London Borough of Islington
Executive, Wednesday 25 March 2026 at 5.00pm

Interim procurement strategy and contract award for voids reservicing, refurbishment and new tenancy repair works

Approved Executive 2 papers

AI summaryIslington Executive approves voids, refurbishment and tenancy repair procurement strategy with up to £5 million direct contract awards to three suppliers for 12 months.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedVia Constellia and Fusion 21 frameworks, up to 12 months
Money£5,000,000 inc VAT eachSame ceiling for each of three contracts
What happens nextAward third contract via delegationCorporate Director to act after consultation
Who it affectsCouncil housing tenantsVoids, refurbishment and new tenancy repairs

What was decided

The Executive approved the procurement strategy and direct awards to Richwell Construction Limited via the Constellia framework and to Pilon Limited via the Fusion 21 Reactive Repairs and Empty Properties Framework, each at a total estimated cost of up to £5,000,000 (inc VAT) and a term of up to 12 months.

A third supplier will be procured by direct award under the Fusion 21 framework, also capped at £5,000,000 (inc VAT) and up to 12 months.

Authority to award the third contract is delegated to the Corporate Director of Homes and Neighbourhoods, in consultation with the Executive Member for Homes and Neighbourhoods, the Corporate Director of Community Wealth Building and the Corporate Director of Resources.

What happens next

The Corporate Director of Homes and Neighbourhoods will award the third contract following consultation with the named officers and Executive Member.

Each awarded contract will run for up to 12 months from the point of award.

The money

  • £5,000,000 (inc VAT) Estimated cost of contract awarded to Richwell Construction Limited via Constellia framework, up to 12 months
  • £5,000,000 (inc VAT) Estimated cost of contract awarded to Pilon Limited via Fusion 21 framework, up to 12 months
  • £5,000,000 (inc VAT) Estimated cost of contract to be awarded to a third supplier via Fusion 21 framework, up to 12 months

Implications

  • Financial: Up to £5,000,000 (inc VAT) committed under each of three separate 12-month direct awards, using existing framework agreements rather than a new competitive tender.
  • Legal: Contracts are let by direct award through named compliant frameworks, avoiding a fresh open procurement exercise.
  • Staffing: Decision-making on the third supplier is delegated to the Corporate Director of Homes and Neighbourhoods, subject to required consultations before award.

Who and where

  • Council housing tenants receiving voids, refurbishment and new tenancy repairs in Islington
  • The council as commissioner of works on its housing stock
  • Named suppliers Richwell Construction Limited and Pilon Limited, and a third supplier to be selected

Timeline

  • 2026-03-25: Executive agreed recommendations at the meeting
  • Up to 12 months: Maximum duration of each awarded contract

Plain English for the jargon

  • Voids: Council homes that are empty between tenancies and need work before being re-let.
  • Direct contract award: Awarding a contract to a chosen supplier without running a new competitive tender.
  • Framework: A pre-approved list of suppliers that public bodies can call on to buy works or services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

Recommendations: 1.1. To approve the procurement strategy as set out in this report. 1.2. To approve a direct contract award to Richwell Construction Limited pursuant of the Constellia framework for a period of up to 12 months, at a total estimated cost of up to £5,000,000 (inc VAT). 1.3. To approve a direct contract award to Pilon Limited pursuant of the Fusion 21 Reactive Repairs and Empty Properties Framework for a period of up to 12 months, at a total estimated cost of up to £5,000,000 (inc VAT). 1.4. To approve the procurement of a third supplier through a direct contract award pursuant of the Fusion 21 Reactive Repairs and Empty properties Framework for a period of up to 12 months, at a total estimated cost of up to £5,000,000 (inc VAT). 1.5. To delegate authority to the Corporate Director of Homes and Neighbourhoods following consultation with the Executive Member for Homes and Neighbourhoods, Corporate Director of Community Wealth Building and Corporate Director of Resources for the award of a contract to the third supplier. Decisions : Agreed recommendations Reason for the decision - as detailed in the report Other options considered – as detailed in the report Conflicts of interest/dispensations granted – none
Word for word from the decision Islington published for this meeting. Source: democracy.islington.gov.uk

Follow this further

Built from Islington's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Interim procurement strategy and contract award for voids reservicing, refurbishment and new tenancy repair worksDecisions 164 KB Copy on its way
PDF
Public Notice of urgency: voids contractReport 75 KB Copy on its way

More from Islington Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 Q1 Financial Risk Monitor 2026-27Recommendations: i. Noted the Q1 Financial Risk Monitor for 2026/27, including the key financial risks, forecast pres... Noted Open
17 Sep 2026 Consultation on the proposed New Tenancy ConditionsRecommendations: i. Noted the reasons why the Council is proposing to update its Tenancy Conditions ii. Agreed that t... Noted Open
17 Sep 2026 Response to Housing Scrutiny Review - New Build Homes May 2024Recommendations: i. Agreed the responses to the recommendations made by the Housing Scrutiny Committee, as set out in... Agreed Open
17 Sep 2026 Response to Overview and Scrutiny Committee Review - Financial ResilienceRecommendations: i. Agreed the Council’s response to the recommendations set out in the Review of Financial Resilienc... Agreed Open