CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Ipswich Borough Council
Executive, Tuesday 29 October 2019 at 6.00pm

E/19/38 Eastern Gateway Infrastructure Contracts

Approved Executive 1 paper

Executive approved this item on Tuesday 29 October 2019. Below is the council's own wording, with the papers it was decided on.

Item75

Resolved

a) that the acceptance of the quotation submitted by UKPN for the sum of £212,595.00 be approved and that the Head of Development, in consultation with the Operations Manager for Legal Services, be authorized to enter into a contract with the recommended provider as set out in this report. Reason: To enable the timely delivery of the power supply to meet delivery requirements. b) that the decision above (a) be exempted from Contract Standing Orders. Reason: To enable the appointment of a single supplier able to conduct all the work associated with the supply of electricity to the site. c) that the allocation of the phase 2 roadways project budget as shown in paragraph 8.2 (from existing budgetary allocations) be agreed and that the Head of Development be authorised to enter into a works contract in consultation with the Head of Governance, Leader of the Council, Chief Executive and S151 Officer, subject to the returned tenders being within the project budget above. Reason: To enable the appointment of a works tender to be made in sufficient time to allow for the necessary work to be completed in accordance with terms agreed with the proposed purchaser. d) that the above decision (c) be certified as urgent and exempt from call-in. Reason: To enable the appointment of the contractors to be made in sufficient time to allow for the necessary work to be completed in accordance with terms agreed with the proposed purchaser. The decision to make the appointments is urgent as the infrastructure for Phase 2 of the site must be completed by 31/03/2020 to comply with the proposed next land sale agreement. If the appointment is delayed it is highly unlikely that these works would be completed in time. There is also the risk of reputational damage to the Council if the infrastructure works are not completed. The impact of any delay in the appointment of the contractor could be considered to prejudice the Council’s and the public’s interest given it could lead to the Council being in breach of contract with subsequent financial consequences. e) that £1,605,441 of existing budget for the project be brought forward from future financial years into 2019/20 in order to enable the rapid delivery of the next proposed land sale enabling works. Reason: To enable appropriate resources to deliver the required Project Rio infrastructure contracts. f) that the award for post contract management ( inc. Project management) fees for ... view the full minutes text for item 75.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Executive

COMMITTEE: EXECUTIVE 9 REF NO: E/19/38 DATE: 29 OCTOBER 2019 SUBJECT: EASTERN GATEWAY – INFRASTRUCTURE CONTRACTS PORTFOLIO HOLDER: COUNCILLOR DAVID ELLESMERE HEAD OF SERVICE: MARTYN FULCHER Short description of report content and the decision requested: To enable the delivery of the infrastructure works at the Eastern Gateway site to serve the next occupier, Ipswich Borough Council is required to provide a fully serviced site, including a new power supply, new access road and drainage.

This report recommends that Executive grants approval of the quotation received from UKPN for the 1.75MVA supply and an exemption from contract standing orders. It also seeks approval to agree the budget for the next phase of conducting work on the access road and attenuation basin ahead of tender returns and authorises officers to award the contract should tenders be returned within budget and, as the award of this contract is urgent, to exempt the decision from call in.

In addition, it also requests authorisation to award post contract design and project management fees to the existing design team and to award a small three stage contract for groundwater investigations to Geosphere Ltd.

Ward(s) affected: None – Out of Borough List of Appendices included in this report: None This report has been prepared by Mark Hunter Tel: 01473 43 2808, Email: [email protected] This report was prepared after consultation with: Internal consultees Head of Development Legal Services Financial Services Property Services The following policies form a context to this report: (all relevant policies must also be referred to in the body of the report)

Building a Better Ipswich 2017

LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (papers relied on to write the report but which are not published and do not contain exempt information)

N/A OTHER HELPFUL PAPERS (papers which the report author considers might be helpful – this might include published material)

Planning Permission - Application Reference: DC/17/06058 Disposal of Land at Eastern Gateway - REF NO: E/17/86 Appointment of Infrastructure Contractor - REF NO: E/18/19 ______________________________________________________________ 1. Introduction

1.1Ipswich Borough Council purchased the former British Sugar site in 2014, with a view to redeveloping the land for employment purposes. In February 2017, Executive approved a masterplan for the site, which included developing the whole site for employment uses, showing road layouts, landscaping and drainage areas.

1.2The first phase of the infrastructure delivery is now complete, with the main spine road, foul and surface water drainage systems, street lighting, Section 278 works all being completed on programme to serve the Park’s first occupier; La Doria (LDH).

1.3The Council is in advanced negotiations with a second occupier, who also has a very ambitious programme for delivery of its works, which will affect the timescales for the delivery of the next phase of infrastructure, to be provided by IBC.

1.4The infrastructure works required comprise the main east/west cross road, installation of all supporting services, (power, gas water, communications), as well as foul and surface water drainage which need to be completed by April 2020.

1.5As part of this, IBC has received a quotation from UK Power Networks (UKPN) for the supply and installation of a 1.75MVA power supply.

1.6UK Power Networks own and maintain electricity cables and lines across London, the South East and East of England and as a result an exemption from Contract Standing Orders is sought on the basis this is a single supplier for the work.

1.7The report also seeks approval to delegate the award of a contract for the Phase 2 works to the winning bid of the current tender if the bid is within the budget agreed by the Executive.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E/19/38 Eastern Gateway Infrastructure ContractsReport 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
DE
Councillor David EllesmereLeader, present
BR
Councillor Bryony RudkinDeputy Leader, apologies
SB
Councillor Sarah BarberCommittee Member, present
MC
Councillor Martin CookCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
NM
Councillor Neil MacDonaldCommittee Member, present
SM
Councillor Sophie MeudecCommittee Member, present
AR
Councillor Alasdair RossCommittee Member, present
PS
Councillor Philip SmartCommittee Member, present
IF
Councillor Ian FisherCommittee Member, present

On this subject at Ipswich

Search all
  1. E/19/38 Eastern Gateway Infrastructure ContractsThis decision
  2. E/24/28 Eastern Gateway Land SaleDecided
  3. E/24/15 Eastern Gateway - Phase 2c (Roundabout) Enabling Works for Openreach to Divert Fibre CableDecided
  4. E/23/57 Eastern Gateway - Phase 3 Power Main Contractor ProcurementDecided
  5. E/23/41 Eastern Gateway Land SaleDecided
  6. E/23/10 Eastern Gateway Land SaleDecided

More from Ipswich Executive

All decisions
MeetingDecisionOutcome
11 Aug 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 14 July 2026 be signed as a true record. Decided Open
11 Aug 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
11 Aug 2026 E/26/14 Competence and Conduct Policy for Housing Servicei) that Executive approves, adopts and publishes the Competence and Conduct Policy (Housing) appended to the report a... Approved Open
11 Aug 2026 Exclusion of Publicthat the public (including the Press) be excluded from the meeting during consideration of the following items under ... Decided Open
14 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 16 June 2026 be signed as a true record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies