E/25/25 Framework for Corporate Building Maintenance

Decided Executive 1 paper

AI summaryIpswich Borough Council's Executive approved procurement of a 4-year Corporate Building Maintenance framework, with 15 lots, worth an estimated £7.22 million, with tenders in early December 2025 and contract awards April to June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedAmends August 2021 decision, authorises framework for corporate building maintenance
Money£7.22 million estimatedTotal framework value, 13% headroom over forecast spend
What happens nextTender in early December 2025Phased contract awards April to June 2026
Who it affectsCorporate building estateNon-housing properties such as Town Hall, leisure centres, crematorium

What was decided

The Executive amended its 10 August 2021 decision and authorised the Assistant Director for Place, in consultation with the Assistant Director of Finance, the Head of Legal Services, the Head of Property and the Head of Procurement, to progress the procurement of a Framework for Corporate Building Maintenance. Report 14.1

The Executive authorised the same officers, with the Portfolio Holders for Place and Resources, to enter into the Framework Agreement and subsequent call-off contracts for a term of up to 4 years following the procurement. Report 14.2

The Executive approved the budget requirements for regular maintenance, compliance and statutory inspection works, reactive and planned repairs for the corporate building estate. Report 14.3

Why

To enable the Council to receive and evaluate bids from appropriate contractors. Report P75

To enable the framework to be established, subsequent call-off contracts to be created and the works to proceed. Report P77

To be aware of the future budgetary requirements to be incorporated into the future MTFP. Report P79

What happens next

An open tender will be issued in early December 2025, with contracts for the 15 lots awarded on a phased basis between April and June 2026. Report 2.4, 2.14

Tenders will be evaluated on price and quality, with emergency lots weighted 20% price and 80% quality, using a 5-point scoring scale; bidders scoring less than 2 on any question will not progress. Report 2.10, 2.11

Financial, compliance and equalities checks will be completed before quality evaluation, with mandatory requirements on Living Wage, GDPR, certifications and equal opportunities policies. Report 2.5, 2.6, 8.4

The money

  • £7.22 million Total estimated value of the framework, including 13% headroom over forecast Report 2.13, 10.5
  • £1.411m Spend on repairs, maintenance and upgrade of corporate properties in 2024/25 and current budget basis Report 10.1
  • £1.482m Forecast budget for 2026/27 assuming 5% inflation Report 10.3, P53
  • £1.556m Forecast budget for 2027/28 assuming 5% inflation Report 10.3, P53
  • £1.634m Forecast budget for 2028/29 assuming 5% inflation Report 10.3, P53
  • £1.715m Forecast budget for 2029/30 assuming 5% inflation Report 10.3, P53
  • £6.387m Total forecast budget across 2025/26 to 2029/30 Report 10.3, P53

Options considered

  • Chosen: Option 1: Proceed with the procurement of the framework as detailed in the report. Allows specialist local contractors to work with the Corporate R&M Team, gives timely, cost effective works and greater opportunities for SMEs Report P25, P26, 4.2
  • Rejected: Option 2: Do not proceed and engage contractors on an ad-hoc basis. Would significantly increase officer time and procurement delivery time, lacks best value and creates continuity delays; not recommended on efficiency grounds Report P28, P29, P30

Implications

  • Financial: Total framework value estimated at £7.22 million, with 13% headroom over the £6.387m five-year forecast; existing 2025/26 budget expected to cover current contracts. Report 2.13, 10.3, 10.5
  • Legal: Procurement will follow the Procurement Act 2023 using the Central Digital Portal, with Contract Standing Orders and a Framework Agreement prepared by the IBC Legal Team; either party can terminate on 13 weeks' notice. Report 2.4, 11.2, 11.3, 11.5, 11.6
  • Equalities: Tender evaluation will require contractors to have robust equal opportunities policies; framework supports access to facilities for people of all abilities. Report 3.4, 8.4
  • Climate: Framework supports the Council's 2030 carbon neutral goal by enabling energy saving projects such as BMS and LED upgrades, use of low carbon materials, and waste reduction and recycling. Report 3.3, 7.2, 7.3
  • Risk: Identified risks include failure to meet H&S obligations, contractor financial failure, supply chain delays, contract overspends and lack of bidder interest; mitigation includes KPI monitoring, H&S enforcement, premarket engagement and contingency planning. Report P35
  • Staffing: The Corporate Repairs and Maintenance Team will manage the overall contract, monitor expenditure and visit properties during and after works. Report 12.3, 12.4

Who and where

  • Users of the Council's corporate buildings, including staff and the public Report P15
  • The Corporate Repairs and Maintenance Team and other council officers managing the framework Report 2.2, 12.3
  • Local and SME contractors able to bid for the 15 specialist lots Report 2.3, 2.8, P10
  • Suppliers required to meet Living Wage, GDPR, certification and equal opportunities standards Report 2.6, 8.4

Timeline

  • 10 August 2021: Original Executive decision to procure a Major Capital Schemes framework Report 2.3, 14.1
  • 2025-10-28: Executive amends the 2021 decision and approves the Corporate Building Maintenance framework procurement Report 14.1
  • Early December 2025: Invitation to tender to be issued Report 2.14
  • April to June 2026: Contracts for each of the 15 lots to be awarded on a phased basis Report 2.14

Plain English for the jargon

  • CDP: Central Digital Portal, the platform used for publishing procurement notices under the Procurement Act 2023
  • HVAC: Heating, Ventilation and Air Conditioning
  • LOLER: Lifting Operations and Lifting Equipment Regulations, covering testing and inspection of lifting equipment
  • RFQ / RFP: Request for Quote / Request for Proposal, used to award call-off contracts
  • R&M Team: Corporate Repairs and Maintenance Team, which manages works on the corporate estate
  • SME: Small and Medium sized Enterprise, with greater bidding opportunities built into the lots
  • MTFP: Medium Term Financial Plan, into which future budget requirements will be incorporated
  • JCT: Joint Contracts Tribunal, a standard form of building contract that may be used for complex call-off works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59

Resolved

a) that Executive amends its decision made on 10 August 2021 and authorises the Assistant Director for Place, in consultation with ... view the full minutes text for item 59.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Executive

Background

2.1Regular maintenance and minor works are undertaken to the Council’s Corporate Properties (e.g. Town Hall, leisure centres, crematorium, offices, and other corporate assets). The works consist of emergency or “reactive” works, planned repairs, statutory routine maintenance, alterations, testing & inspection works, small capital projects and additions to existing premises. This ensures the corporate properties are maintained to the appropriate and legal standard, are safe to use, and service delivery is maintained.

2.2The Council has traditionally tendered separate contracts for services that are required to maintain the commercial buildings across Ipswich. The Corporate Repairs & Maintenance (R&M) Team manages the works to these sites and is expected to maintain these and ensure they are operational and compliant.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
E/25/25 Framework for Corporate Building MaintenanceReport 507 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
NM
Councillor Neil MacDonaldLeader, present
BR
Councillor Bryony RudkinDeputy Leader, apologies
JC
Councillor John CookCommittee Member, present
MC
Councillor Martin CookCommittee Member, apologies
CJ
Councillor Carole JonesCommittee Member, apologies
JR
Councillor Jane RileyCommittee Member, present
AR
Councillor Alasdair RossCommittee Member, present
PS
Councillor Philip SmartCommittee Member, present
LT
Councillor Lucy TrenchardCommittee Member, apologies
IF
Councillor Ian FisherCommittee Member, present

More from Ipswich Executive

All decisions
MeetingDecisionOutcome
11 Aug 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 14 July 2026 be signed as a true record. Decided Open
11 Aug 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda. Decided Open
11 Aug 2026 E/26/14 Competence and Conduct Policy for Housing Servicei) that Executive approves, adopts and publishes the Competence and Conduct Policy (Housing) appended to the report a... Approved Open
11 Aug 2026 Exclusion of Publicthat the public (including the Press) be excluded from the meeting during consideration of the following items under ... Decided Open
14 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 16 June 2026 be signed as a true record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies