Application GR/09/286 - Bulk aggregates Import Terminal handling up to 3 million tpa and associated infrastructure, including reinstated rail access at Northfleet Works, The Shore, Northfleet; Lafarge Cement UK
AgreedPlanning1 paper
Planning Applications Committee agreed this item on Tuesday 2 November 2010. Below is the council's own wording, with the papers it was decided on.
RESOLVED that permission be granted to the application subject to the prior satisfactory conclusion of a legal agreement to secure the Heads of Terms given in Appendix 3 of the report and to conditions, including conditions covering a 5 year time limit to implement the permission; a maximum of 3 million tonnes per annum of imports; the prior approval of various details (including conveyors, gatehouse / security lodge, weighbridge, parking arrangements, external construction materials and fencing); the prior approval of a Code of Construction Practice (relating to air quality, noise, vibration, geotechnics and soil contamination and waste); crushed rock only being stored outside the enclosed aggregate storage building exceptionally in the event of plant / equipment failure or unless otherwise agreed; protection of Port of London Authority radar equipment; the prior approval of a Tunnels Report (dealing with current condition, repairs / remedial measures, monitoring, maintenance and management of road and rail access tunnels and cliffs above their portals); hours of use (ship, barge and rail arrival, departure, loading and unloading and HGV movements being permitted 24 hours a day 7 days a week with all other activities restricted to between 0700 and 1800 hours Monday to Friday, 0700 and 1300 hours on Saturdays with no working on Saturday afternoons, Sundays, Bank and Public Holidays unless the prior written approval of the County Council has been obtained to depart from these hours); measures to prevent mud and debris on the highway (e.g. sheeting of loaded HGVs ); no more than 1.2 million tonnes of materials being exported by road each year; the implementation of a travel plan; ... view the full minutes text for item 62.
Word for word from the decision Kent published for this meeting.Source: democracy.kent.gov.uk
Report to Planning Applications Committee, 58 pages
Item C3 Application by Lafarge Cement UK for a Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend – GR/09/286
A report by Head of Planning Applications Group to Planning Applications Committee on 2 November 2010.
Application by Lafarge Cement UK for Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend.
Recommendation: Planning permission be granted subject to legal agreement and conditions.
Local Members: [name removed] and [name removed] ([name removed] adjoining) Unrestricted
Site description and background
1. The application site lies within the Northfleet Cement Works site which is located on the south bank of the River Thames in Gravesham (see Figure 1.1 “Site Location” on page C3.2 and the application site plan on page C3.3). Northfleet Works is bounded by the River Thames to the north, the North Kent Railway Line to the south, the Kimberly Clark tissue paper mill to the east and Robins Creek and other industrial and residential development to the west. It is dissected by the B2175 Northfleet High Street which runs east to west on a chalk spine through the area. Tilbury Docks lies immediately opposite the site to the north of the River Thames. Northfleet Works is 42.2 ha in size including land in Vineyard Pit and Church Path Pit (to the south of a chalk spine). A Bulk Powder Import Terminal (GR/05/561) has been constructed in the eastern part of the works site which utilises 42 Wharf. The application site comprises 10.02 ha of the overall works area immediately to the west of the Bulk Powders Import Terminal. The works site is a major element of Northfleet Embankment, a key regeneration opportunity within Kent Thameside and Thames Gateway.
2. Northfleet Works can be split into four general areas:-
• Church Path Pit – a former quarry lying between the B2175 and the North Kent Line accessed by tunnel from the main works site (the western branch of this quarry is known as St. Botolph’s Pit); • Northfleet Works – the current site of the cement works laid out on a level quarry floor between the B2175 and 42 Wharf on the River Thames • The former Bevans Works site – the area to the west of Lawn Road including the main site access and land rising up from the riverfront towards the existing community of Northfleet; (formerly the site of Bevans Cement Works); and • Vineyard Pit – a small quarry on what is the main road access into the works site lying between the B2175 and the North Kent Line.
C3.1 Item C3 Application by Lafarge Cement UK for a Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend – GR/09/286
C3.2 Item C3 Application by Lafarge Cement UK for a Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend – GR/09/286
C3.3 Item C3 Application by Lafarge Cement UK for a Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend – GR/09/286
C3.4 Item C3 Application by Lafarge Cement UK for a Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend – GR/09/286
C3.5 Item C3 Application by Lafarge Cement UK for a Bulk Aggregates Import Terminal handling up to 3 million tonnes per annum and associated infrastructure including reinstated rail access at Northfleet Works, The Shore, Northfleet, Gravesend – GR/09/286
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Application GR/09/286: Bulk aggregates Import Terminal handling up to 3 million tpa and associated infrastructure, including reinstated rail access at Northfleet Works, The Shore, Northfleet; Lafarge Cement UKReport
62Application GR/09/286 - Bulk aggregates Import Terminal handling up to 3 million tpa and associated infrastructure, including reinstated rail access at Northfleet Works, The Shore, Northfleet; Lafarge Cement UKThis decision
Application GR/09/286 - Bulk aggregates Import Terminal handling up to 3 million tpa and associated infrastructure, including reinstated rail access at Northfleet Works, The Shore, Northfleet; Lafarge Cement UKThis decision
Minutes of the Meeting Held on 17.6.2026RESOLVED that the minutes of the meeting held on 17 June 2026 were correctly recorded and that they be signed by the ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.