Resolved
That the funding conditions be varied to allow funds to be released, as Phase Two of the works had been completed.
South East Area Committee decided this item on Wednesday 16 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the funding conditions be varied to allow funds to be released, as Phase Two of the works had been completed.
2.1As outlined in the original request the Club is redeveloping its existing pavilion to a new structure of approximately twice the size with better amenities.
Figure 1 proposed floor plan
2.2The Club has been awarded £1,500 by the Committee. The award was made with the condition that “The release of any award will be conditional on the remaining funding having been secured from other sources. The commitment may be held for a maximum of 3 years, from the date of the decision.” (Appendix 1, Para 9.3)
2.3The Club is seeking a variation for this condition to be removed.
2 2.4 The Club has completed the first and second phase of work, laying the foundations and erecting the pavilion extension. It was able to save money on the first phase by members undertaking some of the work. This reduced the cost from an estimate of £9,000 to a spending of £4,188. The Club acquired a better quote for the second phase, reducing the estimate of £12,894 to a spending of £10,540. This represents a saving of £7,166.
Figure 2 Works underway
2.5The revised cost of phases one and two (commitment to date) is £14,728. £10,000 of this was met through of the Club’s own savings, £2,750 through County Councillor Locality funding (£750 from Cllr Quinton, £500 Cllr West, and £1,500 from Cllr Clements) and the remaining shortfall of £1,978 through delayed payment terms and continued contributions from the Club’s membership. The Club plans to use the Committee funding to reduce the shortfall to £478.
2.6The final phase will be to install the new amenities and fittings for a combined cost of £17,359.90. The Club plans to use the external grants currently under consideration to complete the final phase of works.
2.7A number of applications are under consideration with external funders;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SEAC/18/25 Variation to Funding Request Margaret Catchpole Bowls Club Pavilion ExtensionReport | 604 KB | DownloadRead as text |
Follow South East Area Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jan 2025 | Unconfirmed Minutes of the Previous Meeting held on 6 November 2024that the Minutes of the meeting held on 6 November 2024 be signed as a true record. | Decided | Open |
| 8 Jan 2025 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 8 Jan 2025 | SEAC/24/07 Area Committee Financial Updatethat the financial statement in Appendix 1 of the report be noted. Reason: To provide clear and transparent details o... | Noted | Open |
| 6 Nov 2024 | Unconfirmed Minutes of the Previous Meeting held on 11 September 2024that the Minutes of the meeting held on 11 September 2024 be signed as a true record. | Decided | Open |
| 6 Nov 2024 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.