E/23/56 IP City Mechanical & Electrical (M&E): Main Contractor Procurement and Planning Strategy

Decided Executive 2 papers

Executive decided this item on Tuesday 5 March 2024. Below is the council's own wording, with the papers it was decided on.

Item120

Resolved

that Executive: a) authorises the Head of Major Capital Schemes, in consultation with the Head of Legal and Democratic Services and the Head of Procurement, to progress with the procurement of a Main Contractor for the IP City Heating and Cooling replacement works phase 1. Reason: To enable the Council to receive and evaluate bids from appropriate lead consultants and to then design and deliver the project. b) authorises the Assistant Director for Place, in consultation with the Section 151 Officer, Head of Legal and Democratic Services, Head of Procurement, Portfolio Holder for Resources and Portfolio Holder for Place, to enter into a contract for the necessary Main Contractor services providing the preferred tenderer’s bid is within the proposed construction budget (details shown in exempt Appendix 1 to the report). Reason: To enable the contract to be executed and for the project to be designed and delivered. c) authorises the Assistant Director for Place, in consultation with the Head of Legal and Democratic Services and Head of Town Planning and Development, to develop and submit a planning application for the external plant should it be necessary. Reason: To enable the design for the project to be finalised and for the project to be delivered.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Executive

Background

2.1The MTFP provides the budgetary allocation for each future project that the Council is planning to deliver in the medium term. Prior to projects commencing on site, design and procurement activities need to take place.

2.2Within the agreed MTFP is a total budget of some £559,350 allocated to IP City, this is for replacement of part of the Mechanical and Electrical (M & E) systems (phase 1) and for front of house remodelling and café improvements (phase 2). (Budget split is shown in exempt Appendix 1).

2.3As IP City is wholly owned by the Council, the responsibility to replace the significant M & E systems etc. is a requirement of the landlord rather than individual tenants as it includes common areas and multiple units.

2.4The building is heated via an air conditioning system during the winter and the same system provides cooling during the summer. The air conditioning system is life expired, inefficient and requires replacement. Maintenance to the existing system is ongoing and tenants have reported issues with heat loss during colder months. The specification will include a suitable maintenance contract following the completion of the works on site.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E-23-56 Urgent Decision NoticeDecisions 89 KB Download
PDF
E/23/56 IP City Mechanical & Electrical (M&E): Main Contractor Procurement and Planning StrategyReport 359 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
NM
Councillor Neil MacDonaldLeader, present
BR
Councillor Bryony RudkinDeputy Leader, present
JC
Councillor John CookCommittee Member, present
MC
Councillor Martin CookCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
AR
Councillor Alasdair RossCommittee Member, present
PS
Councillor Philip SmartCommittee Member, apologies
IF
Councillor Ian FisherCommittee Member, present

On this subject at Ipswich

Search all
  1. E/23/56 IP City Mechanical & Electrical (M&E): Main Contractor Procurement and Planning StrategyThis decision
  2. E/22/42 IP-City Centre Mechanical & Electrical (M&E) Main Contractor ProcurementDecided

More from Ipswich Executive

All decisions
MeetingDecisionOutcome
11 Aug 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 14 July 2026 be signed as a true record. Decided Open
11 Aug 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
11 Aug 2026 E/26/14 Competence and Conduct Policy for Housing Servicei) that Executive approves, adopts and publishes the Competence and Conduct Policy (Housing) appended to the report a... Approved Open
11 Aug 2026 Exclusion of Publicthat the public (including the Press) be excluded from the meeting during consideration of the following items under ... Decided Open
14 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 16 June 2026 be signed as a true record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies