Resolved
RESOLVED that the Cabinet Member for Environment, Highways & Waste be recommended to approve the proposed changes to the Section 38 Model Agreement outlined in paragraph (4) above.
Environment, Highways and Waste Policy Overview and Scrutiny Committee approved this item on Thursday 16 July 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Cabinet Member for Environment, Highways & Waste be recommended to approve the proposed changes to the Section 38 Model Agreement outlined in paragraph (4) above.
The Committee’s approval is sought to request the Cabinet Member for Environment, Highways and Waste to approve the proposed changes to the Section 38 Model Agreement outlined in section 7 of this report.
1. Introduction
1.1A Report was considered by this Committee on 6th November 2008 which described the backlog in the adoption of newly constructed streets under Section 38 of the Highways Act 1980. This Report sets out how most of these cases have now been resolved and the roads adopted.
1.2Under a “Section 38 Agreement”, developers design and construct the streets in accordance with KCC’s guidance and standards. All stages are audit-checked by KCC such that upon satisfactory completion of all relevant works and legal processes the streets become maintainable at the public expense.
2. Adoption Problems
2.1Not all Section 38 Agreements run smoothly. Inadequate standards of construction and land ownership complications are among the reasons why some streets are not adopted in good time. The failure of developers to complete remedial works, confirm drainage easements and transfer land can make adoption inappropriate. Occasionally, developers have gone into liquidation, leaving no reasonable means by which the Agreements can be seen through to completion.
2.2All Section 38 Agreements include a bond, or equivalent, through which funds for KCC to see the works through to completion can be called upon in the event of the developer defaulting. Unfortunately, for older schemes the bond situation is not always straightforward and can become a lengthy and resource intensive process. 3. The Cold Case project
3.1A significant number of Section 38 Agreements dating back over many years remained unadopted across the County. These schemes were started during the “Agency Agreement” and “Kent Highways Partnership” periods when many of KCC’s highway functions, including highway adoptions, were carried out by the District Council’s Highway Units. The formation of Kent Highway Services (KHS) in April 2005 brought all of these functions under KCC’s direct control.
3.2The outstanding schemes have been called “Cold Cases”. Phase 1 of the project has concentrated on 175 schemes that started before 2002 (information available on display). The project was initiated in Spring 2008 with the aim of dealing with these schemes by the end of March 2009.
3.3Unfortunately, the quantity and quality of historical information relating to the Cold Cases is variable. Phase 1 has therefore been particularly challenging, but we have laid a firm foundation for the next phase by clearing a substantial proportion of the schemes and establishing a robust method which can be used for tackling the remaining outstanding schemes, as well as learning lessons that will make KHS more efficient in its approach to post KHS agreements. Phase 2 will deal with all outstanding schemes between 2002-2005 (information available on display).
4. Project methods
4.1A composite schedule of the pre-2002 incomplete Section 38 Agreement schemes was compiled from records which enabled research, review and investigation. It included some historical information, including legal positions and engineers’ notes. The schedule has been used to maintain control and keep a record of progress, correspondence, site visits, telephone conversations and meetings. They are accessible to all relevant parties.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Adoptions: Cold Case ProjectReport | 5 pages | DownloadRead as text |
Follow Environment, Highways and Waste Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2012 | Minutes - 12 January 2012RESOLVED that the Minutes of the meeting held on 12 January 2012 are correctly recorded and that they be signed by th... | Decided | Open |
| 14 Mar 2012 | Cabinet Member's Update (Oral Report)RESOLVED that the updates be noted and a copy circulated to Members of the Committee. | Noted | Open |
| 14 Mar 2012 | Financial Monitoring Report 2011/2012RESOLVED that the budget variations for the EHW Portfolio for 2011/12 based on the January full monitoring report to ... | Noted | Open |
| 14 Mar 2012 | KCC Quarterly Performance Report, Quarter 3, 2011/12 including mid year Business Plan monitoringRESOLVED that the report be noted. | Noted | Open |
| 14 Mar 2012 | Bus Services to Tunbridge Wells Hospital at PemburyRESOLVED that the current position with regards to Bus Services to the new Tunbridge Wells hospital, be noted | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.