CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kent County Council

Financial Monitoring update 2007/08

Noted Scrutiny 1 paper

Environment and Regeneration Policy Overview and Sctuiny Committee noted this item on Thursday 29 May 2008. Below is the council's own wording, with the papers it was decided on.

Item80

Resolved

RESOLVED that the responses to Members questions and the report be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Environment and Regeneration Policy Overview and Sctuiny Committee, 18 pages

By: Adam Wilkinson, Managing Director Environment & Regeneration

To: Environment & Regeneration Policy Overview Committee – 29 May 2008

Subject: Financial Monitoring Update 2007/08

Classification: Unrestricted

Summary: To update the Committee on the financial position in the 2007/08 year.

Introduction

1. The 2007/08 outturn forecasts, as contained in the financial monitoring Exception Report reported to Cabinet on the 12th May, are compared to the forecasts contained in the third quarter monitoring report. The latter report is included as an attachment. The more significant variations are set out below:

Revenue Budget:

2. In the EH&W Portfolio, the overall under spend decreased by £30k (to - £2.535m), comprising three main items: a forecast increase in waste disposal costs of £150k due to the impact of the rise in oil prices, and its effect on contract indexation, and a revision to the forecast for the costs of the waste diversion due to the non operation of the Allington WtE plant. Also on Waste, a more cautious estimate on income has reduced the forecast by a further £150k. For KHS, the forecast over spend reduced by a net £335k due largely to an improved forecast for income levels. Other Services in this Portfolio have resulted in a £65k increase to the forecast spend.

3. In the R&SI Portfolio, the under spend decreased by £140k (to -£0.915m) due, principally, to the revised funding arrangement for the Fort Hill De-dualling works (now from capital sources) leading to the removal of the forecast slippage under spend on that project, of £450k. However, there has been slippage on certain projects within Regeneration and Economy Division to the value of £225k. The Planning Applications Group has increased its forecast for fee income by £65k. Staff vacancies and other smaller changes accounts for the remaining movement of £20k.

Capital Budget:

4. The forecast for EH&W is that the portfolio will under spend by a further £8.236m, compared to the reported position at the third quarter. The main movements in the forecast (above £0.25m) are detailed below:

• -£2.722m Highway Major Maintenance and Improving Roads & Footpaths Programmes – at the third quarter an accelerated spend was forecast, but the volume of workload involved made this objective unachievable. • -£1.965m Integrated Transport Programme – a similar reason to above; the volume of work required in the last quarter of the year was not achievable.

(A review of workload planning is already underway for the above programmes, for 2008/09)

• +£0.34m Forward design of Major Schemes – largely related to East Kent Access Phase 2. • -£0.5m Wetland Creation – it was hoped to have completed agreements in 2007/08, but this did not prove possible. • -£0.323m Energy & Water Investment Funds – it has taken longer to arrange loans for this work than anticipated in the previous forecast. • -£0.455m East Kent Access Phase 1 – increased slippage into 2008/09. • -£0.362m Everard’s Link Phase 2 - increased slippage into 2008/09. • -£1.885m Re-shaping KHS Accommodation – further re-phasing as construction at the Wrotham site did not proceed, following the judicial review process. There is also several weeks programme delay at the Ashford site, due to the need to revise the internal lay-out. • -£0.258m Safety Camera Partnership activity – slippage into 2008/09.

5. The under spend forecast for the R&SI portfolio has moved by -£0.166m. The main movements (above £0.1m) are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring update 2007/08Report 18 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 21 attended
DP
Dick PascoeChairman, present
RT
Roger TrueloveVice-Chair, present
MA
Mike AngellCommittee Member, present
SC
Susan CareyCommittee Member, present
IC
Ian ChittendenCommittee Member, present as substitute
DD
Dan DaleySpokesperson, apologies, sent representative
MH
Mike HarrisonCommittee Member, present
CH
Charles HibberdCommittee Member, present
RK
Richard KingCommittee Member, present
RL
Richard Long, TDCommittee Member, present
AM
Alan MarshCommittee Member, present
JM
John MuckleCommittee Member, apologies, sent representative

All 21 on the meeting page

On this subject at Kent

Search all
  1. Financial Monitoring update 2007/08This decision
  2. Covid-19 Financial MonitoringNoted
  3. Covid-19 Financial MonitoringNoted
  4. Covid-19 Financial MonitoringNoted
  5. Covid-19 Financial MonitoringNoted
  6. Financial Monitoring 2017-18Noted

More from Kent Environment and Regeneration Policy Overview and Sctuiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2009 Minutes - 20 January 2009RESOLVED that the Minutes of the meeting held on 20 January 2009 are correctly recorded and that they be signed by th... Decided Open
31 Mar 2009 Financial Monitoring Update 2008/09RESOLVED that the report and the comments ... view the full minutes text for item 122. Decided Open
31 Mar 2009 Development Contributions and Future Community Infrastructure ProvisionRESOLVED that (subject to ongoing discussions with Cabinet Members and Budget IMG):- (a) approval be given to the gui... Approved Open
31 Mar 2009 Implications of the Local Democracy, Economic Development and Construction BillRESOLVED that the contents in particular the key actions detailed in paragraph 6 “Next Steps” of the report and comme... Noted Open
31 Mar 2009 Unlocking Kent's Potential - verbal report by Mr K Lynes, Cabinet MemberRESOLVED that the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies