- that Option 1 in the report be approved and the Chief Operating Officer, in consultation with the Section 151 Officer and Operations Manager for Legal Services be authorised, to appoint Supplier A (as identified in exempt appendix B of the report) as the Principle and Main Contractor to refurbish the Christchurch Mansion Consolidation project (2016) as outlined in this report. Reason: To enable the proposed refurbishment work to be undertaken. The work has been tendered and Supplier A’s tender is the most economically advantageous for the Council.
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: EXECUTIVE 14 REF NO: E/15/71 DATE: 8 MARCH 2016 SUBJECT: CHRISTCHURCH MANSION CONSOLIDATION: APPOINTMENT OF MAIN CONTRACTOR PORTFOLIO HOLDER: COUNCILLOR CAROLE JONES HEAD OF SERVICE: HELEN PLUCK Short description of report content and the decision requested: Christchurch Mansion is in general need of improvement and replacement, in terms of various building fabric and related service elements. There is a need to bring the Mansion up to a good standard and level of comfort to allow visitors to enjoy the Mansion. The refurbishment works that are undertaken at Christchurch Mansion will ensure that the Christchurch Mansion is fit for purpose for the next 15 years and able to effectively support the Council’s offer of a great visitor experience.
This report requests authorisation from the Executive to award the preferred Main Contractor for the works following the recent tendering procedure.
Ward(s) affected: St. Margaret’s List of Appendices included in this report: Appendix A – Condition Survey Report The following appendices are to be considered in Part 2 of the agenda as it is likely that if members of the public were present during that item there would be disclosure to them of exempt information. List of Exempt Appendices included in this report: Appendix B – Summary of Supplier names and tenders submitted Appendix C - Summary of Qualitative/Cost Assessment scores Appendix D – Tender Report, as produced by Hyams, dated 25th January 2016
This report has been prepared by Mark Hunter, Tel: 01473 432808, Email: [email protected]
This report was prepared after consultation with: Internal consultees Building and Design Service Legal Services Finance Planning Services Acting Head of Community and Cultural Services Portfolio Holder for Culture and Leisure Leader of the Council
External consultees Suffolk Archaeology Anglian Ecology CCAS – Health and safety advisors Hilary Brightman Conservation Architect MLM – Mechanical and electrical building services Hyams – Quantity surveyors The Morten Partnership – Structural Engineers in association with Pro-flat for specialist scaffold design development
The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report) Building a Better Ipswich
LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)
1. None
OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material) 1. None __________________________________________________________________ 1. Introduction
1.1Christchurch Mansion is in general need of improvement, a statement that is supported by the external specialist conservation Architect who maintains a “watching brief” over the important Grade 1 listed building.
1.2Refurbishment works will significantly improve the standard and level of comfort experienced by visitors to the Mansion.
1.3The works undertaken at Christchurch Mansion will ensure that the Mansion is fit for purpose for the next 15 years and able to effectively support the Council’s offer of a museum visitor experience in Ipswich.
1.4The refurbishment works to be undertaken at Christchurch Mansion will include the following :
Heating and humidity works Roof repair and associated works Minor repair and redecoration works Security and fire safety works.
1.5This report seeks Executive approval to:
approve the release of relevant funds to complete the works; and award the Main Contract for the works following a recent tendering procedure subject to the application for Listed Building Consent being approved.
1.6The design for the refurbishment works has been procured in line with Contract Standing Orders and the Council has sought all necessary consents for the proposed refurbishment works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.