Ipswich Borough Council Planning Enforcement Q2 – 2020/2021
1.0Introduction
1.1This report provides Ipswich Borough Council’s Planning Enforcement performance for the second quarter of 2020/2021.
1.2This quarter has been comparative to previous years in terms of referral numbers with things returning to some normality, following the initial surge of referrals, when lockdown was introduced in March.
1.3Enforcement investigations have continued to be undertaken in accordance with the restrictions on social distancing that are in place. However with the use of technology (photographs and plans being sent via email), in most cases enough information was able to be provided electronically for accurate decision making on enforcement matters.
1.4With regards to investigations, there will always be cases where unannounced or covert site visits are required, and these are continuing where necessary with a risk assessment being completed in advance, meaning these are pre-planned with management oversight, to minimise identifiable risks.
1.5Planning Enforcement is currently having to adapt to the recent changes in planning legislation and it is too early to assess the impact. But it is likely to present some new challenges particularly with HMO conversions and the scope for constructing an additional storey on domestic properties. It is anticipated the changes will generate an initial increase in enforcement referrals as people realise development changes occurring, such as bungalows potentially being converted into houses under the new rules. 2.0 Cases Update 2.1 Total number of cases under investigation at the 63 end of Sep 2020. Total number of cases recorded in the second 22 quarter July - Sept 2020 Total number of cases finalised in the second 8 quarter July - Sept 2020
2.2As in the last quarter report, the overriding theme of enforcement investigations in this quarter has again seen an increase in garden outbuildings emerging across the borough. Some of these are very large structures and breaches in planning legislation have been identified.
These buildings are being used for wide range of uses including games rooms, music studios and offices and although there have been several concerns regarding residential occupation, none been identified as being used for this purpose.
3.0Enforcement Cases of note
29 Dunwich Close
3.1At the end of March an enforcement complaint was received regarding a large structure being constructed in the rear garden of 29 Dunwich Close, which is approximately 7m in length x 3m width and 3m in height. The occupant states this is ancillary to their enjoyment of the main dwelling and in their opinion is compliant with the definition of a caravan under the Caravan Act of 1968.
This structure has now been inspected on site by the Planning and Development Operations Manager and the Senior Planning Enforcement Officer following social distancing measures and an investigation report is currently being considered.
Planning Enforcement will provide an update to this case in the next quarter report.
16 Fairfield Road
3.2This address relates to a very large partially constructed block-built outbuilding which was highlighted in the last quarterly report as requiring planning permission. Following Planning Enforcement intervention, a retrospective planning application was received and following careful consideration full planning permission has been granted (20/00373/FUL refers). 1 Ellenbrook Green
3.3Following information received from the Councils Environmental Health team that people were residing in rooms at the rear of this premises which is a retail food store, planning enforcement intervened.
The owners were given 28 days to restore the shop to its original use and a subsequently unannounced visit confirmed the unauthorised residential use had ceased and the rooms were restored to storage areas.
5 Coniston Square
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PD-20-08 Planning Enforcement Report 2020-21 Quarter 2Report | 129 KB | DownloadRead as text |
PDF |
PD/20/08 Information for CouncillorsReport | 15 KB | Download |
Follow Planning & Development Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2026 | Unconfirmed Minutes of Previous Meeting - 1 July 2026that the Minutes of the meeting held on 1 July 2026 be signed as a true record. | Decided | Open |
| 29 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 29 Jul 2026 | PD/26/03 Information for Councillors, including Planning Enforcement Updatethat the information for Councillors be noted. | Noted | Open |
| 1 Jul 2026 | Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 3 June 2026 be signed as a true record. | Decided | Open |
| 1 Jul 2026 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.