RESOLVED that the budget variations for the EHW Portfolio for 2009/10 based on the March report to Cabinet be noted.
Environment, Highways and Waste Policy Overview and Scrutiny Committee noted this item on Thursday 25 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the budget variations for the EHW Portfolio for 2009/10 based on the March report to Cabinet be noted.
2.1A detailed quarterly budget monitoring report is presented to Cabinet, usually in September, December and March, and a draft final outturn report in June. These reports outline the full financial position for each portfolio and are reported to POSCs after they have been considered by Cabinet. In the intervening months an exception report is made to Cabinet outlining any significant variations from the quarterly report. The detailed quarterly report for March cabinet is attached.
3. Revenue
3.1There are no significant variances to report on the revenue budget since the report was written. The major elements of this predicted outturn remain a significant underspend on Waste offset by additional spending required on Highways.
4. Capital
4.1Since the report was written there has been some slippage on the energy and water investment fund.
5.1Members of the POSC are asked to note the budget variations for the EHW Portfolio for 2009/10 based on the March report to Cabinet.
Richard Hallett, Head of Finance and Resources 01622 69 4035 ENVIRONMENT, HIGHWAYS & WASTE DIRECTORATE JANUARY 2009-10 FULL MONITORING REPORT 1.1 REVENUE 1.1.1 All changes to cash limits are in accordance with the virement rules contained within the constitution, with the exception of those cash limit adjustments which are considered “technical adjustments” i.e. where there is no change in policy, including: § Allocation of grants and previously unallocated budgets where further information regarding allocations and spending plans has become available since the budget setting process. § The inclusion of new 100% grants (i.e. grants which fully fund the additional costs) awarded since the last full monitoring report. These are detailed in Appendix 2 of the executive summary. 1.1.2 Table 1 below details the revenue position by Service Unit:
Budget Book Heading Cash Limit Variance Comment G I N G I N £'000s £'000s £'000s £'000s £'000s £'000s Environment, Highways & Waste portfolio Signs & lines +£0.39m, dilapidations +£0.25m, winter weather +£1.4m, Permit Kent Highways Services 59,986 -6,860 53,126 5,181 0 5,181 Scheme +£0.474m, energy +£0.567m and resurfacing +£2.1m Public Transport Contracts 18,273 -2,400 15,873 360 0 360 Freedom Pass
Reduced tonnage -£3.9m, Allington WtE off-line -£1.3m, Waste Management 69,827 -1,973 67,854 -5,230 -156 -5,386 KWP -£0.030m and additional recycling income -£0.156m
-£0.120m rephasing & - £0.065m additional external Environmental Group 9,263 -4,692 4,571 -494 309 -185 income for land use survey. £0.374m reduced spend & income on KDAONB
Strategic Planning 808 808 0 0 0 Planning Applications 1,440 -477 963 0 0 0 Transport Strategy Group 470 470 0 0 0 Strategic Management 850 850 0 0 0 Vacancies -£0.21m, re- Resources 5,660 -159 5,501 -615 0 -615 phasing of MIDAS replacement -£0.405m Support Services purchased from 1,871 1,871 0 0 0 CED Total E, H & W 168,448 -16,561 151,887 -798 153 -645
Assumed Management Action
Forecast after Mgmt Action -798 153 -645 1.1.3 Major Reasons for Variance: [provides an explanation of the ‘headings’ in table 2]
Table 2, at the end of this section, details all forecast revenue variances over £100k. Each of these variances is explained further below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Financial Monitoring ReportReport | 16 pages | DownloadRead as text |
Follow Environment, Highways and Waste Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2012 | Minutes - 12 January 2012RESOLVED that the Minutes of the meeting held on 12 January 2012 are correctly recorded and that they be signed by th... | Decided | Open |
| 14 Mar 2012 | Cabinet Member's Update (Oral Report)RESOLVED that the updates be noted and a copy circulated to Members of the Committee. | Noted | Open |
| 14 Mar 2012 | Financial Monitoring Report 2011/2012RESOLVED that the budget variations for the EHW Portfolio for 2011/12 based on the January full monitoring report to ... | Noted | Open |
| 14 Mar 2012 | KCC Quarterly Performance Report, Quarter 3, 2011/12 including mid year Business Plan monitoringRESOLVED that the report be noted. | Noted | Open |
| 14 Mar 2012 | Bus Services to Tunbridge Wells Hospital at PemburyRESOLVED that the current position with regards to Bus Services to the new Tunbridge Wells hospital, be noted | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.