Resolved
RESOLVED that progress on the be noted .
Communities Policy Overview and Scrutiny Committee noted this item on Wednesday 11 November 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that progress on the be noted .
1.1The Kent Library and History Centre will provide a centre of excellence for the archive service, replacing the current centres at Centre for Kentish Studies, Sessions House and East Kent Archives, Whitfield. The existing archive buildings have inadequate and unsuitable storage facilities for the documents and artefacts which cover over 1000 years of the county’s administrative, economic and social history. The public facilities are intimidating and old-fashioned and have inadequate space to cope with the rapidly growing interest in family and local history.
1.2The centre will also replace the existing libraries at Springfield and Maidstone, both of which have significant access and maintenance issues, resulting in a centre of excellence for library services in Maidstone.
1.3Bouygues UK were appointed as preferred contractor for the development of the Library and History Centre in December 2007, with a proposal to build the Library and History centre on James Whatman Way together with an enabling development of apartments on the same site.
1.4Since the original appointment the residential property market and the general economy have both suffered a serious downturn and the anticipated receipts from the enabling development have been considerably reduced. This has led to a revision of the enabling development and a delay to progress of the scheme. A revised timeline is included in this document.
2. Policy Context
2.1The Library and History Centre project was initially reported to POC in June 2008 when the first designs were launched for public consultation. A paper on the related vision for the archives service was presented to POC in November 2008.
2.2Libraries and Archives leads on Target 26 of Towards 2010: ‘Modernise the library service to act as a focal point for KCC services and widen access to Kent’s rich culture’. The Library History Centre development contributes to the achievement of that target as it will provide a centre of excellence for both the archive service in Kent and a modern hub library for Maidstone, aiding the further integration of the library and archive services.
2.3The centre will provide greater access to Kent’s historical resources through a fully DDA accessible building, state of the art document search room and Community History areas. It will also provide access to both original documents and digital facsimiles. In addition the centre will have a robust digitisation programme that will widen access to documents through electronic means and enable the dissemination of digitised copies through the network of libraries and Community Archives across the county.
2.4The service is also actively engaged with Kent Agreement 2 (KA2) themes and is supporting a large number of those targets, many of which will benefit from the widening of access to local and family history material. History has the power to change lives and can contribute significantly to targets in education, community cohesion and the health agenda in particular and the Library and Archive service is already engaged in some innovative cross-agency projects in these areas.
3. Process
3.1KCC officers have been working with the preferred developer Bouygues UK and their architects, Astudio, over the last eighteen months to refine the design of the centre and to finalise the details of the enabling developments on James Whatman Way and Springfield.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Kent History CentreReport | 4 pages | DownloadRead as text |
Follow Communities Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2011 | Minutes - 11 January 2011RESOLVED that the minutes of the meeting held on 11 January 2011 are correctly recorded and that they signed by the C... | Decided | Open |
| 5 Apr 2011 | KCC's Performance Management FrameworkRESOLVED that the approach being taken to provide a clear performance management framework for the authority be noted. | Noted | Open |
| 5 Apr 2011 | Core MonitoringRESOLVED that the report be noted. | Noted | Open |
| 5 Apr 2011 | Edenbridge updateIt was agreed that an update on the scheme would be submitted to the Committee in due course. (3) Reference was made ... | Agreed | Open |
| 5 Apr 2011 | Introduction to the Customer and Communities DirectorateRESOLVED that the report and presentation be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.