KCC Regeneration Strategy

Noted Scrutiny 1 paper

Environment and Regeneration Policy Overview and Sctuiny Committee noted this item on Friday 4 April 2008. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

RESOLVED that the Members comments and the report be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Environment and Regeneration Policy Overview and Sctuiny Committee, 3 pages

By: Adam Wilkinson, Managing Director – Environment and Regeneration

To: Environment & Regeneration Policy Overview Committee – 4th April 2008

Subject: KCC Regeneration Strategy

Classification: Unrestricted

Purpose of Report: To provide an update on progress being made towards the KCC Regeneration Strategy

Recommendation: That Members note the progress made and continue to support the continued work towards production of the KCC Regeneration Strategy

1. Introduction

1.1Cabinet approved work to commence at the meeting of 21st January 2008. This report provides an update on progress to date.

1.2A core team and working brief had been in place from early January 2008 and began work during the week commencing 7th January with the objective of providing the KCC Regeneration Strategy for Cabinet on the 12th May 2008.

2. Regeneration Strategy Scope & Approach

2.1The proposed Strategy for KCC’s role in Kent’s regeneration is the continuation of a long-term corporate commitment to regeneration through the activities of Education, Social Services, Arts, Culture, Environment & Transport, and above all, a commitment to tackle deprivation at its root causes.

2.2The strategy will be a living, dynamic document, updated every three years and with an annual action plan. It will set out KCC’s regeneration priorities and how these relate to existing overarching Kent documents including Community Strategy, Kent Prospects and strategies for local transport, health, environment, skills, culture and other relevant areas. It will also make explicit how KCC’s Towards 2010 targets contribute to achieving KCC’s corporate regeneration ambitions.

3. Project Team

3.1Working directly to Adam Wilkinson, a Regeneration Strategy team was set up with Peter Welsh (Head of Analysis and Information Team) as project manager.

3.2The team is made up of experienced officers from across the range of regeneration disciplines and includes representatives from CFE, KASS and CMY directorates.

4. Approach and Methodology 4.1 The strategy is being based upon a wide range of evidence and the first wave of analysis of core indicators, existing projects and priorities on a district by district basis is now complete.

4.2National, Regional and Local strategy context analyses have been completed, including Towards 2010, V4K and the range of core strategies.

4.3The current phase of analysis is focussing on identifying cross-Kent themes and priorities for the Strategic Action Plan section of the document

5. Engagement Process

5.1Although not a statutory document, the KCC Regeneration Strategy is following best practice and engaging with partners through a series of meetings betweens Chief Executives and the Project Manager. These took place during w/c 28th January and w/c 4th February 2008 and prepared the ground for further substantive workshops with Districts/Boroughs and other partners organisations.

5.2During the week commencing 25th February a series of workshops were held, hosted by Adam Wilkinson and Roger Gough with District Leaders, CEOs and Directors of Regeneration. The purpose of these meetings was to provide a clear opportunity to work with District partners on the key issues facing them and sought to explore opportunities for better working practices and continued project development.

5.3The workshops focused on a review of the quantitative evidence compiled during the first part of the KCC Regeneration Strategy project and stimulated debate around the implications of using this intelligence-led approach, which was universally supported.

5.4The findings of the workshops make up part of the evidence base of the KCC Regeneration Strategy and have confirmed or revealed issues central to its focus and delivery.

6. Drafting and Peer Review

6.1The week commencing 4th March saw work on drafting the strategy begin, pulling together all of the information gathering phases, the district and comparative analysis, findings from the engagement workshop phase and the strategic context.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
KCC Regeneration StrategyReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Kent

Search all
  1. KCC Regeneration StrategyThis decision
  2. Proposal SW/10/1003 - Cycle track along the "Canal Bank" (Queensborough Lines) at Halfway Road, Sheerness; KCC Chief Executive's Department Regeneration and Economy DivisionDecided
  3. A Summary of Progress in Delivery of KCC’s Environment Policy, including Climate Change and an overview of next steps for KCC and Environment and RegenerationNoted
  4. Proposal SE/08/1896 - Extension of existing hard paved car park with alteration to the line of the existing western boundary fence and widening of the entrance drive at Lullingstone County Park, Kingfisher Bridge, Castle Road, Eynsford, Dartford; KCC Environment and Regeneration.Decided
  5. Proposal SW/04/1453 - Alternative bridge designs at Sittingbourne Northern Relief Road; KCC Environment and Regeneration.Noted
  6. Regeneration Strategy for KCCNoted

More from Kent Environment and Regeneration Policy Overview and Sctuiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2009 Minutes - 20 January 2009RESOLVED that the Minutes of the meeting held on 20 January 2009 are correctly recorded and that they be signed by th... Decided Open
31 Mar 2009 Financial Monitoring Update 2008/09RESOLVED that the report and the comments ... view the full minutes text for item 122. Decided Open
31 Mar 2009 Development Contributions and Future Community Infrastructure ProvisionRESOLVED that (subject to ongoing discussions with Cabinet Members and Budget IMG):- (a) approval be given to the gui... Approved Open
31 Mar 2009 Implications of the Local Democracy, Economic Development and Construction BillRESOLVED that the contents in particular the key actions detailed in paragraph 6 “Next Steps” of the report and comme... Noted Open
31 Mar 2009 Unlocking Kent's Potential - verbal report by Mr K Lynes, Cabinet MemberRESOLVED that the report be noted. Noted Open