JMS/25/06 Colchester and Ipswich Museum Service: Budget 2026/27

Agreed Committee 1 paper

AI summaryJoint Museums Committee agreed a 2026/27 budget contribution of £2,269,900, to be recommended to both councils' executives. The figure differs from the £2,238,300 total in the officer report.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedRecommended to CCC Cabinet and IBC Executive
Money£2,269,900Total 2026/27 contribution: CCC £1,251,300, IBC £1,018,600
What happens nextRefer to both councilsEach council to adopt through its own budget setting process
Who it affectsJoint Museum Service and visitorsColchester and Ipswich Museum Service funded by both councils

What was decided

The Committee agreed a total 2026/27 budget contribution of £2,269,900 from the two councils, to be recommended to each council's executive for adoption.

The split is £1,251,300 from Colchester City Council and £1,018,600 from Ipswich Borough Council.

Why

The officer report set out an indicative 2026/27 budget built on a 3.8% inflation uplift (September 2025 CPI), an assumed 2.5% pay award, and the transfer of £228,400 of Colchester Museums asset-related budgets to a new Corporate Landlord model. Report P11, P13, P16

The 2025/26 forecast shows a £16k net underspend after an £81k employees overspend and a £20k supplies overspend, partly offset by £117k of additional income, grant income and reimbursements. Report 2.2, P7, P8, P9

What happens next

The Cabinet of Colchester City Council is asked to adopt the recommended total and the £1,251,300 share. Report P11

The Executive of Ipswich Borough Council is asked to adopt the recommended total and the £1,018,600 share through its own budget setting process. Report P11

The money

  • £2,269,900 Total 2026/27 budget contribution agreed by the Committee
  • £1,251,300 Colchester City Council share for 2026/27 (as decided)
  • £1,018,600 Ipswich Borough Council share for 2026/27
  • £2,238,300 Total 2026/27 contribution set out in the officer report Report P11, P14
  • £1,219,700 Colchester City Council share in the officer report Report P11
  • £23,961 Reserves surplus carried into 2025/26
  • £16k Forecast 2025/26 net underspend Report 2.2
  • £81k Employees budget forecast overspend 2025/26 Report P7
  • £20k Supplies and services forecast overspend 2025/26 Report P8
  • £117k Additional income, grants and reimbursements offsetting 2025/26 overspend Report P9
  • £228,400 Colchester Museums asset-related budgets transferred to Corporate Landlord Report P11, P13

Implications

  • Financial: Each council's contribution rises in line with September 2025 CPI of 3.8%; £228,400 of Colchester Museums asset budgets move out of the service into a new Corporate Landlord model. Report P11, P13, P16
  • Staffing: The 2026/27 budget assumes a 2.5% pay award; the 2025/26 forecast includes a £15k pay award cost above budget. Report P7, P11

Who and where

  • Colchester and Ipswich Museum Service (CIMS) Report P11
  • Colchester City Council Report P11
  • Ipswich Borough Council Report P11
  • Visitors and users of the museums Report P11

Timeline

  • July 2025: Reserves surplus of £23,961 reported to Joint Committee
  • December 2025: Current 2025/26 financial position reported
  • 26 January 2026: Joint Museums Committee considers 2026/27 budget Report P1
  • 2026/27: Financial year to which the agreed contribution applies Report P11

Plain English for the jargon

  • CIMS: Colchester and Ipswich Museum Service
  • CCC: Colchester City Council
  • IBC: Ipswich Borough Council
  • CPI: Consumer Price Index, used here at the September 2025 rate of 3.8%
  • Corporate Landlord: New asset management model to which Colchester Museums asset budgets have been transferred
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

(i) that the total Colchester City Council and Ipswich Borough Council budget contribution to the Colchester and Ipswich Museum Service for 2026/27 be agreed as £2,269,900. (ii) that the budget contribution for 2026/27 in relation to Colchester City Council be agreed as £1,251,300. (iii) that the budget contribution for 2026/27 in relation to Ipswich Borough Council be agreed as £1,018,600. (iv) that the total figure and respective partner contributions be recommended to the Cabinet of Colchester City Council and the Executive of Ipswich Borough Council for adoption.
Word for word from the decision Ipswich published for this meeting. Source: democracy.ipswich.gov.uk

Follow this further

Built from Ipswich's papers

What the report saysPro

Report to Colchester & Ipswich Joint Museums Committee

Item Colchester and Ipswich Museum Service Joint Commitee 7 JMS/25/06 26 January 2026

Report of Colchester and Ipswich Museum Manager Author Frank Hargrave [phone removed] Title 2026/27 Budget for Colchester & Ipswich Museum Service

1.0Summary & Content 1.1 This report provides a brief update on the current financial position, as of December 2025 for Colchester & Ipswich Joint Museum Service for 2025/26.

1.2The report also summarises the current indicative position in relation to setting the 2026/27 budget for Colchester & Ipswich Joint Museum Service and recommended financial contributions from Colchester City Council and Ipswich Borough Council, to be agreed through each Council’s budget setting process.

2.02025/26 Budget (current year) 2.1 As reported to the Joint Committee in July 2025, the reserves position carried forward into 2025/26 was showing a surplus of £23,961. The reserve is within the £100k agreed surplus/deficit limit for the joint service.

2.2Current year income and expenditure forecast is indicating a £16k net underspend. The key drivers to this forecast are as follows:

Employees budget forecast £81k overspend - £60k vacancy factor savings target - Pay award greater than budgeted for (£15k) - Other: casual staff, training and overtime costs (£6k)

Supplies and Services forecast £20k overspend: - General operational expenses

The overspend is mitigated by a mixture of additional income, grant income and reimbursements totalling £117k.

3.02026/27 Budget 3.1 The summary of the 2026/27 Budget recommendations are as follows:

 The total CCC and IBC budget contribution to Colchester and Ipswich Museum Service for 2026/27 be agreed as £2,238,300.  The budget contribution for 2026/27 in relation to Colchester City Council be agreed as £1,219,700.  The budget contribution for 2026/27 in relation to Ipswich Borough Council be agreed as £1,018,600.  The total figure and the respective partner contributions are recommended to the Cabinet of Colchester City Council and the Executive Committee of Ipswich Borough Council for adoption. 4.0 Background / Supporting Information  Under the terms of the revised Joint Museums agreement, each partner authority now retains the majority of its income. The income shown for CIMS for 2026/27 primarily relates to income from retail activities, events and grants.  The budget includes an assumed 2.5% allowance for a pay award.  An inflationary increase of 3.8% based on the September 2025 CPI rate has been applied to the contributions for each authority.  Please note that asset-related budgets – a total of £228,400 – relating to Colchester Museums only, have been transferred to the newly created Corporate Landlord model to enable more efficient asset management.  The total contribution to CIMS is £2,238,300 of which CCC contributes £1,219,700 and IBC, £1,018,600.

The proposed 2026/27 budget is set out below:

Budget 2026/27 Total £000 2025/26 Contribution 2,376.4 Inflation increase 3.8% CCC 53.0 Inflation increase 3.8% IBC 37.3 Additional Changes Asset related budgets move to Corp.Land. - CCC -228.4

2026/27 Total Contributions 2,238.3

Total contribution increase (excl.asset budgets) +90.3

The total contribution had increased by 3.8%, representing September 2025 CPI inflation increase as per the Joint Museums agreement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
JMS/25/06 Colchester and Ipswich Museum Service: Budget 2026/27Report 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 4 attended
CP
Councillor Chris PearsonCommittee Member, present
LS
Councillor Lee ScordisCommittee Member, present
CJ
Councillor Carole JonesCommittee Member, present
JR
Councillor Jane RileyCommittee Member, apologies

On this subject at Ipswich

Search all
  1. JMS/25/06 Colchester and Ipswich Museum Service: Budget 2026/27This decision
  2. JMS/26/04 Budget Update for the Colchester & Ipswich Museum ServiceNoted
  3. JMS/25/07 Colchester and Ipswich Joint Museum Service: Business Plan 2023-2028Approved
  4. JMS/25/02 Budget Update for the Colchester & Ipswich Museum ServiceNoted
  5. JMS/24/07 Colchester and Ipswich Museum Service: Budget 2025/26Agreed
  6. JMS/24/08 Colchester and Ipswich Museum Service: Business Plan 2023-2026Approved

More from Ipswich Colchester & Ipswich Joint Museums Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 Election of Chairthat Councillor Jay be elected as Chair for the 2026/27 municipal year. Decided Open
20 Jul 2026 Election of Vice-Chairthat Councillor Jones be elected as Vice-Chair for the 2026/27 municipal year. Decided Open
20 Jul 2026 Unconfirmed Minutes of Previous Meetingthat the Minutes of the meeting held on 26 January 2026 be signed as a true record. Decided Open
20 Jul 2026 To Confirm or Vary the Order of Businessthat the Order of Business be confirmed as printed on the Agenda . Decided Open
20 Jul 2026 Performance against NPO Action Plan - Verbal Updatethat the progress made against the NPO Action Plan be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies