Resolved
that the Minutes of the meeting held on 13 September 2017 be signed as a true record.
Central Area Committee decided this item on Wednesday 8 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Minutes of the meeting held on 13 September 2017 be signed as a true record.
CENTRAL AREA COMMITTEE MINUTES WEDNESDAY 13 SEPTEMBER 2017 IPSWICH COMMUNITY CHURCH, CLARKSON STREET, IP1 2JP 7.00 PM
Present: Alexandra Ward Councillors: J Riley St Margaret’s Ward Councillors: O Holmes, I Lockington and L Reynolds Westgate Ward Councillors: J Gibbs, C Jones and C Kreidewolf SCC Councillors: C Chambers, I Lockington, M Gaylard
There were 39 members of the public in attendance.
17. Apologies for Absence
Apologies for absence were received from Councillor Cook, Councillor Leeder and County Councillor Abbott.
18. Unconfirmed Minutes of Previous Meeting
18.1Minute 7.1: The Chair reported the reference to ‘Ipswich Umbrella Trust’ should be replaced with ‘Chapman Centre’.
Resolved:
that, subject to the correction above, the Minutes of the meeting held on 19 July 2017 be signed as a true record.
19. To Confirm or Vary the Order of Business
Resolved:
that the Order of Business be confirmed as printed on the Agenda.
20. Declarations of Interest
There were no declarations of interest.
1 21. To Confirm the Venues of Future Meetings
21.1The Chair reported that there had been availability issues with venues in the St Margaret’s ward for the November meeting and proposed that the November meeting be held in Alexandra ward and the January meeting be held in the St Margaret’s ward, and this was agreed.
Resolved:
that the meetings and venues be confirmed as follows:
Wednesday 8 November 2017, 7pm – Alexandra ward Wednesday 17 January 2018, 7pm – St Margaret’s ward Wednesday 7 March 2018, 7pm – Westgate ward
22. Presentation: Upper Orwell Crossings Update
22.1The Chair introduced [name removed], Project Manager for the Upper Orwell Crossings, who gave a presentation with the following key points:
Informal consultation was undertaken last year on the proposal for the 3 Upper Orwell Crossings in order to raise awareness of this project and its objectives and to hear local concerns. Over the last year, surveys have been undertaken relating to environment, habitats, air quality, noise, river bed and transport modelling. Options for the location of the bridges and their alignment were still being considered. Foster and Partners won the tender competition to be the Architectural Team for the project.
Next stages include: boat surveys (to assess the dimensions of vessels and determine bridge clearance levels); concept design development and transport modelling; ongoing land discussions and ground investigations – a compound has been established on the east of the site; focus group consultations and a further 6-week public consultation on a similar basis to the 2016 consultation; submission for Development Consent Order (DCO) in 2018 (decision would take approximately 18 months) – decision would be made by the Secretary of State; if approved, start construction in 2020, which would take 2-3 years.
22.2Further information on the Upper Orwell Crossings Project could be found at: www.suffolk.gov.uk/UpperOrwellCrossings, with contact details as follows: email: [email protected], phone: 0345 603 1842.
2 22.3. Councillor Kreidewolf: Can the County Council manage a project of this scale? This was a major project, but there was a large project team with specialist support in place for all areas, e.g. legal, land, contract specialists, and would be undertaken on a design and build approach. Lessons were learnt from the Travel Ipswich project and Suffolk County Council (SCC) was confident that this project could be delivered.
22.4Local resident: The main bridge will be an open-sided structure – will this need to be closed in high winds like the Orwell Bridge? High winds would be taken into consideration as part of the design process. A swing bridge was being considered and the height of the bridge would not be as high as the Orwell Bridge, so the wind should not stop it from operating.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Unconfirmed Minutes of Previous MeetingMinutes | 126 KB | DownloadRead as text |
Follow Central Area Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jan 2025 | Unconfirmed Minutes of Previous Meeting held on 30 October 2024that the Minutes of the meeting held on 30 October 2024 be signed as a true record. | Decided | Open |
| 15 Jan 2025 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda . | Decided | Open |
| 15 Jan 2025 | Responses to Public QuestionsIt was agreed that the issues regarding speeding would be raised with the Police at the next Central Neighbourhood Pa... | Agreed | Open |
| 15 Jan 2025 | CAC/24/07 Area Committee Budget Updatethat the financial statement in Appendix 1 to the report be noted. Reason: To provide clear and transparent details o... | Noted | Open |
| 30 Oct 2024 | Unconfirmed Minutes of Previous Meeting held on 4 September 2024that the Minutes of the meeting held on 4 September 2024 be signed as a true record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.