Proposal SE/09/1028 - Retention of a single storey modular building and installation of a new modular building and link corridor at Milestone School, Ash Road, New Ash Green; KCC Children, Families and Education
DecidedPlanning1 paper
Planning Applications Committee decided this item on Tuesday 14 July 2009. Below is the council's own wording, with the papers it was decided on.
RESOLVED that:- (a) permission be granted to the proposal subject to conditions, including the buildings being removed and the site restored within 5 years of the grant of planning permission; and the additional modular unit matching the existing building in colour, style and finish; and (b) the applicant be advised by Informative that the mobile classrooms have been granted temporary permission on Green Belt land on the basis of very special circumstances which outweigh any potential harm, and on the understanding that the post 16 facilities will be provided off site in the future.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Planning Applications Committee, 10 pages
Background
2. Milestone School is designated for children with Special Educational Needs, and includes those with Profound and Multiple Learning Difficulties. The children range in age from 2 to 19 years old and the school is divided into Key Stage 1 and 2, Key Stage 3 and 4, and Further Education departments. In total, Milestone School provides 223 full-time school places.
3. The modular building that exists on site was granted temporary planning permission in 2005, and expires on 30 June 2010. That planning application was to provide temporary accommodation for the Further Education (post 16) department, whilst alternative, permanent facilities were incorporated in a proposed development at Axton Chase School. The education for post-16 Special Educational Needs pupils within the areas of Gravesend, Dartford, Swanley, Sevenoaks and Tonbridge areas, takes place within these facilities at Milestone School.
4. Recent developments on site include a large extension to the school buildings to provide additional Key Stage 1 and 2 accommodation, an extension to the car park and the provision of a new play area. In 2008, two mobile classrooms were granted temporary planning permission to be sited on the school playing fields, for use during extension works at the school. However, these buildings were not installed on site and the permission has since expired.
D7.1 Item D7 Retention of existing single storey modular building and provision of new modular building – SE/09/1028
Metropolitan Green Belt Land
D7.2 Item D7 Retention of existing single storey modular building and provision of new modular building – SE/09/1028
D7.3 Item D7 Retention of existing single storey modular building and provision of new modular building – SE/09/1028
D7.4 Item D7 Retention of existing single storey modular building and provision of new modular building – SE/09/1028
Proposal
5. This application proposes the retention of the modular building granted temporary permission in 2005, and the siting of an additional, identical modular building adjacent to the original. The two buildings are proposed to be attached by a link corridor which incorporates toilets and a storeroom. The existing modular building is located between the Teacher Learning Centre and the tennis courts. The additional building is proposed to be sited on the grass area between the existing modular building and the tennis courts.
6. The modular classrooms are to provide accommodation for post 16 year old pupils who currently attend Milestone School. The long term intention is for post 16 pupils to be sited away from the Milestone campus, integrated into a main stream Further Education College.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Proposal SE/09/1028: Retention of a single storey modular building and installation of a new modular building and link corridor at Milestone School, Ash Road, New Ash Green; KCC Children, Families and EducationReport
51Proposal SE/09/1028 - Retention of a single storey modular building and installation of a new modular building and link corridor at Milestone School, Ash Road, New Ash Green; KCC Children, Families and EducationThis decision
Proposal SE/09/1028 - Retention of a single storey modular building and installation of a new modular building and link corridor at Milestone School, Ash Road, New Ash Green; KCC Children, Families and EducationThis decision
Minutes of the Meeting Held on 17.6.2026RESOLVED that the minutes of the meeting held on 17 June 2026 were correctly recorded and that they be signed by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.