Resolved
RESOLVED that the information set out in the report and given in response to Members’ comments and questions be noted, with thanks, and the approach being taken in the Integrated Infrastructure and Finance Model be endorsed.
Regeneration and Economic Development Policy Overview and Scrutiny Committee noted this item on Tuesday 18 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the information set out in the report and given in response to Members’ comments and questions be noted, with thanks, and the approach being taken in the Integrated Infrastructure and Finance Model be endorsed.
By: Kevin Lynes, Cabinet Member for Regeneration David Cockburn, Executive Director for Strategy, Economic Development and ICT
To: Regeneration and Economic Development Policy Overview and Scrutiny Committee 18 January 2011
Subject: Supporting Community Infrastructure
Classification: Unrestricted
Summary: In June 2003, KCC published Kent – What Price Growth?, which set out the approximate costs of community infrastructure to support the housing targets set by the former Government. In the Regeneration Framework, we made a commitment to revise What Price Growth? using a more robust and transparent approach to investment requirements and costings and considering more innovative approaches to funding.
This report sets out the progress we have made to date in taking this work forward, particularly through the joint development of an Integrated Infrastructure and Finance Model, by Corporate Finance and Regeneration & Economy. It explains the Model and the timescales for completion; presents the issues relating to future community infrastructure provision and financing in the context of changing Government policy and reductions in public spending; and sets out measures that KCC is taking to address these.
1. Introduction
1.1The original Kent – What Price Growth? (WPG) was produced several years ago in the context of a major expansion of Government expenditure accompanied by a heightened pressure to deliver new housing as part of the former Government's Sustainable Communities Plan. The intention was to set out what the costs to Kent would be of delivering the community infrastructure to support that growth agenda, while at the same time safeguarding quality of life.
1.2The original WPG only sought to make ballpark estimates of strategic requirements and costs. However, it did serve as an important basis in attracting significant public investment under the Sustainable Communities Plan. It also provided a starting point for a more robust and credible assessment of the county's needs and the implications for KCC services. Since the production of WPG, we have in particular:
• Strengthened our joint working with Districts, particularly in the preparation of their Infrastructure Delivery Plans, associated with the Local Development Frameworks; • Worked closely with groups of districts in taking forward Local Investment Plans, highlighting priorities for investment from the Homes and Communities Agency and other bodies; • Sought to maximise development contributions to KCC services (securing some £3.4 million in 2009/10 from sites under 500 units); • Progressed innovative approaches to new community infrastructure provision to reduce overall capital and running costs and provide a better service to the public (for example, the integrated community and education provision at The Bridge in Dartford).
1.3Following this progress and in the context of a sharp reduction in future public sector funding, the 2009 Regeneration Framework committed KCC to a comprehensive revision of What Price Growth? There are three main elements in taking this forward:
• Firstly, developing an infrastructure planning framework for KCC services (CFE, CMY and KASS) for the purposes outlined in this paper;
• Secondly, addressing the ‘gap’ in community infrastructure funding by taking advantage of emerging funding mechanisms and new approaches to service delivery; and
• Thirdly, considering how this approach is integrated with wider infrastructure priorities and requirements.
2. Developing an infrastructure planning framework
2.1In December 2009, we commissioned URS (now URS Scott Wilson) to develop an Integrated Infrastructure and Finance Model (IIFM). This will provide the evidence base for a planning framework for KCC’s community infrastructure provision.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Supporting Community InfrastructureReport | 5 pages | DownloadRead as text |
Follow Regeneration and Economic Development Policy Overview and Scrutiny Committee at Kent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Jan 2012 | Minutes of the meeting held on 16 November 2011RESOLVED that the Minutes of the meeting held on 16 November are correctly recorded and that they be signed by the Ch... | Decided | Open |
| 19 Jan 2012 | Presentations: Professor Peter Gregory, Chief Executive, East Malling ResearchRESOLVED that the Chairman and Members thanked Professor Gregory for attending the meeting and agreed to keep in cont... | Agreed | Open |
| 19 Jan 2012 | Feedback report from RED POSC Rural visitsRESOLVED that the information given in the report and to Members be noted with thanks. | Noted | Open |
| 19 Jan 2012 | The Future of SEEDA's AssetsRESOLVED that the information in the report be noted, with thanks. | Noted | Open |
| 19 Jan 2012 | Thanet - Economic Growth and Development - updateRESOLVED that the information given in the report and to Members be noted, with thanks. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.