Resolved
RESOLVED that the latest developments on the Turner Contemporary project and an update be submitted to the Committee twice a year.
Communities Policy Overview and Scrutiny Committee decided this item on Tuesday 13 January 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the latest developments on the Turner Contemporary project and an update be submitted to the Committee twice a year.
2.1The desire to create a gallery in Margate to celebrate JMW Turner’s links with the area was inspired, in part, by the need to provide additional cultural infrastructure within Kent but more importantly to stimulate the regeneration of Margate and East Kent.
2.2The original plans for the gallery were discontinued in February 2006 when costs increased well beyond the funds approved or available. At the time of this cancellation assurances were made that an alternative affordable scheme would be put together which would deliver similar regeneration and cultural benefits as those envisaged from the original scheme.
2.3In July 2006 KCC appointed the internationally renowned David Chipperfield Architects (DCA) Ltd to develop a new design for the gallery on the Rendezvous site. DCA delivered the outcome of their feasibility study in December 2006 which led to the inclusion of a £17.4m project in the capital programme approved in 2007/08 for the design, construction and fitting out of the new gallery.
2.4Throughout 2007 DCA completed the outline design (RIBA stage C) and detail design (RIBA stage D). The detail design report was issued in November 2007 which settled on the two storey building organised into 6 uniform blocks with a glass façade. The overall floor area of the design was 2,732m2. The technical design (RIBA stage E) was completed in February 2008 when planning permission was also granted by Thanet District Council.
2.5It was agreed to tender for the construction contract under a single stage process where a number of contractors would be approached with the aim of producing a short list from which the final contractor would be chosen. Following a comprehensive evaluation of submissions from 5 contractors it was agreed in October 2008 to award the construction contract to R Durtnell & Sons for a tender sum of £13.36m. This sum can be accommodated within the overall £17.4m budget for the design, construction and fitting out of the gallery building.
2.6We have successfully applied for £4.1m of capital funding from Arts Council England (ACE) and £4m from the South East England Development Agency (SEEDA). We are also planning to raise £2.9m through the Turner Contemporary Arts Trust (TCAT) and the remaining £6.4m necessary to fund the capital project will be provided from KCC capital programme.
2.7The chair and trustees for the Turner Contemporary trust have been appointed. It is planned that when the gallery is complete KCC will lease the building and enter into a service agreement for the running of the gallery with this trust, and staff would transfer to the trust’s employment.
3. Gallery Construction
3.1A groundbreaking event took place on 25th November 2008 to mark the formal start of construction. The contract with R. Durtnell and Sons Ltd has been signed and the company has taken control of the site and has started its preliminary work. The work will be completed by summer 2010 when the Turner Contemporary team will be able to take over the building. This will be followed by a period of commissioning and testing of the plant and equipment, and making all the practical arrangements for arranging exhibitions. As a consequence we are planning the formal opening of the gallery for spring 2011.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Turner Contemporary UpdateReport | 6 pages | DownloadRead as text |
Follow Communities Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2011 | Minutes - 11 January 2011RESOLVED that the minutes of the meeting held on 11 January 2011 are correctly recorded and that they signed by the C... | Decided | Open |
| 5 Apr 2011 | KCC's Performance Management FrameworkRESOLVED that the approach being taken to provide a clear performance management framework for the authority be noted. | Noted | Open |
| 5 Apr 2011 | Core MonitoringRESOLVED that the report be noted. | Noted | Open |
| 5 Apr 2011 | Edenbridge updateIt was agreed that an update on the scheme would be submitted to the Committee in due course. (3) Reference was made ... | Agreed | Open |
| 5 Apr 2011 | Introduction to the Customer and Communities DirectorateRESOLVED that the report and presentation be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.