Resolved
that the Minutes of the meeting held on 4 November 2020 be signed as a true record.
South East Area Committee decided this item on Wednesday 13 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
that the Minutes of the meeting held on 4 November 2020 be signed as a true record.
SOUTH EAST AREA COMMITTEE MINUTES WEDNESDAY 4TH NOVEMBER 2020 VIRTUAL MEETING 7.00 PM
Present: Gainsborough Ward Councillors: S Connelly, M Cook and S Handley Holywells Ward Councillors: E Harsant, J Parry and B Studd Priory Heath Ward Councillors: S Barber and L Richardson
SCC Councillors M Gaylard and B Quinton
29. Apologies for Absence
Apologies for absence were received from Councillor Maguire.
30. Unconfirmed Minutes of the Previous Meeting
Resolved:
that the Minutes of the meeting held on 2 September 2020 be signed as a true record.
31. To Confirm or Vary the Order of Business
Resolved:
that the Order of Business be confirmed as printed on the agenda.
32. Declarations of Interest
Councillor Harsant reported that she had a Local Non Pecuniary Interest in item 7 as Vice-Chair of the IP3 Good Neighbour Scheme.
1 33. Responses to Public Questions
33.1The Chair reported that 2 questions had been received from local residents.
33.2Question 1: - Is it not policy of the Council that when road works are carried out if there are small businesses within that road to ensure that there is suitable signage that businesses are open with access and workable diversions, not what happened when Cliff Lane was resurfaced when delivery lorries and customers were turned around to follow diversion signs. - Why is it that despite making a formal request over the telephone to speak to the person in charge of roadworks as to what the businesses in Cliff Lane have had to put up with for a week, no one has contacted us as we would not like to see other shopping parades suffer in the same way. No access, No customers resulting in shops closing.
33.3Suffolk County Councillor Paul West provided the below response: Having spoken with one of our Customer Liaison Coordinators and looking back at our records and a review of the call made to Suffolk Highways, we can report as follows: - The original contact was around access for deliveries and ‘Business Open as Usual’ boards (13/07). - Follow up calls (24/07 & 27/07) further requests for ‘Business Open as Usual’ boards and comment that customers are concerned about whether they can access the shops. The records show no mention of customers or deliveries being declined access by staff on site. - 28/07 reported that a delivery was turned away – it would appear from what I can determine that the section of road outside the shops had physically had machinery operating in it and therefore road access could not be given at that specific time (there will be occasions where parts of a road are closed but managed access can be given where there is no danger presented by operational activity. A request was made on that call to speak with the site works manager to discuss further. The customer was advised that this cannot be promised but a request will be forwarded to the site works manager.
Pedestrian access to the shops would not have been prevented due to the wide footways with guidance offered by Pedestrian Management Operatives on-site.
It would be normal practice to install ‘Business Open as Usual’ boards on a site such as this. It doesn’t appear that any photographs were taken of the site, prior to works commencing, and therefore we are unable to ascertain whether these signs were in-situ and/or whether the request was for signs over and above those that were provided. Suffolk Highways can confirm that our records detail that additional signage was provided on-site following contact by the customer.
It would appear that the site works manager did not make contact with the customer. We can only apologise that this was the case, it would be usual for
2 that individual to do so. We are not in a position to explore that further as that works manager has left Suffolk County Council’s contractors, Kier.
Suffolk Highways do empathise that maintenance works can be disruptive, however it is essential that these works were carried out and we work to do our best to reduce the impact on local businesses.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Unconfirmed Minutes of the Previous MeetingMinutes | 304 KB | DownloadRead as text |
Follow South East Area Committee at Ipswich and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Jan 2025 | Unconfirmed Minutes of the Previous Meeting held on 6 November 2024that the Minutes of the meeting held on 6 November 2024 be signed as a true record. | Decided | Open |
| 8 Jan 2025 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
| 8 Jan 2025 | SEAC/24/07 Area Committee Financial Updatethat the financial statement in Appendix 1 of the report be noted. Reason: To provide clear and transparent details o... | Noted | Open |
| 6 Nov 2024 | Unconfirmed Minutes of the Previous Meeting held on 11 September 2024that the Minutes of the meeting held on 11 September 2024 be signed as a true record. | Decided | Open |
| 6 Nov 2024 | To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.