What was decided
Executive authorised the Director of Operations and Place, in consultation with the Portfolio Holder for Place and Portfolio Holder for Planning, to take all necessary steps to enable development of a Masterplan for South Ravenswood, within the budget set in Exempt Appendix 2. Report 14.1, P84
The requirement to produce a Masterplan is to be added to the existing development agreement with Handford Homes Limited, trading as Handford Developments, who will procure external support and manage the process on behalf of the Council. Report 4.12, 12.1
Option B (proceed with a Masterplan) was chosen over Option A (do not proceed), because the area needs a comprehensive, plan led approach to address infrastructure, character and environmental challenges. Report 4.2, 4.6, 4.7, 4.11
Why
Local Plan Policy SP9 requires new development at South Ravenswood to be delivered through a Masterplan approach involving landowner collaboration and community engagement. Report 2.5, 2.6
The area has infrastructure, character and environmental challenges, including highway junctions already under strain, that need a comprehensive plan led approach to identify access options and capacity enhancements. Report 2.10, 2.11, 2.12
A Masterplan will provide a platform for future planning applications, including a comprehensive cost plan, phasing and delivery strategy for the individual development parcels and associated infrastructure. Report 2.17, 2.18, 4.9
What happens next
Develop the Masterplan to RIBA Stage 2 (initial design concepts and visualisations), with separate appointments to be made later for RIBA Stage 3 detailed design to inform planning applications. Report 2.19, 12.1
Undertake landowner collaboration and community engagement, with EQIAs to be produced as proposals are considered during Masterplan development. Report 5.1, 5.2, 8.5
Explore alternative land uses for some sites and access options from the A1190 and Nacton Road, with the process likely to lead to proposed amendments to current Local Plan land allocations. Report 2.12, 2.13, P17
The money
- £0.5m Additional proposed budget within the future capital programme to fund Masterplans for North West Ipswich and South Ravenswood past RIBA Stage 2, subject to Council agreement on 18th February 2026 Report 10.2
Options considered
- Rejected: Option A: Do not proceed with developing a Masterplan at this time and either rely on a developer to undertake the work or delay it to a future point. Would delay future development and delay identification of improvements to alleviate the existing traffic burden on access points and traffic flows Report 4.2, 4.5, 4.6
- Chosen: Option B: Proceed with developing a Masterplan for South Ravenswood. Will assess and solve infrastructure, character and environmental challenges, provide a cost plan, phasing and delivery strategy, and support investment Report 4.7, 4.8, 4.9, 4.10, 4.11
Implications
- Financial: An additional £0.5m capital budget is proposed for Masterplans covering North West Ipswich and South Ravenswood past RIBA Stage 2, subject to Council approval on 18th February 2026. Report 10.2
- Legal: Once endorsed, the Masterplan will be a material planning consideration in the determination of any relevant planning application. Report 11.3
- Equalities: The Priory Heath Lower Super Output Area is in the 20% most deprived nationally for Education and Health, so the Masterplan will consider issues for existing and future residents. Report 8.4
- Climate: The Study Area is close to the Stour and Orwell Special Protection Area and Ramsar Site, so a project level Habitats Regulations Assessment and mitigation strategy will be required, alongside a 10% Biodiversity Net Gain from January 2024. Report 7.2, 7.3, 7.8
- Risk: Two risks are identified in the risk table: failure to develop a Masterplan for the area (impact 2, probability 2) and failure to engage with the local community (impact 2, probability 2), both to be mitigated through the actions in the report. Report P49
- Other: It is unknown whether the Masterplan would form part of an Outline planning application or a Supplementary Plan, depending on progress of the Levelling Up and Regeneration Act 2023 and supporting Regulations. Report 2.7
Who and where
- Local community in and around South Ravenswood, including Priory Heath residents Report 2.15, 8.4
- Handford Homes Limited, trading as Handford Developments, as the developer partner under the existing development agreement Report 4.12, 12.1
- The private owner of site IP152 (other sites are in Council ownership) Report 2.8
- Users of Priory Lane accessing Orwell County Park, Alnesbourne Priory Golf Club, Priory Park Residential and Holiday Homes, and Hallowtree Scout Activity Centre Report 2.8
- Suffolk County Council as Local Highway Authority, due to possible adoption of Priory Lane Report P15
Timeline
- January 2024: A 10% increase in existing Biodiversity Net Gain became mandatory Report 7.8
- 18th February 2026: Council to consider the additional £0.5m capital programme budget Report 10.2
- 2025: A subsequent development of 96 dwellings was completed in Ravenswood Report 2.1
Plain English for the jargon
- Masterplan: A structured planning document setting out the framework for development of an area, including land use, infrastructure, phasing and design.
- RIBA Stage 2: The second stage of the Royal Institute of British Architects work plan, covering initial design concepts and visualisations.
- Supplementary Plan: A planning document that supplements existing local plan policy; the route here depends on progress of the Levelling Up and Regeneration Act 2023 and supporting Regulations.
- Habitats Regulations Assessment: An assessment required to demonstrate that urbanisation impacts on European and internationally designated protected sites are prevented.
- Biodiversity Net Gain: A policy requirement for development to deliver a measurable increase in biodiversity, with a 10% uplift mandatory from January 2024.
- LSOA: Lower Super Output Area, a small geographic area used in the Index of Multiple Deprivation to compare levels of deprivation.