CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Kent County Council

S278 Agreements for Developer-Funded Highway Improvements

Agreed Scrutiny 2 papers

Environment, Highways and Waste Policy Overview and Scrutiny Committee agreed this item on Tuesday 14 September 2010. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED that the following recommendations to the Cabinet Member for Environment Highways &Waste be endorsed:- (a) the introduction of a new Model S278 Highways Agreement for use in accordance with the Highways Act 1980 with immediate effect; (b) the change to the existing fixed sum consultancy fee for transportation advice on new S278 highway works, as set out in the report; (c) implementing a percentage-based fee structure for professional costs incurred by Kent Highway Services with respect to new S278 highway works, as set out in the report; and (d) for existing S278 Highways Agreements, the charges for professional costs incurred by Kent Highway Services continuing to be based on actual time, but at an average hourly rate, as set out in the report.
Word for word from the decision Kent published for this meeting. Source: democracy.kent.gov.uk

Follow this further

Built from Kent's papers

What the report saysPro

Report to Environment, Highways and Waste Policy Overview and Scrutiny Committee, 5 pages

By: Nick Chard, Cabinet Member for Environment, Highways & Waste

John Burr, Director of Kent Highway Services

To: Environment, Highways & Waste Policy Overview & Scrutiny Committee - Sept 2010

Subject: S278 Agreements for Developer-Funded Highway Improvements

Classification: Unrestricted

Summary: This paper provides an overview of a new Model Agreement under S278 Highways Act 1980 and requests approval for adopting it and also for a revised charging structure for professional advice, design checks, project management, site inspections and administration. The paper includes responses from developers to a consultation report.

FOR DISCUSSION

1. Introduction 1.1 When a developer obtains planning permission for a development it is often a requirement that he undertakes certain improvements to the existing highway to mitigate the impact of the development on the public road network.

1.2The mechanism used to permit the developer to design and construct works on the highway is Section 278 of the Highways Act 1980. Before any works are carried out the developer must enter into an agreement with the Highway Authority [i.e. KCC] under this section.

1.3The terms and conditions of the current Model S278 Highways Agreement have evolved over the last 20 years and the Agreement needed reviewing to ensure that it is still fit for purpose, reflects current standards or policies and protects the interests of KCC. Officers from Kent Highway Services have reviewed the current document assisted by the Director of Law & Governance and suggested a number of improvements.

1.4The result of the review is a new Model S278 Highways Agreement which incorporates a new charging structure and is now ready for use.

2 The New Model S278 Highways Agreement The changes to the terms and conditions are mainly re-wording and updating. They are generally no more onerous on the Developer or the County Council than past versions of the document. The three major changes are:

2.1Land Transfer. It has been the norm within Kent for the developer to be required to transfer the land under any new highway constructed and dedicated by him. Following the decision in July 2009 on Section 38 works [for new estate roads] that the land transfer need not be a requrement, it is now proposed for the transfer of the land for Section 278 to be optional depending on the particular circumstances of the development.

This will make the processes more efficient and brings Kent into line with the majority of other local highway authorities who do not always require a land transfer.

2.2Kent Permit Scheme. The new Model Agreement includes provisions for the developer to comply with the new Kent Permit Scheme for works on the highway. The effect of this is that there will be better early planning for developer works on the highway which will give the County Council more control over works on the public highway.

The Kent Permit Scheme covers statutory undertakers, developers and our own highway works; it is an innovatory scheme compared to those operated by other County Councils.

2.3Fees and Charges. There are three main elements of the existing charge structure:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item B6: AppendixAppendix 7 pages Download
PDF
S278 Agreements for Developer-Funded Highway ImprovementsReport 5 pages DownloadRead as text

More from Kent Environment, Highways and Waste Policy Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
14 Mar 2012 Minutes - 12 January 2012RESOLVED that the Minutes of the meeting held on 12 January 2012 are correctly recorded and that they be signed by th... Decided Open
14 Mar 2012 Cabinet Member's Update (Oral Report)RESOLVED that the updates be noted and a copy circulated to Members of the Committee. Noted Open
14 Mar 2012 Financial Monitoring Report 2011/2012RESOLVED that the budget variations for the EHW Portfolio for 2011/12 based on the January full monitoring report to ... Noted Open
14 Mar 2012 KCC Quarterly Performance Report, Quarter 3, 2011/12 including mid year Business Plan monitoringRESOLVED that the report be noted. Noted Open
14 Mar 2012 Bus Services to Tunbridge Wells Hospital at PemburyRESOLVED that the current position with regards to Bus Services to the new Tunbridge Wells hospital, be noted Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies