Ipswich Borough Council Planning Enforcement Q2 2019
1.0Introduction
1.1This report provides members with an update for Ipswich Borough Council’s Planning Enforcement performance for the second quarter 2019. 1.2 At the end of the second quarter of 2019, there have been no new reports of HMO’s being developed in Ipswich although we remain cautiously optimistic and continue to monitor and respond to any potential development sites. 1.3 The reduction in HMO investigations has meant Planning Enforcement has had capacity to review some of its more protracted and historic cases, some of which have been detailed in this report. 1.4 Regionally other planning authorities have encountered significant issues where serviced apartments such as through Airbnb are being operated. The types of issues include where planning permission has been granted for a property to be developed into separate multiple dwellings and then become short term lets, for two to three days at a time. 1.5 These properties can attract a range of illicit activities, including the occupants holding loud parties over extended periods. The first case was recently identified within IBC area at an apartment within St Edmunds House, Rope Walk, which has since been resolved satisfactorily, but the team remains vigilant on this matter and would welcome any relevant information.
2.0Cases Update 2.1 Total number of cases still under investigation at the end of March 2019. 55
Total number of cases recorded in the fourth quarter Jan-March 2019 40
Total number of cases finalised in the fourth quarter Jan-March 2019 26
2.2Ararat Restaurant 18 Norwich Road
In April 2018, the Ararat Restaurant 18 Norwich Road, erected a roof top conservatory structure intended for use as an extension to their main restaurant. This structure requires planning permission. The strcuture was inspected by IBC Building Control who deemed it unsafe. It was considered that the section of the building supporting the structure would require engineering work before Building Regulations approval would be granted.
2.3A planning application and building regulatiosn application have been subsequently submitted.
2.4Planning Enforcement have been engaging with the owners of the restaurant in order that the respective engineering reports could be submitted, in order to satisfy Building Control. The requisite information has taken some considerable time to arrive, and following the threat of formal enforcement action, it is with the BC team for consideration.
2.5The planning application has now been amended with the submission of revised drawings and the engineers report and is still under consideration, with the aim of determining it presently.
2.6New Cut West
A large untidy site to the south of the Steam Boat Tavern, on Mather Way and New Cut West was recently identified to the enforcement team by Environmental Health. Planning Enforcement engaged with the owner who promised to clear the site and a recent follow up visit has confirmed the site has now been cleared and is tidy.
2.75 Coniston Square and 157 Bramford Lane
Two HMO developments at 5 Coniston Square and 157 Bramford Lane, were found to be in a very dangerous condition. These properties are linked to several other HMO developments in the town and whilst under conversion important structural supports were removed leaving them vulnerable to collapse.
2.8Planning Enforcement intervention resulted in both properties having been made safe by a reputable building company. These still require significant renovation, which we are optimistic the same building company will complete within a relatively short time frame. The Senior Enforcement officer is monitoring these developments.
2.9Restaurant 16 Tacket Street
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PD-19-08 Appeal Decision 147-149 Whitby RoadDecisions | 116 KB | Download |
PDF |
PD-19-08 Appeal Decision 7 Summerfield CourtDecisions | 94 KB | Download |
PDF |
PD-19-08 Appeal Decision 7 Summerfield Court: CostsDecisions | 87 KB | Download |
PDF |
PD-19-08 Enforcement Update: 2019 Quarter 2Report | 134 KB | DownloadRead as text |
PDF |
PD/19/08 Information for CouncillorsReport | 17 KB | Download |
Follow Planning & Development Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Unconfirmed Minutes of Previous Meeting - 1 July 2026that the Minutes of the meeting held on 1 July 2026 be signed as a true record. | Decided | Open |
| 29 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 29 Jul 2026 | PD/26/03 Information for Councillors, including Planning Enforcement Updatethat the information for Councillors be noted. | Noted | Open |
| 1 Jul 2026 | Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 3 June 2026 be signed as a true record. | Decided | Open |
| 1 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.