CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Ipswich Borough Council
Planning & Development Committee, Wednesday 6 April 2016 at 9.30am

PD/15/16 Item 5 - Application IP/16/00156/FPI3

Deferred Planning 2 papers

Planning & Development Committee deferred this item on Wednesday 6 April 2016. Below is the council's own wording, with the papers it was decided on.

Item166

Resolved

Application deferred.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Planning & Development Committee

All dimensions to be verified on site by Main Contractor before the start of any shop drawings or work whatsoever either on their own behalf or that of sub-contractors.

LEGEND: Report any discrepancies to the Contract Administrator at once.

This drawing is to be read with all relevant Architect's and Engineer's N Road / Car park construction; drawings and other relevant information.

Porous Asphalt placed to attenuate within © Ingleton Wood LLP the sub-base, laid to falls towards soakaway.

Important Note: Important Note: DO NOT SCALE Road / Car park construction; Soakaway sizing is subject to in-situ percolation All existing drainage for re-use is unconfirmed for Impermeable Asphalt finish. Notes: testing. Tests in accordance with BRE Digest 365 condition, levels & connections. CCTV survey is - The principle disposal of surface water runoff is to be by Existing level means of infiltration via a buried soakaway. Northwestern must be undertaken to confirm infiltration rates. required to demonstrate appropriateness of all most corner of car park resurfacing to fall towards existing drainage to be reused and to confirm outfall. 7.00 Proposed level channel drain to be re-used to provide positive drainage. 1/80 - The permeable paving car park is designed to provide Fall 3No. stages of surface water treatment prior to discharge

LC Lighting Column from the drainage system; 1. porous asphalt road construction, Kerb Type Details: 2. filter media placed above buried soakaway, 3. and via buried tank soakaway. 125 x 255mm Type HB2 PCC kerb to HB2 - Stockpiled and excavated material to be reused as BS EN 1340:2003 with 100mm upstand. capping material to regulate existing site levels to design 125 x 150mm Type BN PCC kerb to formation of porous asphalt road construction. BN New ACO channel drain to be BS EN 1340:2003 with 0-25mm upstand. - Soakaway sizing is subject to in-situ percolation testing Existing petrol interceptor to be installed in place of existing, re-using cleaned and de-sludged for re-use. existing outlet connection to existing 125 x 255/150mm Type DL1 & DR1 PCC kerb to to confirm infiltration rates in accordance with BRE Digest surface water drainage network. DK Existing condition to be surveyed BS EN 1340:2003 with 100 down to 25mm upstand. 365. and confirmed by Contractor and ACO M150D 0.0 or similar approved. - Manhole covers to be taken up and re-layed regulated to findings reported to the Engineer. 50 x 150mm Type EF PCC edging to EF suit final surface levels. BS EN 1340:2003 laid flush. 6.46 6.35 LC Former Crown 6.36 Ex.SW 1 6.75 Zone of infiltration within footprint of former Court Building Ø CL 6.39 IL TBC building, subsequently demolished. 0 Ex.SW 2 1/2 10 0 Existing surface water drain to be reused. CL 6.53 54 0Ø IL 6.08 10 55 New channel drain to be installed on LC

1/20 7.325 56 existing outlet

1/20 57 Buried Tank Soakaway;

1/ 58

25 30 year return period Ex.SW 3 59 CL 7.10, IL 5.50 6.975 CL 6.57 60 A: 27.0 x 8.0m = 216.0m²

3 IL 4.95

1/8 61 V: 216.0 x 0.8m dp = 164.2m³ 62 Wavin 'Aquacell Core' 1.0 x 0.5 x 0.4m units 63 (95% void ratio)

150Ø 1/9 52 53 7.30

0 7.19 HB2 LC

1/9 7.285 7.20 7.19 7.19 42 43 44 HB2 45 46 47 48 49 50 7.30

51 7.37 7.20 7.15 7.15 64 7.30 Ex.SW 4

1/120 0

1/120 1/9 CL 6.82 LC 7.45 IL 3.62 7.21

7.687.64 7.10 7.10 150Ø 1/124

1/5 5 7.10 34 35 36 37 38 39 40 41 31 32 33

7.2514 15 16 17 18 19 7.175 1/120 LC HB2 7.10 LC HB2 7.10 7.10 28 HB2 29 30 LC 20 21 HB2 22 23 24 25 7.10 26 27 PRELIMINARY CI

1/8 0 0 1/58 1/4 7.515 7.265 VI

LC Ex.SW 5 7.205 C

CL TBC IL 3.50 DR

1/120 1/120 IV

Approximate location of existing buried manhole. To be confirmed on site and 30

HB2 E

0Ø

confirmed to the Engineer. 3 4 5 6 7 8 9 10 11 12 13 2 1/2

1 21

P1 09.02.16 Fist issue. JS -

Revision: Date: Description: Drw: Chk: 7.25 7.305 7.25 7.25

1/25

1/45 Ex.SW 6 CL 6.80 (7.14) (7.21) IL 3.41

Vision, form and function (7.00) (7.04) Cambridge Billericay Compass House, Vision Park C TB

Cambridge Chivers Way, Histon Cambridge CB24 9AD Ø

Colchester

T RE ET London T: 01223 965200

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 05: 16-00156Report 2 MB DownloadRead as text
PDF
PD/15/16 Item 5: Application IP/16/00156/FPI3Report 527 KB Download

At this meeting

Whole meeting

Who was there

13 of 14 attended
PG
Councillor Peter GardinerChair, present
BQ
Councillor Bill QuintonVice-Chair, present
SG
Councillor Sandra GageCommittee Member, present
AG
Councillor Albert GrantCommittee Member, present
AH
Councillor Andi HopgoodCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
BK
Councillor Bill KnowlesCommittee Member, present
CK
Councillor Colin KreidewolfCommittee Member, present
BR
Councillor Bryony RudkinCommittee Member, present
JC
Councillor John CarnallCommittee Member, apologies, sent representative
DG
Councillor David GoldsmithCommittee Member, present
EH
Councillor Elizabeth HarsantCommittee Member, present

All 14 on the meeting page

On this subject at Ipswich

Search all
  1. PD/15/16 Item 5 - Application IP/16/00156/FPI3This decision
  2. PD/26/01 Item 5 - Application IP/26/00156/FPI3Approved
  3. PD/25/07 Item 2 - Application IP/25/00377/FPI3Approved
  4. PD/25/02 Item 7 - Application IP/25/00348/FPI3Decided
  5. PD/24/12 Item 3 - Application IP/25/00097/FPI3Decided
  6. PD/24/11 Item 3 - Application IP/25/00019/FPI3Approved

More from Ipswich Planning & Development Committee

All decisions
MeetingDecisionOutcome
29 Jul 2026 Unconfirmed Minutes of Previous Meeting - 1 July 2026that the Minutes of the meeting held on 1 July 2026 be signed as a true record. Decided Open
29 Jul 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
29 Jul 2026 PD/26/03 Information for Councillors, including Planning Enforcement Updatethat the information for Councillors be noted. Noted Open
1 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 3 June 2026 be signed as a true record. Decided Open
1 Jul 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies