Resolved
that the content of the update report and future actions be noted.
Planning & Development Committee noted this item on Wednesday 26 August 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
that the content of the update report and future actions be noted.
2.1EDF Energy are seeking the Grant of a Development Consent Order (DCO) to construct Sizewell C Nuclear Power Station.
2.2There have been four rounds of formal consultation by EDF Energy for the proposed Sizewell C (Stages 1, 2, 3 and 4).
2.3IBC provided formal consultation responses to Stages 2, 3 and 4 all of which were presented to the Planning & Development Committee for discussion prior to submission.
2.4IBC have also provided a formal consultation response on the Scoping Opinion for the Environmental Statement to accompany the DCO (June 2019).
2.5IBC has most recently provided a formal response to the Adequacy of Consultation Request by PINS (June 2020). This confirmed that the required consultation, in line with legislation, had been undertaken with IBC.
3.0Current Stage:
3.1On the 27th May 2020 EDF Energy submitted an application to the Secretary of State Planning Inspectorate (PINS) for a Development Consent Order (DCO) for Sizewell C, having undertaken the necessary pre-submission consultation.
3.2PINS accepted the application as having been adequately consulted upon on the 24th June 2020, meaning it could move to the next stage in the process.
3.3The Sizewell C DCO proposal is now in its Pre-Examination Stage, and the timetable will now be dictated by PINS.
3.4EDF have to publish a notice under Section 56 of the DCO regulations. This is not a public consultation but provides time to read the application and for anyone to notify PINS that they wish to be registered as an interested party.
3.5IBC are not automatically notified of the DCO or logged as an interested party (this was changed by the 2011 Localism Act). East Suffolk and SCC are automatically interested parties as the proposal is within their administrative boundaries. 3.6 As an interested party any written representation submitted when you register will be read as part of the Examination. There would also be the opportunity to provide further written representation through the Examination and the Inspectorate may request the interested party to attend relevant hearings.
3.7The PINS website confirms the time period to register as an interested party opened on the 8th July and ends at 23:59 on Wednesday 30th September 2020.
3.8The DCO Examination is expected to commence Autumn – Winter 2020.
4.0IBC’s Formal Consultation Responses: 4.1 The Inspector determining the DCO will not have seen IBC’s full formal consultation responses to Stages 2, 3 and 4. 4.2 EDF Energy is only required to summarise comments received as part of the Formal Consultation Stages within a Consultation document. This summary forms part of the application submission to PINS. 4.3 It is considered by officers that the summaries within the EDF’s Consultation Document do reflect those concerns that had been raised by IBC. 4.4 The following are the relevant extracts from EDF Energy’s Consultation Summary of IBC’s formal consultation responses: Stage 2:
1.21.1 Ipswich Borough Council believed a lack of consideration had been given to the use of clean energy and reducing CO2 emissions of construction. They requested that as little as possible of the construction materials should leave the main development site.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PD/20/06 Sizewell C Nuclear Power StationReport | 331 KB | DownloadRead as text |
Follow Planning & Development Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Unconfirmed Minutes of Previous Meeting - 1 July 2026that the Minutes of the meeting held on 1 July 2026 be signed as a true record. | Decided | Open |
| 29 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 29 Jul 2026 | PD/26/03 Information for Councillors, including Planning Enforcement Updatethat the information for Councillors be noted. | Noted | Open |
| 1 Jul 2026 | Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 3 June 2026 be signed as a true record. | Decided | Open |
| 1 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.