Resolved
RESOLVED that the use of agency staff, interim managers and consultants in Kent County Council at September 2007 be noted.
Personnel Committee noted this item on Friday 1 February 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the use of agency staff, interim managers and consultants in Kent County Council at September 2007 be noted.
1.1In September 2004, Personnel Committee endorsed a report recommending annual monitoring of the use of interim managers and agency staff in KCC and from 2005 consultants would be included. In January 2006 it was agreed that this should be extended to six monthly monitoring from 2007.
1.2The report noted the difference between consultants procured to deliver a specific piece of work and the individuals brought into the organisation to cover existing vacancies or supplement the workforce at times of peak workload, i.e. agency staff and interim managers.
1.3It was agreed that the date for the monitoring would be 30 March and 30 September each year and this paper reports the outcomes of the latest monitoring.
1.4It was also agreed at the last Personnel Committee that the numbers of staff being re-employed following at risk of redundancy status. These figures are as follows:
At risk of At risk of Slotted Redeployed Redundancy Restructure Staff Nos 25 74 14 61
2. AGENCY STAFF AND INTERIM MANAGERS IN PLACE ON 30.9.07
2.1The figure for use of agency staff and interim managers across KCC was 2.8% of the workforce which is lower than in March 2007. Information on the use of agency staff in other local authorities is scant.
2.2Appendix 1 shows the number of agency staff and interim managers in place across KCC by Directorate. Appendix 2 shows comparisons since September 2004. 2.3 The use of interim managers was as follows:
CED 2 1 x Property and 1 x Corporate Diversity Team
2.4The percentage use of agency staff was lowest in Communities (0.9%) and highest in Environment & Regeneration (8.2%). Most of the agency staff in Environment & Regeneration were in Kent Highway Services where it has been necessary to use agency staff during restructuring to avoid taking on permanent staff.
2.5In Chief Executive’s the total figure was 8.0%. Higher percentages were seen in Legal Services where there were a high number of locum solicitors and in ISG where there were a total of 36 agency staff at this time working in the development team, service desk, projects and integration, procurement, TRP, Oracle Support, EIS and IS commissioning.
2.6In Kent Adult Social Services, the overall figure was 4.0% an increase since March but lower than the September figure in 2006. In the East Kent Social Care area the number of agency staff remained relatively high to support the implementation of SWIFT.
2.7In Children, Families & Education the use of agency staff accounted for 1.8% of the workforce. This is a decrease on the March figures and agency staff are still mainly in Children’s Social Services, covering both social workers and administration roles. Consultants in CFE were deployed in the Advisory Service and most of these were part of the school improvement partner set up.
3. KENT TOP TEMPS (KTT)
3.1Personnel Committee has asked that this monitoring report include information on Kent Top Temps. The number of agents that KTT had in place on 30 September 2007 is shown in Appendix 2. The information includes the number of supply teachers placed through Kent Top Temps. Information on supply teachers placed by other agencies is only available by requesting each school to provide it.
4.1Personnel Committee is asked to note the usage of agency staff, interim managers and consultants in KCC on 30 September 2007.
Amanda Beer Director of Personnel & Development Ext 4136 APPENDIX 1
NUMBERS OF AGENCY STAFF AND INTERIM MANAGERS ON 30 SEPTEMBER 2007
Directorate No of Agency No of interim Total Temporary Total temporary No of staff managers Staff staff as a % of Consultants (FTE) (FTE) (FTE) Directorate procured headcount between 01.04.07 and 30.09.07 Chief Executive 79.41 2 81.41 8.0 14
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Monitoring Use of Interim Managers, Agency Staff and ConsultantsReport | 5 pages | DownloadRead as text |
Follow Personnel Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2026 | Election of ChairRESOLVED that [name removed] be elected Chair for this meeting. | Decided | Open |
| 25 Mar 2026 | Minutes of the meeting held on 29 January 2026RESOLVED that the minutes of the meeting held on 29 January 2026 are correctly recorded and that they be signed by th... | Decided | Open |
| 25 Mar 2026 | Cadet Force Adult Volunteers Special LeaveRESOLVED, by majority vote, that Personnel Committee defer consideration of the report and request that officers brin... | Deferred | Open |
| 25 Mar 2026 | Fostering Friendly LeaveRESOLVED that the Personnel Committee approve the proposal described in section 4, which introduces a special leave e... | Approved | Open |
| 29 Jan 2026 | Minutes of the meeting held on 23 September 2025 and 27 November 2025RESOLVED that the minutes of the meeting held on 23 September 2026 and 27 November 2026 are correctly recorded and th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.