2009/10 Budget Monitoring Exception Report

Noted Scrutiny 1 paper

Communities Policy Overview and Scrutiny Committee noted this item on Tuesday 7 July 2009. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED that the budget variations for the Communities Portfolio for 2009/10, based on the first exception monitoring report to Cabinet, be noted.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Communities Policy Overview and Scrutiny Committee, 3 pages

Summary

Members of the POC are asked to note the initial budget monitoring exception report for 2009/10 to be reported to Cabinet on 13th July 2009.

FOR INFORMATION

1. Introduction

1.1This is a regular report to this Committee on the forecast outturn against budget for the Communities portfolio.

Background

2.1A detailed quarterly budget monitoring report is presented to Cabinet, usually in September, December and March, and a draft final outturn report in June. These reports outline the full financial position for each portfolio and are reported to POCs after they have been considered by Cabinet. In the intervening months an exception report is made to Cabinet outlining any significant variations from the quarterly report. The first exception report for 2009/10 is being presented to Cabinet on 13th July, extracts of which are highlighted below.

3. Revenue

3.1At this early stage in the year we have identified the following variations, totalling £776,000, from the revenue budget approved by County Council on 19th February, both within the Communities Portfolio:

3.1.1 £0.533m KEY Training – this is made up as follows:

• +£0.211m: the net deficit on KEY in 2008-09 was £0.454m, after drawing down £0.131m of available reserves (gross deficit - £0.585m). This deficit has been offset by £0.243m of underspends in 2008-09 elsewhere within the portfolio, giving an aggregated roll forward deficit on KEY of £0.211m (if approved by Cabinet). • -£0.145m: part of the 2008-09 deficit was as a result of a mid-year change in payment profiles from the LSC for funding for Entry to Employment. This funding was earned during 2008-09 and payment will be received by July 2009 and is therefore not reported as a recurring pressure.

• +£0.440m: the reduction in LSC contracts in 2008-09 is a base pressure and will have a similar impact in 2009-10. The gross deficit in 2008-09 was £0.585m but we are expecting to receive £0.145m of Entry to Employment grant by July 2009 (see above), as this was purely a timing difference, therefore the underlying base pressure is £0.440m.

• +£0.027m: the most current indication from the LSC of maximum contract values for 2009-10 shows a further reduction of £0.027m.

Management Action:

This pressure cannot be managed within KEY in the current financial year without service delivery being adversely affected so a two year management action plan has been implemented, however Communities as a whole will endeavor to deliver a balanced budget in 09-10.

At the end of the two year management action the service should deliver a small surplus each year, which can be set aside in reserves in order to help manage income fluctuations in the future.

3.1.2 £0.243m Deferment of 2008-09 expenditure

The 2008-09 underspending elsewhere in the Portfolio has been offset against the KEY deficit and the following deferred projects and pressures arise:

• +£0.036m Kent Volunteers Towards 2010 target to support volunteer organizations, whose aim is to enhance volunteering in Kent

• +£0.060m Dover Big Screen additional unanticipated costs, including highways, legal, piling and archaeological fees, which would delay the unveiling if not met

• +£0.039m deferred funding from 2008-09 in relation to Folkestone Forward project

• +£0.108m Contribution toward Church Street dilapidation costs. These are currently estimated at £0.3m for remediation of both the internal and external areas, with the dilapidation works currently out to tender. Negotiations are ongoing with the previous tenants and stakeholders regarding liability for funding these works. Management Action:

A management action plan is in the process of being devised to mitigate the £0.243m pressure. This will be put forward in the next monitoring report to Cabinet in September.

4. Capital

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2009/10 Budget Monitoring Exception ReportReport 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 25 attended
ET
Elizabeth TweedChairman, present
AC
Alan ChellCommittee Member, present
IC
Ian ChittendenCommittee Member, present
HC
Harold CraskeCommittee Member, present
DH
David HirstCommittee Member, present
JL
Jean LawCommittee Member, present
JO
Jan OzogCommittee Member, present
KS
Kit SmithCommittee Member, apologies
RT
Roland TolputtCommittee Member, present
CW
Chris WellsCommittee Member, present
AW
Andrew WickhamCommittee Member, present
AW
Alan WillicombeCommittee Member, present

All 25 on the meeting page

On this subject at Kent

Search all
  1. 2009/10 Budget Monitoring Exception ReportThis decision
  2. 26/00055 - Revenue and Capital Budget Monitoring Report - Q1 2026-27Agreed
  3. 25/00077 - Revenue and Capital Budget Monitoring Report - Quarter 1 2025-26Agreed
  4. Revenue and Capital Budget Monitoring Report – November 2024-25Noted
  5. Revenue and Capital Budget Monitoring Report – Outturn 2023-24Noted
  6. 24/00021 - Revenue and Capital Budget Monitoring Report - December 2023-2024 (Q3)Agreed

More from Kent Communities Policy Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
5 Apr 2011 Minutes - 11 January 2011RESOLVED that the minutes of the meeting held on 11 January 2011 are correctly recorded and that they signed by the C... Decided Open
5 Apr 2011 KCC's Performance Management FrameworkRESOLVED that the approach being taken to provide a clear performance management framework for the authority be noted. Noted Open
5 Apr 2011 Core MonitoringRESOLVED that the report be noted. Noted Open
5 Apr 2011 Edenbridge updateIt was agreed that an update on the scheme would be submitted to the Committee in due course. (3) Reference was made ... Agreed Open
5 Apr 2011 Introduction to the Customer and Communities DirectorateRESOLVED that the report and presentation be noted. Noted Open