By: Adam Wilkinson, Managing Director – Environment and Regeneration
To: Environment & Regeneration Policy Overview Committee – 4th April 2008
Subject: KCC Regeneration Strategy
Classification: Unrestricted
Purpose of Report: To provide an update on progress being made towards the KCC Regeneration Strategy
Recommendation: That Members note the progress made and continue to support the continued work towards production of the KCC Regeneration Strategy
1. Introduction
1.1Cabinet approved work to commence at the meeting of 21st January 2008. This report provides an update on progress to date.
1.2A core team and working brief had been in place from early January 2008 and began work during the week commencing 7th January with the objective of providing the KCC Regeneration Strategy for Cabinet on the 12th May 2008.
2. Regeneration Strategy Scope & Approach
2.1The proposed Strategy for KCC’s role in Kent’s regeneration is the continuation of a long-term corporate commitment to regeneration through the activities of Education, Social Services, Arts, Culture, Environment & Transport, and above all, a commitment to tackle deprivation at its root causes.
2.2The strategy will be a living, dynamic document, updated every three years and with an annual action plan. It will set out KCC’s regeneration priorities and how these relate to existing overarching Kent documents including Community Strategy, Kent Prospects and strategies for local transport, health, environment, skills, culture and other relevant areas. It will also make explicit how KCC’s Towards 2010 targets contribute to achieving KCC’s corporate regeneration ambitions.
3. Project Team
3.1Working directly to Adam Wilkinson, a Regeneration Strategy team was set up with Peter Welsh (Head of Analysis and Information Team) as project manager.
3.2The team is made up of experienced officers from across the range of regeneration disciplines and includes representatives from CFE, KASS and CMY directorates.
4. Approach and Methodology 4.1 The strategy is being based upon a wide range of evidence and the first wave of analysis of core indicators, existing projects and priorities on a district by district basis is now complete.
4.2National, Regional and Local strategy context analyses have been completed, including Towards 2010, V4K and the range of core strategies.
4.3The current phase of analysis is focussing on identifying cross-Kent themes and priorities for the Strategic Action Plan section of the document
5. Engagement Process
5.1Although not a statutory document, the KCC Regeneration Strategy is following best practice and engaging with partners through a series of meetings betweens Chief Executives and the Project Manager. These took place during w/c 28th January and w/c 4th February 2008 and prepared the ground for further substantive workshops with Districts/Boroughs and other partners organisations.
5.2During the week commencing 25th February a series of workshops were held, hosted by Adam Wilkinson and Roger Gough with District Leaders, CEOs and Directors of Regeneration. The purpose of these meetings was to provide a clear opportunity to work with District partners on the key issues facing them and sought to explore opportunities for better working practices and continued project development.
5.3The workshops focused on a review of the quantitative evidence compiled during the first part of the KCC Regeneration Strategy project and stimulated debate around the implications of using this intelligence-led approach, which was universally supported.
5.4The findings of the workshops make up part of the evidence base of the KCC Regeneration Strategy and have confirmed or revealed issues central to its focus and delivery.
6. Drafting and Peer Review
6.1The week commencing 4th March saw work on drafting the strategy begin, pulling together all of the information gathering phases, the district and comparative analysis, findings from the engagement workshop phase and the strategic context.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
KCC Regeneration StrategyReport | 3 pages | DownloadRead as text |
Follow Environment and Regeneration Policy Overview and Sctuiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 31 Mar 2009 | Minutes - 20 January 2009RESOLVED that the Minutes of the meeting held on 20 January 2009 are correctly recorded and that they be signed by th... | Decided | Open |
| 31 Mar 2009 | Financial Monitoring Update 2008/09RESOLVED that the report and the comments ... view the full minutes text for item 122. | Decided | Open |
| 31 Mar 2009 | Development Contributions and Future Community Infrastructure ProvisionRESOLVED that (subject to ongoing discussions with Cabinet Members and Budget IMG):- (a) approval be given to the gui... | Approved | Open |
| 31 Mar 2009 | Implications of the Local Democracy, Economic Development and Construction BillRESOLVED that the contents in particular the key actions detailed in paragraph 6 “Next Steps” of the report and comme... | Noted | Open |
| 31 Mar 2009 | Unlocking Kent's Potential - verbal report by Mr K Lynes, Cabinet MemberRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.