Resolved
(i ) the progress to date be noted and the allocation of an additional £1.5m to this Programme be agreed; and, (ii) the approach to repairs on And B class roads as set out in the Cabinet report be endorsed
Cabinet noted this item on Monday 12 July 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
(i ) the progress to date be noted and the allocation of an additional £1.5m to this Programme be agreed; and, (ii) the approach to repairs on And B class roads as set out in the Cabinet report be endorsed
As part of the response to the unprecedented damage to the roads in Kent following the severe winter, KHS has been working to make all the roads in the county safe (in particular with repairs to potholes) and improve the condition of the carriageway surface. Previous cabinet papers have given updates on the delivery of repairs by the seven companies who were awarded contracts on 12th April to repair all the potholes, and carry out larger patching maintenance work, in the non-principal road network throughout each district with a first time permanent repair. This report (as requested at the 17th May 2010 Cabinet) gives an update on these contracts and also details how other roads are being repaired in relation to the weather damage. External Find and Fix Progress (Non classified roads)
The contractors work on a “find and fix” basis using up to 5 separate gangs (and more in extreme cases) in each district, according to the size of the district. The contractors are able to work up to 7 days a week between 7am and 7pm. Kent Highway Services officers deploy the contractors, giving instructions to ensure the highest priority areas in each district are targeted first, and moving progressively to roads with a lesser volume of repair need. The programme of works is available to all members and members of the public via the KCC website.
The focus is on the county’s non-principal roads, particularly the rural and estate roads which make up 71% of the total of the network. Other work is continuing in parallel, as appropriate and in particular critical safety defects, through the term maintenance contractor, Ringway.
After 10 weeks of the programme (up to 22nd June) some 57,000m2 of repairs (equivalent to almost 46 Olympic size swimming pools) have been completed.
Due to the approach of repairing all defects in a road, rather than simply those that are considered most critical to the safe passage of road users, the amount of patching in each road is almost 6 times greater that we would anticipate undertaking against normal “intervention” criteria. This inevitably means that each road takes longer to repair, however from the positive feedback received, this is clearly an approach that people favour. At the current rate of repair, it is envisaged that the programme will be completed in early autumn.
Building on investment
KHS is planning to increase its programme for surface dressing rural roads over the coming 2 – 3 years, to be financed through re-prioritisation of existing capital maintenance spend. This will ensure that the significant investment made through the find and fix programme is protected over the coming years.
A and B Roads
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Operation Find and Fix: Weather Damage Repairs to RoadsReport | 4 pages | DownloadRead as text |
Follow Cabinet at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Oct 2026 | Minutes of the Meeting held on 22 July 2026RESOLVED that the minutes of the meeting held on 22 July 2026 were approved as a correct record. | Approved | Open |
| 1 Oct 2026 | 26/00055 - Revenue and Capital Budget Monitoring Report - Q1 2026-27It was RESOLVED that Cabinet agreed to: a) NOTE the revenue and ... view the full minutes text for item 153. | Agreed | Open |
| 1 Oct 2026 | Quarterly Performance Report, Q1 2026-2027It was RESOLVED that Cabinet agreed to note the Quarter 1 Performance Report and the actions being taken to address a... | Agreed | Open |
| 22 Jul 2026 | Minutes of the Meeting held on 25 June 2026RESOLVED that the minutes of the meeting on 25 th June 2026 were a correct record and that they be signed by the Chair. | Decided | Open |
| 22 Jul 2026 | 26/00031 - Adoption of the Delivery of Local Government Efficiency (DOLGE) StrategyIt was RESOLVED that Cabinet: (a) Approved and adopted the Delivery of Local Government Efficiency (DOLGE) Strategy ;... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.