Item310
Resolved
(i) To agree the addition to the Capital Programme of £1.790m for Future Work Phase 2 funded by borrowing to reflect a technical accounting adjustment to capitalise existing expenditure. Note that this is not new council spend. (ii) To agree the reduction of £1.292m from New River College SEND/ Elthorne funded by borrowing. (iii) To agree the addition to the Capital Programme of £3.366m for the Disabled Facilities Grant funded by grant to reflect a technical accounting adjustment to capitalise existing expenditure. Note that this is not new council spend. (iv) To agree the reduction to the Capital Programme of £12.852m for the placeholder relating to Decarbonisation – Grant Match Funding funded by borrowing. (v) To agree the reduction to the Capital Programme of £2.267m from Elmore Street & Lindsey Mews Current New Build funded by capital receipts.
Word for word from the decision Islington published for this meeting.
Source: democracy.islington.gov.uk