authorised to seek expressions of interest from relevant organisations for sporting uses/developments to take place on Plots A and B, as illustrated in Appendix 5 of the report. Reason: To start the process to ensure that the rest of the site is brought into credible sports uses. (iv) That the Council’s on-going revenue budget commitment to Ransomes Sports Ground be noted. Reason: To make clear the related revenue commitments of the Borough Council to the site so that they may be included in the MTFP for 2016/17.
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: EXECUTIVE 9 REF NO: E/15/15 DATE: 14 JULY 2015 SUBJECT: RANSOMES SPORTS GROUND – UPDATE INCLUDING APPOINTMENT OF MAIN CONTRACTOR FOR THE PAVILION PORTFOLIO HOLDER: COUNCILLOR BRYONY RUDKIN HEAD OF SERVICE: GORDON MOLE Short description of report content and the decision requested: Ipswich Borough Council assumed responsibility for the Ransomes Sports and Social Club on 1 November 2013. Following an assessment that the main sports pavilion, incorporating changing facilities, was unsafe, the buildings were condemned and subsequently demolished in December 2014.
Temporary buildings have been supplied for the various clubs to use as changing facilities. The Council has been granted planning permission to build a replacement sports pavilion on the site using a mix of its own capital funds, together with funding from the Football Foundation.
This report requests authorisation for the Head of Culture and Environment Services to appoint the preferred Main Contractor and to approve the release of appropriate funding in response to the recent tendering procedure.
Ward(s) affected: Rushmere List of Appendices included in this report: (a) Appendix 3 – Football Foundation and Suffolk Football Association Letters of Confirmation (b) Appendix 4 - Letters from Commonwealth War Graves Commission and Ransomes Jacobson regarding the covenant over the Memorial (entrance) Gates (c) Appendix 5 – Site drawing showing Plots A and B of land that could be redeveloped The following appendices are to be considered in Part 2 of the Agenda as it is likely that if members of the public were present during that item there would be disclosure of exempt information. List of Exempt Appendices included in this report: (a) Appendix 1 – Tender Report, as produced by Marstan BDB LLP, dated April 2015 (b) Appendix 2 – Supplier list This report has been prepared by Mark Hunter, Tel: 01473 432808, Email: [email protected] This report was prepared after consultation with: Internal consultees Building and Design Service Legal Services Finance Planning Services Head of Culture and Environment Deputy Leader of the Council (Portfolio Holder) Leader of the Council External consultees Football Foundation England and Wales Cricket Board Suffolk Football Association
The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report)
Building a Better Ipswich LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. None
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)
1. Exempt Executive report E/11/83: Ransomes Sports and Social Club options ______________________________________________________________ 1. Introduction
1.1This report seeks Executive approval to:
authorise the Head of Culture and Environment, in consultation with the Council’s Section 151 Officer and Legal Services Operations Manager, to: (a) approve the release of relevant funds to complete the works; and, (b) appoint the preferred Principal/Main Contractor for the works.
Seek expressions of interest for sports (and related uses) for the parts of the site that are not currently in sporting use.
1.2The report also asks Executive to note the on-going revenue expenditure associated with the site as set out in 9.11.
1.3The design for the replacement building has been procured in line with Contract Standing Orders and the Council has sought all necessary consents for the proposed replacement building. Tenders for the building were returned on 27th February 2015. The Planning Committee approved an application for the new building at its meeting on 18th February 2015.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.