a) that the Assistant Director for Housing and Community Services, in consultation with the Housing and Resources Portfolio Holders, the Section 151 Officer, Legal Services Operations Manager and the Procurement Manager, be authorised to progress the procurement of additional contractors for void property works. Reason: To enable the Council to receive and evaluate bids from appropriate contractors. b) that the Assistant Director for Housing and Community Services, in consultation with the Housing and Resources Portfolio Holders, the Section 151 Officer, Legal Services Operations Manager and the Procurement Manager, be authorised to enter into contracts with successful bidders for a term of 12 months and within the budget set out in Section 10 of the report. ... view the full minutes text for item 76.
Word for word from the decision Ipswich published for this meeting.Source: democracy.ipswich.gov.uk
COMMITTEE: EXECUTIVE 6 REF NO: E/22/35 DATE: 1 NOVEMBER 2022 SUBJECT: HOUSING – PROCUREMENT OF VOID CONTRACTS PORTFOLIO HOLDER: COUNCILLOR NEIL MACDONALD SENIOR OFFICER: GAVIN FISK Short description of report content and the decision requested: This report details the requirement to procure void support contracts to ensure capacity is maintained to deliver services.
Executive is asked to approve the delegation to senior officers to progress with the procurement and, once complete, award contracts to the most economically advantageous bid(s) within the agreed HRA budget.
Executive is also asked to consider the approval of the Voids Contractor budget for the 2023/24 financial year.
Ward(s) affected: All List of Appendices included in this report: N/A This report has been prepared by Justin Wright-Newton, Tel: 01473 432452, Email: [email protected] This report was prepared after consultation with: Internal consultees Assistant Director - Housing & Community Services Assistant Director - Governance Operations Manager Maintenance & Contracts Business Service Accountant Assistant Operations Manager – Procurement Lead Lawyer – Legal
The following policies form a context to this report: Building a Better Ipswich 2017 LIST OF BACKGROUND PAPERS AS REQUIRED BY LAW (Papers relied on to write the report but which are not published and do not contain exempt information)
None
OTHER HELPFUL PAPERS (Papers which the report author considers might be helpful – this might include published material)
1. Housing Repairs & Voids Contracts – Executive E/21/38 2. Out-Turn Report for 2021/22 Financial Year – Executive E/22/06 (paragraphs 8.7 to 8.11) ______________________________________________________________ 1. Executive Summary
1.1The Council is responsible for maintaining, repairing, and improving its housing stock to meet the Government’s Decent Homes Standard and the Council’s higher Ipswich Standard.
1.2The housing repairs and maintenance service employs direct labour to refurbish homes that become empty when a tenancy ends. The empty property is known as a void. Properties are refurbished to the Ipswich Voids Standard and re-let.
1.3The Council continues to experience a high demand in the voids service.
There is a 17% increase (to date in 2022/23) in the number of voids. Tenancies ending have averaged 8.2 per week since April 2022 compared to a pre-Covid rate of 7 per week
Property condition (upon vacant possession) has deteriorated, compared to pre-Covid, meaning there is more work to complete in each void to bring it back up to the Voids Standard (this is measured by the number of A, B, C, D type voids, type A being the least work, D the most). C type voids have increased by 47% and D Type Voids have increased by 144% compared to pre-Covid
1.4The increase in void demand has occurred during and since the Covid pandemic. It is expected that households spending more time in the home and the inability for physical house inspections during the pandemic have been key factors in these changes.
1.5As void demand continues, the working assumption is the service needs to be aligned to the “new normal” service demand levels. Therefore, this report identifies the additional capacity needed to maintain service standards, which proposes using a hybrid approach of directly employed teams and support contractors.
1.6Executive are asked to consider the procurement of support contractors and this recommended approach has the benefit of ensuring voids are let as quickly as possible, backlogs will not re-occur and provides resilience and flexibility to cope with any peaks in demand.
1.7The intention is to review the position at the end of 12 months to consider whether the higher demand levels have continued and if so to review options to either increase the in-house capacity or continue with additional contractor support. 2. Background
Voids
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.